Home
Current Affairs January 2024

What is the correct answer?

4

The process of filling hollow spaces of walls before plastering, is known

A. Hacking

B. Dubbing out

C. Blistering

D. Peeling

Correct Answer :

B. Dubbing out


Related Questions

What is the correct answer?

4

In any good staircase, the maximum and minimum pitch respectively should be

A. 90° and 0°

B. 75° and 30°

C. 60° and 10°

D. 40° and 25°

What is the correct answer?

4

A wall constructed with stones to protect slopes of cuttings in natural ground from the action of weathering agents, is called

A. Retaining wall

B. Breast wall

C. Buttress

D. Parapet wall

What is the correct answer?

4

The members which support covering material of a sloping roof, are

A. Rafters

B. Purlins

C. Battens

D. Struts

What is the correct answer?

4

The form work from the underside of slabs, can be removed only after

A. 1 day

B. 4 days

C. 7 days

D. 14 days

What is the correct answer?

4

The rock formed from the solidification of molten matter (magma) is called:

A. Sedimentary rock

B. Metamorphic rock

C. Igneous rock

D. None of the above

What is the correct answer?

4

In ordinary residential and public buildings, the damp proof course is generally provided at

A. Ground level

B. Plinth level

C. Water table level

D. Midway ground level and water-table level

What is the correct answer?

4

In case of Raymond pile

A. Lengths vary from 6 m to 12 m

B. Diameter of top of piles varies from 40 cm to 60 cm

C. Diameter of pile at bottom varies from 20 cm to 28 cm

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. Plain cement concrete is equally strong in compression as well as in tension

B. Slump test is performed to check concrete strength

C. Curing of concrete is done for proper compaction of cement

D. Fineness modulus is the index number expressing the relative sizes of both coarse and fine aggregates

What is the correct answer?

4

Pick up the correct statement from the following:

A. Isolated footing is provided under column to transfer the load safely to soil bed

B. Column footings may have steps or projections in the concrete base

C. Heavily loaded column base must be provided steel reinforcement in both directions

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. A mortar joint having a concave finishing in brick masonry, is called keyed joint

B. A mortar joint projecting beyond the face of a masonry wall, is called tucked joint

C. A mortar joint having a recess in it, is called ruled joint

D. All the above

What is the correct answer?

4

The horizontal timber piece provided at the apex of a roof truss which supports the common rafter is called

A. Ridge board

B. Hip rafter

C. Eaves board

D. Valley rafter

What is the correct answer?

4

The loose pockets in soil mass can be bridged safely by providing a raft foundation provided the soft area is smaller than

A. The column spacing

B. One-third the column spacing

C. Half the column spacing

D. Three-fourth the column spacing

What is the correct answer?

4

Arches in the form of masonry arcs struck from more than four centres, are called

A. Two curved arches

B. Gothic arches

C. Ogee arches

D. Drop gothic arches

What is the correct answer?

4

Which one of the following factors is considered for the orientation of buildings?

A. The direction of the prevailing winds in the area

B. The exposure of the walls and roof of the buildings to the rays of sun

C. The extent up to which the sunrays penetrate with the verandah

D. All the above

What is the correct answer?

4

The vertical distance between the springing line and highest point of the inner curve of an arch is known as

A. Intrados

B. Rise

C. Spandril

D. Extrados

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. In dog-legged stairs, no space between its flights is provided

B. In open newel stair, a rectangular well is provided

C. In geometric stair, a curved shaped well between forward and backward flights, is provided

D. In geometrical stair, two quarter space landing is provided

What is the correct answer?

4

The line of intersection of two surfaces of a sloping roof forming an internal angle less than 180°, is known as

A. Ridge

B. Hip

C. Valley

D. None of these

What is the correct answer?

4

The minimum depth of foundation in clayey soils is

A. 0.5 m

B. 0.7 m

C. 0.9 m

D. 1.2 m

What is the correct answer?

4

The form Work including the props can be removed from beams, only after

A. 3 day

B. 7 days

C. 14 days

D. 21 days

What is the correct answer?

4

The Auger boring method is not suitable for

A. Very hard soil

B. Cemented soil

C. Vary soft soil

D. All the above

What is the correct answer?

4

In jack arch floor, the rise is kept

A. 1/6th of the span

B. 1/8th of the span

C. 1/10th of the span

D. 1/12th of the span

What is the correct answer?

4

A wooden block hinged on post outside a door, is known

A. Cleat

B. Stop

C. Horn

D. None of these

What is the correct answer?

4

A pre-stressed concrete pile is

A. Easy to handle

B. Lighter in weight

C. Extremely durable

D. All the above

What is the correct answer?

4

If (φ) is the angle of repose of soil of weight w kg/m3, the horizontal pressure p at a depth of h metres per metre length of wall, is

A. wh × [(1 - sin φ)/(1 + sin φ)]

B. (wh/2) × [(1 - sin φ)/(1 + sin φ)]

C. wh × √[(1 - sin φ)/(1 + sin φ)]

D. wh × √[(1 + sin φ)/(1 - sin φ)]

What is the correct answer?

4

The brick laid with its length parallel to the face of a wall, is a known as

A. Header

B. Stretcher

C. Closer

D. None of these

What is the correct answer?

4

The important test to be conducted on a stone used in docks and harbours is

A. Hardness test

B. Workability test

C. Weight test

D. Toughness test

What is the correct answer?

4

Pick up the correct statement from the following:

A. The bearing capacity of a pile is defined as the load which can be sustained by the pile without producing excessive settlement

B. The safe bearing capacity of a pile is obtained by dividing the ultimate bearing capacity with a suitable factor of safety

C. The factor of safety for piles is taken as 6

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. Inclined borings are made for taking samples under existing structures

B. Inclined borings are occasionally used instead of vertical holes

C. The spacing of inclined borings is kept such that one bore hole is vertically above the bottom of an adjacent bore hole

D. All the above

What is the correct answer?

4

The pile which is provided with a bulb filled with concrete at its lower end, is known as

A. Simplex pile

B. Mac-Arthur pile

C. Raymond pile

D. Franki pile

What is the correct answer?

4

In the method of tube boring of soil investigation, the following is essential:

A. A tube of about 2 metres length and 20 cm diameter with a cutting edge

B. A flap valve at the bottom of tube is provided to extract the soil sample

C. The tube is raised and lowered by 4 thick rope moving over a pulley suspended on a tripod stand

D. All the above