An analytic in concept
Limited of event oriented diagrams
Used for research and development projects
All the above
D. All the above
Is an improvement upon bar chart method
Provides a realistic approach to daily problems
Avoids delays which are very common in bar charts
All the above
To concentrate his attention on critical activities
To divert the resources from non-critical advanced activities to critical activities
To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
All the above
Total float
Free float
Interfering float
Independent float
Optimistic time
Pessimistic time
Most likely time
All the above
The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
The difference between total float and free float, is called interfering float
All the above
Optimistic time estimate refers to activities
Pessimistic time estimate refers to activities
Most likely time estimate refers to activities
All the above
Most likely time
Optimistic time
Pessimistic time
Expected time
Yes, because of heavier overheads and handling cost
Yes, because of the very high order of quality control for the factory made components
No, because of repetitive manufacture of a number of elements
No, because of savings in site labour
Light construction
Heavy construction
Industrial construction
Private construction
Crash time
Normal time
Optimistic time
Between normal time and crash time
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
All the above
Programme Evaluation and Review Technique, is event oriented
Programme Evaluation and Review Technique is not event oriented
Critical Path Method is event oriented
Critical Path method is event oriented
Normal distribution curve
Poisson's distribution curve
Beta distribution curve
None of the above
Increase in rates of only important materials
Variation in cost in materials element, labour element and petrol-oillubricant element
Variation in total cost of the project on an ad hoc basis
Rate of inflation
Rs. 1740
Rs. 3480
Rs. 5220
Rs. 6960
The activity is the time consuming part of a project
The beginning and end of a job, are called events
The activity which consumes maximum time, is called a node
Logically and sequentially connected activities and events form a network
80 and 90
90 and 80
85 and 75
75 and 83
Kneading
Pressing
Tamping
Vibration
Moist loam
Good common earth
Well blasted rock
Wet sticky clay
Vertical lines
Horizontal lines
Dots
Crosses
Crash time
Normal time
Optimistic time
Standard time
Excavation for foundation
Curing of concrete
Setting of question paper
All the above
Equal to X
More than X
Less than X
Any of the above
The various functions under each activity, are shown by one bar on Bar Charts
Bar chart establishes the interdependency of one event on another
Only approximate percentage of the completed work is reported
None of these
1, 2 and 3 are correct
1 and 4 are correct
2, 3 and 4 are correct
1, 2 and 4 are correct
Rs. 4,75,000
Rs. 5,75,000
Rs. 6,50,000
Rs. 8,50,000
Synthesising in concepts
Is built of activities oriented programme
Is based on time estimate
All the above
Only (i) is correct
(i) and (ii) are correct
(i) and (iii) are correct
(ii) and (iii) are correct
Rs. 8,800
Rs. 7,600
Rs. 6,400
Rs. 5,000
An engineer
An architect
An owner
All the above