Related Questions
What is the correct answer?
4
Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth, (iv) Output can be increased by increasing the size of shovel. Of these statements
A. (ii), (iii) and (iv) are correct
B. (i), (ii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i) and (iv) are correct
What is the correct answer?
4
For which of the following materials, the output of power shovels for a fixed shovel size will be maximum
What is the correct answer?
4
The time corresponding to minimum total project cost is
D. Between normal time and crash time
What is the correct answer?
4
Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements
B. (i) and (ii) are correct
C. (i) and (iii) are correct
D. (ii) and (iii) are correct
What is the correct answer?
4
For the execution of a project, a contractor is
What is the correct answer?
4
A CPM family includes
A. CPA (Critical Path Analysis)
B. CPP (Critical Path Plotted)
C. MCE (Minimum Cost Expenditure)
What is the correct answer?
4
Whenever an activity has zero total float, then
A. Free float of the activity must be zero but independent float need not be zero
B. Independent float must be zero but free float need not be zero
C. Free float and independent float both must be zero
D. Free float and independent float both need not be zero
What is the correct answer?
4
Pick up the correct statement from the following:
A. Earliest expected time is denoted by TE
B. Latest occurrence time is denoted by TL
C. Contractual obligation time is denoted by Ts
What is the correct answer?
4
Output of a bulldozer is
(i) Increased if drawbar HP of the tractor is increased for a given hauling distance
(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance
(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor
(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor
Of these statement
A. (i) and (iii) are correct
B. (i) and (iv) are correct
C. (ii) and (iii) are correct
D. (ii) and (iv) are correct
What is the correct answer?
4
Pick up the correct statement from the following:
A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
C. The difference between total float and free float, is called interfering float
What is the correct answer?
4
The main advantage of line organisation is:
A. Effective command and control
B. Rigid discipline in the organisation
C. Defined responsibilities at all levels
What is the correct answer?
4
Final technical authority of a project lies with
C. Superintending Engineer
What is the correct answer?
4
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
What is the correct answer?
4
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
What is the correct answer?
4
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
What is the correct answer?
4
A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is
What is the correct answer?
4
Interfering float is the difference between
A. Total float and free float
B. Total float and independent float
C. Free float and independent float
What is the correct answer?
4
CPM is
A. Synthesising in concepts
B. Is built of activities oriented programme
C. Is based on time estimate
What is the correct answer?
4
Railway projects are treated as
C. Industrial construction
What is the correct answer?
4
The basic action involved in sheep foot rolling is
What is the correct answer?
4
The constraints in case of resource smoothening operation would be
C. Both resources and project duration time
What is the correct answer?
4
For the network shown in the given figure, the expected time for the activity
What is the correct answer?
4
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to
What is the correct answer?
4
Henry Gantt developed Bar charts for planning and scheduling of projects in
What is the correct answer?
4
The direct cost of a project with respect to normal time is
What is the correct answer?
4
If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be
What is the correct answer?
4
The technique for establishing and maintaining priorities among the various jobs of a project, is known
A. Event flow scheduling technique
B. Critical ratio scheduling
C. Slotting technique for scheduling
D. Short interval scheduling
What is the correct answer?
4
Sinking fund is
A. The fund for rebuilding a structure when its economic life is over
B. Raised to meet maintenance costs
C. The total sum to be paid to the municipal authorities by the tenants
D. A part of the money kept in reserve for providing additional structures and structural modifications
What is the correct answer?
4
Mobilization advance up to 10% of the cost of work is given to a contractor
A. On commencement of work at site for payment of loan taken by him
B. For the purchase of construction materials
C. For the payment of advances to labour and other staff
D. For all activities required to start the work at site on finalization of the contract document
What is the correct answer?
4
Which of the following is a weakness of bar chart?
A. Interdependencies of activities