Home
Current Affairs January 2024

What is the correct answer?

4

Critical Path Net Work helps an engineer

A. To concentrate his attention on critical activities

B. To divert the resources from non-critical advanced activities to critical activities

C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

D. All the above

Correct Answer :

D. All the above


Related Questions

What is the correct answer?

4

Completion of an activity on CPM network diagram, is generally known

A. Event

B. Node

C. Connector

D. All the above

What is the correct answer?

4

Slack time refers to

A. An activity

B. An event

C. Both event and activity

D. None of the above

What is the correct answer?

4

Updating may result in

A. Change of critical path

B. Decrease of project completion time

C. Increase of project completion time

D. All of the above

What is the correct answer?

4

An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is

A. Rs. 8,43,750

B. Rs. 8,75,000

C. Rs. 10,50,000

D. Rs. 11,56,250

What is the correct answer?

4

Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of project PERT is preferred for planning because of

A. 1, 2 and 4

B. 3, 4 and 5

C. 1, 3 and 4

D. 1, 2 and 5

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The various functions under each activity, are shown by one bar on Bar Charts

B. Bar chart establishes the interdependency of one event on another

C. Only approximate percentage of the completed work is reported

D. None of these

What is the correct answer?

4

If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is

A. 30 kg

B. 300 kg

C. 900 kg

D. 1000 kg

What is the correct answer?

4

The independent float affects only

A. Preceding activities

B. Succeeding activities

C. The particular activity involved

D. None of the above

What is the correct answer?

4

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

A. (a + m + b)/6

B. (a + 2m + b)/6

C. (a + 4m + b)/6

D. (a + 5m + b)/6

What is the correct answer?

4

A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be

A. 3.7 years

B. 4.23 years

C. 5 years

D. 7.87 years

What is the correct answer?

4

The technique for establishing and maintaining priorities among the various jobs of a project, is known

A. Event flow scheduling technique

B. Critical ratio scheduling

C. Slotting technique for scheduling

D. Short interval scheduling

What is the correct answer?

4

A critical ratio scheduling

A. Determines the status of each activity

B. Adjusts automatically changes in activity progress

C. Is a dynamic system

D. None of these

What is the correct answer?

4

Critical path method

A. Is an improvement upon bar chart method

B. Provides a realistic approach to daily problems

C. Avoids delays which are very common in bar charts

D. All the above

What is the correct answer?

4

PERT technique of network analysis is mainly useful for

A. Small projects

B. Large and complex projects

C. Research and development projects

D. Deterministic activities

What is the correct answer?

4

Final technical authority of a project lies with

A. Assistant Engineer

B. Executive Engineer

C. Superintending Engineer

D. Chief Engineer

What is the correct answer?

4

Pick up the correct statement from the following:

A. The float may be positive, zero or negative

B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed

C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

D. All the above

What is the correct answer?

4

Output of a bulldozer is
(i) Increased if drawbar HP of the tractor is increased for a given hauling distance
(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance
(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor
(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor
Of these statement

A. (i) and (iii) are correct

B. (i) and (iv) are correct

C. (ii) and (iii) are correct

D. (ii) and (iv) are correct

What is the correct answer?

4

The final selection of a construction site, is done by

A. Departmental representative or user

B. Local civil authority representative

C. Representative of engineer authority

D. All the above

What is the correct answer?

4

Which one of the following represents an event?

A. Concrete cured

B. Fixing of door

C. Plastering of walls

D. Selecting sites

What is the correct answer?

4

The reduction in project time normally results in

A. Decreasing the direct cost and increasing indirect cost

B. Increasing the direct cost and decreasing the indirect cost

C. Increasing the direct cost and indirect cost both

D. Decreasing the direct cost and indirect cost both

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not consume time

D. All the above

What is the correct answer?

4

Which one of the following is not an excavating and moving type of equipment?

A. Bulldozer

B. Clam shell

C. Scraper

D. Dump truck

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth, (iv) Output can be increased by increasing the size of shovel. Of these statements

A. (ii), (iii) and (iv) are correct

B. (i), (ii) and (iv) are correct

C. (i), (iii) and (iv) are correct

D. (i) and (iv) are correct

What is the correct answer?

4

The main advantage of line organisation is:

A. Effective command and control

B. Rigid discipline in the organisation

C. Defined responsibilities at all levels

D. All the above

What is the correct answer?

4

A Milestone chart

A. Shows the interdependencies of various jobs

B. Depicts the delay of jobs, if any

C. Points outgoing ahead of schedule of jobs, if any

D. None of these

What is the correct answer?

4

Pick up the correct statement from the following:

A. The difference of latest occurrence time and earliest expected time, is called slack

B. The activities connecting the events having zero slack, lie on the critical path

C. The critical path consumes the maximum time

D. All the above

What is the correct answer?

4

Which of the following is not a PERT event?

A. Site investigation started

B. Sessional work completed

C. Bus starts from Jaipur

D. Class is being attended

What is the correct answer?

4

If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be

A. Equal to X

B. More than X

C. Less than X

D. Any of the above

What is the correct answer?

4

The object of technical planning, is

A. Preparation of specifications

B. Preparation of estimates

C. Initiating the procurement action of resources

D. All the above