Home
Current Affairs January 2024

What is the correct answer?

4

The form work from the sides of beams can be removed only after

A. 1 day

B. 4 days

C. 7 days

D. 14 days

Correct Answer :

A. 1 day


Related Questions

What is the correct answer?

4

The vertical member running through middle of a shutter frame, is

A. Style

B. Reveal

C. Mullion

D. Post

What is the correct answer?

4

Which one of the following rocks is used for monumental buildings?

A. Granite

B. Marble

C. Sand stone

D. Slate

What is the correct answer?

4

Cast iron piles

A. Are suitable for works under sea water

B. Resist shocks or vibrations

C. Are suitable for use as batter piles

D. Are useful for heavy vertical loads

What is the correct answer?

4

The form work from the sides of beams can be removed only after

A. 1 day

B. 4 days

C. 7 days

D. 14 days

What is the correct answer?

4

If (φ) is the angle of repose of soil of weight w kg/m3, the horizontal pressure p at a depth of h metres per metre length of wall, is

A. wh × [(1 - sin φ)/(1 + sin φ)]

B. (wh/2) × [(1 - sin φ)/(1 + sin φ)]

C. wh × √[(1 - sin φ)/(1 + sin φ)]

D. wh × √[(1 + sin φ)/(1 - sin φ)]

What is the correct answer?

4

The piece of a brick cut along the centre of width in such a way that its length is equal to that of full brick, is called

A. Half brick

B. Queen closer

C. King closer

D. Bevelled closer

What is the correct answer?

4

The bond in which headers and stretchers are laid in alternate courses and every stretcher course is started with a three fourth brick bat, is known as

A. English cross bond

B. Dutch bond

C. Monk bond

D. Rat-trap bond

What is the correct answer?

4

In clay soil

A. Swelling and shrinkage characteristics prevail

B. Consolidation continues even after several years of construction

C. Differential settlement is generally prevalent

D. All the above

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. In dog-legged stairs, no space between its flights is provided

B. In open newel stair, a rectangular well is provided

C. In geometric stair, a curved shaped well between forward and backward flights, is provided

D. In geometrical stair, two quarter space landing is provided

What is the correct answer?

4

Black cotton soil is unsuitable for foundations because its

A. Bearing capacity is low

B. Permeability is uncertain

C. Particles are cohesive

D. Property to undergo a volumetric change due to variation of moisture content

What is the correct answer?

4

In soft clay of low bearing capacity, the type of steel pile generally used, is

A. H-pile

B. Screw pile

C. Disc pile

D. Pipe pile

What is the correct answer?

4

Crown is located at

A. Highest point on the extrados of the arch

B. Highest point on the intrados of the arch

C. Skew-back of the arch

D. None of these

What is the correct answer?

4

A pre-stressed concrete pile is

A. Easy to handle

B. Lighter in weight

C. Extremely durable

D. All the above

What is the correct answer?

4

Pick up the correct specification of one-room quarters generally adopted from the following:

A. Six quarters in a row

B. The size of room is either 3.5 m × 3 m or 4.2 m × 2.5 m

C. The front verandah is kept 2 m wide

D. All the above

What is the correct answer?

4

The loose pockets in soil mass can be bridged safely by providing a raft foundation provided the soft area is smaller than

A. The column spacing

B. One-third the column spacing

C. Half the column spacing

D. Three-fourth the column spacing

What is the correct answer?

4

A roof which slopes in four directions, is called

A. Shed roof

B. Gable end roof

C. Hipped roof

D. Gambrel roof

What is the correct answer?

4

The skirting/dado in a bath roof should be upto

A. Ceiling

B. 15 cm above floor level

C. 200 cm

D. Level of the tap

What is the correct answer?

4

The stone blocks approximately triangular in shape, used as steps, are known

A. Stone steps

B. Built up steps

C. Spandril steps

D. None of these

What is the correct answer?

4

The concrete slump recommended for foundations, is

A. 25 to 50 mm

B. 30 to 125 mm

C. 50 to 100 mm

D. 75 to 125 mm

What is the correct answer?

4

The voussoir placed at crown of an arch, is known as a

A. Key

B. Soffit

C. Springer

D. Haunch

What is the correct answer?

4

The minimum depth of foundation in clayey soils is

A. 0.5 m

B. 0.7 m

C. 0.9 m

D. 1.2 m

What is the correct answer?

4

The radial splits which are wider on the outside of the log and narrower towards the pith are known as

A. Heart shakes

B. Cupshakes

C. Starshakes

D. Rindgalls

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The retaining wall should be structurally capable to resist the applied earth pressure

B. The section of the retaining wall should be so proportioned that it may not overturn by the lateral pressure

C. The retaining wall should be safe against sliding

D. To drain off water from the earth retained, weep holes are provided near the top of the retaining wall

What is the correct answer?

4

The opening provided in sloping roof with its top parallel to the roof surface, is called

A. Dormer window

B. Sky light window

C. Lantern window

D. Louvered window

What is the correct answer?

4

The depth of an arch is the distance between

A. Ground level and springing line

B. Crown and springing line

C. Crown and ground level

D. Intrados and extrados

What is the correct answer?

4

The construction joints in buildings are provided after

A. 10 m

B. 15 m

C. 20 m

D. 40 m

What is the correct answer?

4

For each storey of a building, the depth of exploration should be

A. 1 metre

B. 2 metres

C. 3 metres

D. 4 metres

What is the correct answer?

4

Gravels

A. Are cohesionless aggregates

B. Vary in size between 2 to 20 mm

C. Never swell when they come into contact with water

D. All the above

What is the correct answer?

4

Rotary drilling is the fastest method in case of

A. Rocky soils

B. Clay soils

C. Sandy soil

D. All of these

What is the correct answer?

4

For plastering the exposed brick walls, the cement sand mortar should be

A. 1 : 2

B. 1 : 3

C. 1 : 4

D. 1 : 6