Home
Current Affairs January 2024

What is the correct answer?

4

Select the incorrect statement.

A. Start float and finish float are always equal.

B. Total float can be either start float or finish float.

C. Start float and finish float need not be equal.

D. Start float and finish float are the differences between activity times and not event times.

Correct Answer :

C. Start float and finish float need not be equal.


Related Questions

What is the correct answer?

4

The critical activity has

A. Maximum float

B. Minimum float

C. Zero float

D. None of these

What is the correct answer?

4

The main principle of an organisation, is

A. Unity of command

B. Effective control at all levels

C. Delegation of authority

D. All the above

What is the correct answer?

4

The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is

A. 19

B. 14

C. 24

D. None of these

What is the correct answer?

4

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

A. (a + m + b)/6

B. (a + 2m + b)/6

C. (a + 4m + b)/6

D. (a + 5m + b)/6

What is the correct answer?

4

Consider the following statements: Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control. Of these statements

A. 1, 3 and 4 are correct

B. 2, 3 and 4 are correct

C. 1, 2 and 3 are correct

D. 1, 2 and 4 are correct

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not consume time

D. All the above

What is the correct answer?

4

The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack Of these statements

A. (i), (ii) and (iv) are correct

B. (ii), (iii) and (iv) are correct

C. (i), (iii) and (iv) are correct

D. (i), (ii) and (iii) are correct

What is the correct answer?

4

Mobilization advance up to 10% of the cost of work is given to a contractor

A. On commencement of work at site for payment of loan taken by him

B. For the purchase of construction materials

C. For the payment of advances to labour and other staff

D. For all activities required to start the work at site on finalization of the contract document

What is the correct answer?

4

Pick up the correct statement from the following:

A. Programme Evaluation and Review Technique, is event oriented

B. Programme Evaluation and Review Technique is not event oriented

C. Critical Path Method is event oriented

D. Critical Path method is event oriented

What is the correct answer?

4

For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

A. 1

B. 2

C. 3

D. 4

What is the correct answer?

4

PERT technique of network analysis is mainly useful for

A. Small projects

B. Large and complex projects

C. Research and development projects

D. Deterministic activities

What is the correct answer?

4

Pick up the correct statement from the following:

A. The difference of latest occurrence time and earliest expected time, is called slack

B. The activities connecting the events having zero slack, lie on the critical path

C. The critical path consumes the maximum time

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. The float may be positive, zero or negative

B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed

C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

D. All the above

What is the correct answer?

4

If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be

A. 2.3% and 84.1%

B. 97.7% and 84.1%

C. 97.7 % and 15.9%

D. 15.9% and 97.7%

What is the correct answer?

4

For completion of a project, the critical path of the network represents

A. Minimum time

B. Maximum time

C. Maximum cost

D. Minimum cost

What is the correct answer?

4

Preliminary project report for a road project must contain

A. The detailed estimated cost based on detailed design

B. The several alternatives of the project that have been considered

C. The soil survey, traffic survey, concept design and approximate cost

D. The contract documents for inviting tenders

What is the correct answer?

4

At a work site, statistical quality control of concrete means

A. Measurement of risks to eliminate failures

B. Applying the theory' of probability to sample testing or inspection

C. Reduction in wastage of inspection costs

D. Reduction in costs for the removal of defects

What is the correct answer?

4

For the execution of a project, a contractor is

A. A person

B. A firm

C. An agency

D. All the above

What is the correct answer?

4

Works costing less than Rs. 20,000 are treated as

A. Any project

B. Major projects

C. Minor projects

D. All the above

What is the correct answer?

4

Which of the following is a weakness of bar chart?

A. Interdependencies of activities

B. Project progress

C. Uncertainties

D. All of the above

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The activity is the time consuming part of a project

B. The beginning and end of a job, are called events

C. The activity which consumes maximum time, is called a node

D. Logically and sequentially connected activities and events form a network

What is the correct answer?

4

An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

A. Rs. 31050

B. Rs. 34500

C. Rs. 37950

D. Rs. 50000

What is the correct answer?

4

Batching refers to

A. Controlling the total quantity at each batch

B. Weighing accurately, the quantity of each material for a job before mixing

C. Controlling the quantity of each material into each batch

D. Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch

What is the correct answer?

4

Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is

A. 1, 2, 4, 3, 5

B. 1, 3, 2, 4, 5

C. 1, 2, 3, 4, 5

D. 1, 3, 4, 2, 5

What is the correct answer?

4

Completion of an activity on CPM network diagram, is generally known

A. Event

B. Node

C. Connector

D. All the above

What is the correct answer?

4

The salient feature of functional organisation is

A. Strict adherence to specifications

B. Separation of planning and design part

C. Each individual maintains functional efficiency

D. All the above

What is the correct answer?

4

Select the incorrect statement.

A. Start float and finish float are always equal.

B. Total float can be either start float or finish float.

C. Start float and finish float need not be equal.

D. Start float and finish float are the differences between activity times and not event times.

What is the correct answer?

4

In PERT analysis, the time estimates of activities and probability of their occurrence follow

A. Normal distribution curve

B. Poisson's distribution curve

C. Beta distribution curve

D. None of the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. Optimistic time estimate refers to activities

B. Pessimistic time estimate refers to activities

C. Most likely time estimate refers to activities

D. All the above

What is the correct answer?

4

Sinking fund is

A. The fund for rebuilding a structure when its economic life is over

B. Raised to meet maintenance costs

C. The total sum to be paid to the municipal authorities by the tenants

D. A part of the money kept in reserve for providing additional structures and structural modifications