Home
Current Affairs January 2024

What is the correct answer?

4

For the network shown in the given figure, the expected time for the activity

A. 1-2 is 4

B. 2-3 is 7

C. 3-4 is 8

D. All the above

Correct Answer :

D. All the above


Related Questions

What is the correct answer?

4

Pick up the correct statement from the following:

A. CPM analysis is activity oriented

B. PERT analysis is event oriented

C. In CPM, the time is related to cost

D. All the above

What is the correct answer?

4

Which one of the following is not an excavating and moving type of equipment?

A. Bulldozer

B. Clam shell

C. Scraper

D. Dump truck

What is the correct answer?

4

Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?

A. Ice

B. Concrete

C. Loose sand

D. Earth

What is the correct answer?

4

At a work site, statistical quality control of concrete means

A. Measurement of risks to eliminate failures

B. Applying the theory' of probability to sample testing or inspection

C. Reduction in wastage of inspection costs

D. Reduction in costs for the removal of defects

What is the correct answer?

4

The time with which direct cost does not reduce with the increase in time is known as

A. Crash time

B. Normal time

C. Optimistic time

D. Standard time

What is the correct answer?

4

In CPM analysis,

A. Emphasis is given to activities

B. Uncertainties are not allowed

C. Activities are represented by arrows

D. All the above

What is the correct answer?

4

The main disadvantage of line organisation, is

A. Rigid structure

B. Extraordinary delay in communications

C. Top level executions over work

D. All the above

What is the correct answer?

4

The most popular type of organisation used for Civil Engineering Constructions, is

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

A. to + 3tm+ tp/3

B. to + 4tm+ tp/4

C. to + 4tm+ tp/5

D. to + 4tm+ tp/6

What is the correct answer?

4

Pick up the PERT event from the following:

A. Digging of foundation started

B. Digging of foundation completed

C. Laying of concrete started

D. All the above

What is the correct answer?

4

The time corresponding to minimum total project cost is

A. Crash time

B. Normal time

C. Optimistic time

D. Between normal time and crash time

What is the correct answer?

4

In time-cost optimization of a project, crashing is done.

A. On all the activities

B. On all the activities lying on the critical path

C. Only on activities lying on the original critical path and having flatter cost slopes

D. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

What is the correct answer?

4

Pick up the correct statement from the following:

A. The float may be positive, zero or negative

B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed

C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

D. All the above

What is the correct answer?

4

The area under the Beta distribution curve is divided into two equal parts by

A. Most likely time

B. Optimistic time

C. Pessimistic time

D. Expected time

What is the correct answer?

4

Select the incorrect statement.

A. Earliest start of an activity is the early event time of the node it leaves.

B. Latest finish of an activity is the late event time of the node it enters.

C. Latest start of an activity is its latest finish minus its duration.

D. None of the above

What is the correct answer?

4

If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

A. Started 5 days later

B. Completed 5 days later

C. Performed at slower rate in 15 days

D. All the above

What is the correct answer?

4

The probability of completion of any activity within its expected time is

A. 50 %

B. 84.1 %

C. 99.9 %

D. 100 %

What is the correct answer?

4

Mile Stone charts were invented in the year of

A. 1910

B. 1920

C. 1930

D. 1940

What is the correct answer?

4

For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

A. Moist loam

B. Good common earth

C. Well blasted rock

D. Wet sticky clay

What is the correct answer?

4

Critical Path Net Work helps an engineer

A. To concentrate his attention on critical activities

B. To divert the resources from non-critical advanced activities to critical activities

C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

D. All the above

What is the correct answer?

4

Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.

A. A is correct but R is not correct

B. R is correct but A is not correct

C. Both A and R is correct

D. Both A and R is incorrect

What is the correct answer?

4

Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?

A. Concrete

B. Loose sand

C. Asphalt

D. Firm earth

What is the correct answer?

4

Frequency distribution curves

A. Having a single lump, are called uninodal curves

B. If symmetrical, are called normal curves

C. If not symmetrical, are called skew curves

D. All the above

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not consume time

D. All the above

What is the correct answer?

4

The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as

A. Event

B. Free float

C. Dummy

D. Constraint

What is the correct answer?

4

The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively

A. 80 and 90

B. 90 and 80

C. 85 and 75

D. 75 and 83

What is the correct answer?

4

Power stations are generally treated as

A. Light construction

B. Heavy construction

C. Industrial construction

D. Electrical construction

What is the correct answer?

4

A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be

A. Rs. 1740

B. Rs. 3480

C. Rs. 5220

D. Rs. 6960

What is the correct answer?

4

The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be

A. Rs. 8,800

B. Rs. 7,600

C. Rs. 6,400

D. Rs. 5,000

What is the correct answer?

4

Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements

A. Only (i) is correct

B. (i) and (ii) are correct

C. (i) and (iii) are correct

D. (ii) and (iii) are correct