Home
Current Affairs January 2024

What is the correct answer?

4

Pick up the correct statement from the following:

A. The difference of latest occurrence time and earliest expected time, is called slack

B. The activities connecting the events having zero slack, lie on the critical path

C. The critical path consumes the maximum time

D. All the above

Correct Answer :

D. All the above


Related Questions

What is the correct answer?

4

Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?

A. Concrete

B. Loose sand

C. Asphalt

D. Firm earth

What is the correct answer?

4

The main principle of an organisation, is

A. Unity of command

B. Effective control at all levels

C. Delegation of authority

D. All the above

What is the correct answer?

4

Mile Stone charts were invented in the year of

A. 1910

B. 1920

C. 1930

D. 1940

What is the correct answer?

4

If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be

A. 50 %

B. Less than 50 %

C. More than 50 %

D. 100 %

What is the correct answer?

4

Preliminary project report for a road project must contain

A. The detailed estimated cost based on detailed design

B. The several alternatives of the project that have been considered

C. The soil survey, traffic survey, concept design and approximate cost

D. The contract documents for inviting tenders

What is the correct answer?

4

The difference between the time avail-to do a job and the time required to do the job, is known as

A. Event

B. Float

C. Duration

D. Constraint

What is the correct answer?

4

Pick up the correct statement from the following:

A. CPM analysis is activity oriented

B. PERT analysis is event oriented

C. In CPM, the time is related to cost

D. All the above

What is the correct answer?

4

Select the incorrect statement.

A. Start float and finish float are always equal.

B. Total float can be either start float or finish float.

C. Start float and finish float need not be equal.

D. Start float and finish float are the differences between activity times and not event times.

What is the correct answer?

4

If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is

A. 30 kg

B. 300 kg

C. 900 kg

D. 1000 kg

What is the correct answer?

4

While scheduling a project by C.P.M.

A. A project is divided into various activities

B. Required time for each activity is established

C. Net work is drawn by connecting the activities and the events

D. All the above

What is the correct answer?

4

A critical ratio scheduling

A. Determines the status of each activity

B. Adjusts automatically changes in activity progress

C. Is a dynamic system

D. None of these

What is the correct answer?

4

Time and progress chart of a construction, is also known as

A. Bar chart

B. Gantt chart

C. Modified Mile stone chart

D. All the above

What is the correct answer?

4

Mobilization advance up to 10% of the cost of work is given to a contractor

A. On commencement of work at site for payment of loan taken by him

B. For the purchase of construction materials

C. For the payment of advances to labour and other staff

D. For all activities required to start the work at site on finalization of the contract document

What is the correct answer?

4

Grader is used mainly for

A. Trimming and finishing

B. Shaping and trimming

C. Finishing and shaping

D. Finishing, shaping and trimming

What is the correct answer?

4

The constraints in case of resource smoothening operation would be

A. Resources

B. Project duration time

C. Both resources and project duration time

D. None of the above

What is the correct answer?

4

Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.

A. A is correct but R is not correct

B. R is correct but A is not correct

C. Both A and R is correct

D. Both A and R is incorrect

What is the correct answer?

4

Pick up the correct statement from the following:

A. The float may be positive, zero or negative

B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed

C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

D. All the above

What is the correct answer?

4

PERT is

A. An analytic in concept

B. Limited of event oriented diagrams

C. Used for research and development projects

D. All the above

What is the correct answer?

4

The performance of a specific task in CPM, is known

A. Dummy

B. Event

C. Activity

D. Contract

What is the correct answer?

4

A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be

A. 20 kg/tonne

B. 30 kg/tonne

C. 40 kg/tonne

D. 50 kg/tonne

What is the correct answer?

4

Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

A. 20

B. 25

C. 35

D. 15

What is the correct answer?

4

Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is

A. 1, 2, 4, 3, 5

B. 1, 3, 2, 4, 5

C. 1, 2, 3, 4, 5

D. 1, 3, 4, 2, 5

What is the correct answer?

4

Frequency distribution curves

A. Having a single lump, are called uninodal curves

B. If symmetrical, are called normal curves

C. If not symmetrical, are called skew curves

D. All the above

What is the correct answer?

4

Modular co-ordination of construction means proper

A. Planning

B. Designing

C. Execution

D. All the above

What is the correct answer?

4

If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is

A. (t1 - t2) - t

B. t - (t1 - t2)

C. (t1 + t2) - t

D. t + (t1 - t2)

What is the correct answer?

4

The object of technical planning, is

A. Preparation of specifications

B. Preparation of estimates

C. Initiating the procurement action of resources

D. All the above

What is the correct answer?

4

The salient feature of functional organisation is

A. Strict adherence to specifications

B. Separation of planning and design part

C. Each individual maintains functional efficiency

D. All the above

What is the correct answer?

4

Site order book is used for recording

A. Instructions by the executive engineers

B. Construction measurements

C. Issue of store equipments

D. Names of the casual labour

What is the correct answer?

4

A CPM family includes

A. CPA (Critical Path Analysis)

B. CPP (Critical Path Plotted)

C. MCE (Minimum Cost Expenditure)

D. All the above

What is the correct answer?

4

Works costing less than Rs. 20,000 are treated as

A. Any project

B. Major projects

C. Minor projects

D. All the above