Unity of command
Effective control at all levels
Delegation of authority
All the above
D. All the above
Event
Float
Duration
Constraint
Kneading
Pressing
Tamping
Vibration
Activity arrows in a CPM network are drawn to scale
The tail of an arrow represents the finish of an activity
Arrow bead represents the start of an activity
None of the above
to + 3tm+ tp/3
to + 4tm+ tp/4
to + 4tm+ tp/5
to + 4tm+ tp/6
Normal durations for all the activities
Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Effective command and control
Rigid discipline in the organisation
Defined responsibilities at all levels
All the above
Maximum float
Minimum float
Zero float
None of these
An engineer
An architect
An owner
All the above
Free float of the activity must be zero but independent float need not be zero
Independent float must be zero but free float need not be zero
Free float and independent float both must be zero
Free float and independent float both need not be zero
Determines the status of each activity
Adjusts automatically changes in activity progress
Is a dynamic system
None of these
Departmental representative or user
Local civil authority representative
Representative of engineer authority
All the above
Strict adherence to specifications
Separation of planning and design part
Each individual maintains functional efficiency
All the above
1
2
3
4
Reduce by 200 kg
Increase by 200 kg
Increase by 250 kg
Reduce by 250 kg
Normal distribution curve
Poisson's distribution curve
Beta distribution curve
None of the above
Number of operations
Output of labour
Output of machinery
All the above
The difference of latest occurrence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above
Cheapest critical activity
Cheapest noncritical activity
Costliest critical activity
Costliest noncritical activity
A circle
A square
A triangle
All the above
8 days
9 days
10 days
15 days
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
An analytic in concept
Limited of event oriented diagrams
Used for research and development projects
All the above
Longest duration
Highest cost slope
Least cost slope
Shortest duration
Positive
Negative
Zero
Same
A project is divided into various activities
Required time for each activity is established
Net work is drawn by connecting the activities and the events
All the above
Preparation of estimate
Survey of the site
Initiation of proposal
Preparation of tender
1880
1900
1920
1940
50 %
84.1 %
99.9 %
100 %
Smooth-wheeled rollers
Vibratory rollers
Sheep foot rollers
Tampers
Is an improvement upon bar chart method
Provides a realistic approach to daily problems
Avoids delays which are very common in bar charts
All the above