Related Questions
What is the correct answer?
4
A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be
What is the correct answer?
4
The constraints in case of resource smoothening operation would be
C. Both resources and project duration time
What is the correct answer?
4
Time and progress chart of a construction, is also known as
C. Modified Mile stone chart
What is the correct answer?
4
The first stage of a construction, is
A. Preparation of estimate
C. Initiation of proposal
What is the correct answer?
4
A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will
What is the correct answer?
4
Batching refers to
A. Controlling the total quantity at each batch
B. Weighing accurately, the quantity of each material for a job before mixing
C. Controlling the quantity of each material into each batch
D. Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
What is the correct answer?
4
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
What is the correct answer?
4
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
What is the correct answer?
4
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
What is the correct answer?
4
If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is
What is the correct answer?
4
Power stations are generally treated as
C. Industrial construction
D. Electrical construction
What is the correct answer?
4
Bar charts are suitable for
What is the correct answer?
4
Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is
What is the correct answer?
4
The main principle of an organisation, is
B. Effective control at all levels
C. Delegation of authority
What is the correct answer?
4
Military organisation is known as
B. Line and staff organisation
C. Functional organisation
What is the correct answer?
4
Residential buildings are treated as
C. Industrial construction
What is the correct answer?
4
The basic action involved in sheep foot rolling is
What is the correct answer?
4
Consider the following statements: In the critical path method of construction planning, Free Float can be.
1. Greater than Total Float.
2. Greater than Independent Float
3. Equal to Total Float.
4. Less than Independent Float. Of these statements
What is the correct answer?
4
Final technical authority of a project lies with
C. Superintending Engineer
What is the correct answer?
4
Which one of the following represents an event?
What is the correct answer?
4
While filling the tender for any work, the contractor considers
B. Availability of construction materials
C. Availability of labour
What is the correct answer?
4
For the network shown in the given figure, the expected time for the activity
What is the correct answer?
4
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
What is the correct answer?
4
CPM is
A. Synthesising in concepts
B. Is built of activities oriented programme
C. Is based on time estimate
What is the correct answer?
4
The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack Of these statements
A. (i), (ii) and (iv) are correct
B. (ii), (iii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i), (ii) and (iii) are correct
What is the correct answer?
4
During the construction period, price variation clause in contracts caters to
A. Increase in rates of only important materials
B. Variation in cost in materials element, labour element and petrol-oillubricant element
C. Variation in total cost of the project on an ad hoc basis
What is the correct answer?
4
Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of project PERT is preferred for planning because of
What is the correct answer?
4
Which one of the following represents an activity?
A. Excavation for foundation
C. Setting of question paper
What is the correct answer?
4
Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements
B. (i) and (ii) are correct
C. (i) and (iii) are correct
D. (ii) and (iii) are correct
What is the correct answer?
4
Various activities of a project, are shown on bar charts by