Home
Current Affairs January 2024

What is the correct answer?

4

While scheduling a project by C.P.M.

A. A project is divided into various activities

B. Required time for each activity is established

C. Net work is drawn by connecting the activities and the events

D. All the above

Correct Answer :

D. All the above


Related Questions

What is the correct answer?

4

A contractor has two options;
(I): Invest his money in project A or
(II): Invest his money in project B.
If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

A. Should invest in neither of the two projects

B. Could invest in either of the two projects

C. Should invest in project A

D. Should invest in project B

What is the correct answer?

4

The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively

A. 80 and 90

B. 90 and 80

C. 85 and 75

D. 75 and 83

What is the correct answer?

4

The estimated time required to perform an activity, is known as

A. Event

B. Dummy

C. Duration

D. Float

What is the correct answer?

4

If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be

A. 50 %

B. Less than 50 %

C. More than 50 %

D. 100 %

What is the correct answer?

4

A construction schedule is prepared after collecting

A. Number of operations

B. Output of labour

C. Output of machinery

D. All the above

What is the correct answer?

4

A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be

A. Rs. 1740

B. Rs. 3480

C. Rs. 5220

D. Rs. 6960

What is the correct answer?

4

Select the incorrect statement.

A. Earliest start of an activity is the early event time of the node it leaves.

B. Latest finish of an activity is the late event time of the node it enters.

C. Latest start of an activity is its latest finish minus its duration.

D. None of the above

What is the correct answer?

4

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

A. (a + m + b)/6

B. (a + 2m + b)/6

C. (a + 4m + b)/6

D. (a + 5m + b)/6

What is the correct answer?

4

The reduction in project time normally results in

A. Decreasing the direct cost and increasing indirect cost

B. Increasing the direct cost and decreasing the indirect cost

C. Increasing the direct cost and indirect cost both

D. Decreasing the direct cost and indirect cost both

What is the correct answer?

4

Sensitivity analysis is a study of

A. Comparison of profit and loss

B. Comparison of assets and liabilities

C. Change in output due to change in input

D. Economics of cost and benefits of the project

What is the correct answer?

4

Grader is used mainly for

A. Trimming and finishing

B. Shaping and trimming

C. Finishing and shaping

D. Finishing, shaping and trimming

What is the correct answer?

4

Mobilization advance up to 10% of the cost of work is given to a contractor

A. On commencement of work at site for payment of loan taken by him

B. For the purchase of construction materials

C. For the payment of advances to labour and other staff

D. For all activities required to start the work at site on finalization of the contract document

What is the correct answer?

4

Pick up the correct statement from the following:

A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'

B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float

C. The difference between total float and free float, is called interfering float

D. All the above

What is the correct answer?

4

Interfering float is the difference between

A. Total float and free float

B. Total float and independent float

C. Free float and independent float

D. None of the above

What is the correct answer?

4

In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

A. Yes, because of heavier overheads and handling cost

B. Yes, because of the very high order of quality control for the factory made components

C. No, because of repetitive manufacture of a number of elements

D. No, because of savings in site labour

What is the correct answer?

4

Which one of the following represents an event?

A. Concrete cured

B. Fixing of door

C. Plastering of walls

D. Selecting sites

What is the correct answer?

4

Pick up the PERT event from the following:

A. Digging of foundation started

B. Digging of foundation completed

C. Laying of concrete started

D. All the above

What is the correct answer?

4

For the network shown in the given figure, the expected time for the activity

A. 1-2 is 4

B. 2-3 is 7

C. 3-4 is 8

D. All the above

What is the correct answer?

4

Whenever an activity has zero total float, then

A. Free float of the activity must be zero but independent float need not be zero

B. Independent float must be zero but free float need not be zero

C. Free float and independent float both must be zero

D. Free float and independent float both need not be zero

What is the correct answer?

4

PERT is

A. An analytic in concept

B. Limited of event oriented diagrams

C. Used for research and development projects

D. All the above

What is the correct answer?

4

If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

A. EF = ES + D

B. LS = LF - D

C. LF = LS + D

D. All the above

What is the correct answer?

4

If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is

A. 500 cum

B. 1000 cum

C. 1500 cum

D. 2000 cum

What is the correct answer?

4

The main principle of an organisation, is

A. Unity of command

B. Effective control at all levels

C. Delegation of authority

D. All the above

What is the correct answer?

4

At a work site, statistical quality control of concrete means

A. Measurement of risks to eliminate failures

B. Applying the theory' of probability to sample testing or inspection

C. Reduction in wastage of inspection costs

D. Reduction in costs for the removal of defects

What is the correct answer?

4

The time with which direct cost does not reduce with the increase in time is known as

A. Crash time

B. Normal time

C. Optimistic time

D. Standard time

What is the correct answer?

4

Pre-tender stage requires

A. Acquisition of land

B. Selection of site

C. Fmalisation of alignment of work

D. All the above

What is the correct answer?

4

Military organisation is known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. None of these

What is the correct answer?

4

The process of incorporating changes and rescheduling or replanning is called

A. Resource levelling

B. Resource smoothening

C. Updating

D. Critical path scheduling

What is the correct answer?

4

For completion of a project, the critical path of the network represents

A. Minimum time

B. Maximum time

C. Maximum cost

D. Minimum cost

What is the correct answer?

4

Pick up the correct statement from the following:

A. Optimistic time estimate refers to activities

B. Pessimistic time estimate refers to activities

C. Most likely time estimate refers to activities

D. All the above