CPM analysis is activity oriented
PERT analysis is event oriented
In CPM, the time is related to cost
All the above
D. All the above
Trimming and finishing
Shaping and trimming
Finishing and shaping
Finishing, shaping and trimming
Normal distribution curve
Poisson's distribution curve
Beta distribution curve
None of the above
Line organisation
Line and staff organisation
Functional organisation
None of these
Event
Free float
Dummy
Constraint
Site investigation started
Sessional work completed
Bus starts from Jaipur
Class is being attended
Emphasis is given to activities
Uncertainties are not allowed
Activities are represented by arrows
All the above
Comparison of profit and loss
Comparison of assets and liabilities
Change in output due to change in input
Economics of cost and benefits of the project
A person
A firm
An agency
All the above
Unity of command
Effective control at all levels
Delegation of authority
All the above
The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
The difference between the maximum time available for the job and actual time it consumes, is called total float
The difference between the latest start time and earliest start time of an activity, is called total float
None of these
3.5 and 5/6
5 and 25/36
3.5 and 25/36
4 and 5/6
Moist loam
Good common earth
Well blasted rock
Wet sticky clay
Number of operations
Output of labour
Output of machinery
All the above
Most likely time
Optimistic time
Pessimistic time
Expected time
Kneading
Pressing
Tamping
Vibration
Forward pass is used for calculating earliest expected time
Backward pass is used for calculating the latest occurrence time
Maximum value of earliest expected time is used if there is more than one value of any event
All the above
Start float and finish float are always equal.
Total float can be either start float or finish float.
Start float and finish float need not be equal.
Start float and finish float are the differences between activity times and not event times.
20
25
35
15
Strict adherence to specifications
Separation of planning and design part
Each individual maintains functional efficiency
All the above
Total float
Free float
Interfering float
Independent float
The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
The difference between total float and free float, is called interfering float
All the above
Total float and free float
Total float and independent float
Free float and independent float
None of the above
Event flow scheduling technique
Critical ratio scheduling
Slotting technique for scheduling
Short interval scheduling
Earliest expected time is denoted by TE
Latest occurrence time is denoted by TL
Contractual obligation time is denoted by Ts
All the above
(i), (ii) and (iv) are correct
(ii), (iii) and (iv) are correct
(i), (iii) and (iv) are correct
(i), (ii) and (iii) are correct
A is correct but R is not correct
R is correct but A is not correct
Both A and R is correct
Both A and R is incorrect
Controlling the total quantity at each batch
Weighing accurately, the quantity of each material for a job before mixing
Controlling the quantity of each material into each batch
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Both A and R is true and R is the correct explanation of A
Both A and R is true but R is not the correct explanation of A
A is true but R is false
A is false but R is true
1, 2, 4, 3, 5
1, 3, 2, 4, 5
1, 2, 3, 4, 5
1, 3, 4, 2, 5
1, 3 and 4 are correct
2, 3 and 4 are correct
1, 2 and 3 are correct
1, 2 and 4 are correct