Ground level and springing line
Crown and springing line
Crown and ground level
Intrados and extrados
D. Intrados and extrados
h/4
1/2 h
h
2 h
The seismic method
Electrical resistivity method
Gravitational method
Both (a) and (b) of the above
Ground level and springing line
Crown and springing line
Crown and ground level
Intrados and extrados
English bond
Flemish bond
Russian band
Mixed bond
25°
30°
40°
50°
1 day
4 days
7 days
14 days
Louvered door is generally provided in bath rooms
Flush door is generally provided in dining room
Revolving door is generally provided in cinema halls
Sliding door is generally provided in show rooms
Horizontal D.P.C. is provided at plinth level in internal walls
D.P.C. is provided under door and verandah openings
Vertical D.P.C. is not provided in internal walls
Cement concrete is a rigid damp-proofing material
Ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole
Caving or mixing of strata are caused in soft soils or cohesionless soils
The soil to a considerable depth below the bottom of the hole gets disturbed
All the above
Laying bricks as stretchers in cement mortar
Laying bricks as headers in cement mortar
Reinforcing brick wall with iron straps
Constructing brick work within a wooden framework
25 mm
40 mm
65 mm
100 mm
Increase the depth of foundation
Drain the soil
Compact the soil
Replace the poor soil
In soils that require lateral support
In cohesive soils
In soft soils
None of the above
English bond
Flemish bond
Header bond
Stretcher bond
Lengths vary from 6 m to 12 m
Diameter of top of piles varies from 40 cm to 60 cm
Diameter of pile at bottom varies from 20 cm to 28 cm
All the above
Retaining wall
Breast wall
Buttress
Parapet wall
Two directions without break in the slope on each side
Two directions with break in the slope on each side
Four directions without break in the slope on each side
Four directions with break in the slope on each side
Cork flooring
Glass flooring
Wooden flooring
Linoleum flooring
Flemish bond
English bond
Stretcher bond
Header bond
Cornice
Coping
Frieze
Lintel
Ridge
Hip
Valley
None of these
Rafter
Ridge
Crown
Eave
Upper horizontal wooden member
Lower horizontal wooden member
Intermediate horizontal wooden member
Vertical wooden member
Looking through the well in the vicinity
Standing on the well in the vicinity
Measuring the depth of water in the well
None of the above
The column spacing
One-third the column spacing
Half the column spacing
Three-fourth the column spacing
350
420
450
500
Random rubble masonry
Course rubble masonry
Uncoursed rubble masonry
Ashlar masonry
Walls having thickness more than 4 bricks
Architectural finish to the face work
Ornamental panels in brick flooring
All the above
2
3
5
No limit
Centring
Actual laying of arch work
Striking of centring
None of the above