Home

Industrial Engineering & Production Management Test MCQ Question with Answer

Industrial Engineering & Production Management Test MCQ with detailed explanation for interview, entrance and competitive exams. Explanation are given for understanding.

Download Industrial Engineering & Production Management Test MCQ Question Answer PDF

Question No : 29
In order to avoid excessive multiplication of facilities, the layout preferred is

Product layout
Process layout
Group layout
Static layout

Question No : 30
The most popular type of organisation used for Civil Engineering Constructions is

Line organisation
Line and staff organisation
Functional organisation
Effective organisation

Question No : 31
P.M.T.S. (Predetermined Motion Time Systems) include

M.T.M. (Method Time Measurement)
W.F.S. (Work Factor Systems)
B.M.T.S. (Basic Motion Time Study)
All of these

Question No : 32
The term 'value' in value engineering refers to

Total cost of the product
Selling price of the product
Utility of the product
Manufactured cost of the product

Question No : 33
Dispatching

Prescribes the sequence of operations to be followed
Determines the programme for the operations
Is concerned with the starting of processes
Regulates the progress of job through various processes

Question No : 34
Line organisation is suitable for

Sugar industries
Oil refining industries
Spinning and weaving industries
All of these

Question No : 35
An event is indicated on the network by

A straight line
A number enclosed in a circle or a square
A straight line with circles at the ends
A dotted line