Start float and finish float are always equal.
Total float can be either start float or finish float.
Start float and finish float need not be equal.
Start float and finish float are the differences between activity times and not event times.
C. Start float and finish float need not be equal.
Maximum float
Minimum float
Zero float
None of these
Unity of command
Effective control at all levels
Delegation of authority
All the above
19
14
24
None of these
(a + m + b)/6
(a + 2m + b)/6
(a + 4m + b)/6
(a + 5m + b)/6
1, 3 and 4 are correct
2, 3 and 4 are correct
1, 2 and 3 are correct
1, 2 and 4 are correct
Is artificially introduced
Is represented by a dotted line
Does not consume time
All the above
(i), (ii) and (iv) are correct
(ii), (iii) and (iv) are correct
(i), (iii) and (iv) are correct
(i), (ii) and (iii) are correct
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
Programme Evaluation and Review Technique, is event oriented
Programme Evaluation and Review Technique is not event oriented
Critical Path Method is event oriented
Critical Path method is event oriented
1
2
3
4
Small projects
Large and complex projects
Research and development projects
Deterministic activities
The difference of latest occurrence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above
The float may be positive, zero or negative
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
If the float of an activity is negative, delay in its performance is bound to delay the completion of project
All the above
2.3% and 84.1%
97.7% and 84.1%
97.7 % and 15.9%
15.9% and 97.7%
Minimum time
Maximum time
Maximum cost
Minimum cost
The detailed estimated cost based on detailed design
The several alternatives of the project that have been considered
The soil survey, traffic survey, concept design and approximate cost
The contract documents for inviting tenders
Measurement of risks to eliminate failures
Applying the theory' of probability to sample testing or inspection
Reduction in wastage of inspection costs
Reduction in costs for the removal of defects
A person
A firm
An agency
All the above
Any project
Major projects
Minor projects
All the above
Interdependencies of activities
Project progress
Uncertainties
All of the above
The activity is the time consuming part of a project
The beginning and end of a job, are called events
The activity which consumes maximum time, is called a node
Logically and sequentially connected activities and events form a network
Rs. 31050
Rs. 34500
Rs. 37950
Rs. 50000
Controlling the total quantity at each batch
Weighing accurately, the quantity of each material for a job before mixing
Controlling the quantity of each material into each batch
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
1, 2, 4, 3, 5
1, 3, 2, 4, 5
1, 2, 3, 4, 5
1, 3, 4, 2, 5
Event
Node
Connector
All the above
Strict adherence to specifications
Separation of planning and design part
Each individual maintains functional efficiency
All the above
Start float and finish float are always equal.
Total float can be either start float or finish float.
Start float and finish float need not be equal.
Start float and finish float are the differences between activity times and not event times.
Normal distribution curve
Poisson's distribution curve
Beta distribution curve
None of the above
Optimistic time estimate refers to activities
Pessimistic time estimate refers to activities
Most likely time estimate refers to activities
All the above
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications