Increase the depth of foundation
Drain the soil
Compact the soil
Replace the poor soil
D. Replace the poor soil
Compacting the soil
Draining the soil
Increasing the depth of foundation
Grouting
Balusters
Newel posts
Balustrades
Railings
Lack of ventilation
Alternate wet and dry conditions
Complete submergence in water
None of the above
Scaffolding
Dead shore
Raking shore
Under pinning
350
420
450
500
Distance of C.G. of the loads from the smaller column = 3.00 m
The length of the foundation slab = 7.00 m
Area of footing slab = 11.00 m2
All the above
(P/w) × [(1 + sin φ)/(1 - sin φ)]²
(P/w) × [(1 - sin φ)/(1 + sin φ)]²
(P/2w) × [(1 - sin φ)/(1 + sin φ)]²
(P/w) × [(1 + sin φ)/(1 - sin φ)]
1 cm per metre length
2 cm per metre length
4 cm per metre length
5 cm per metre length
Shed roof
Gable end roof
Hipped roof
Gambrel roof
1 metre
2 metres
3 metres
4 metres
Half brick
Queen closer
King closer
Bevelled closer
Horizontal D.P.C. is provided at plinth level in internal walls
D.P.C. is provided under door and verandah openings
Vertical D.P.C. is not provided in internal walls
Cement concrete is a rigid damp-proofing material
Combined footing
Raft footing
Pier footing
Strap footing
Copper sheets
Lead sheets
Aluminium sheets
All the above
Stretcher
Face
Front
Header
1 day
4 days
7 days
14 days
Draining sub-soil water
Ramming crushed stone in soil
Driving sand piles
Watering surface of soil
Laying bricks as stretchers in cement mortar
Laying bricks as headers in cement mortar
Reinforcing brick wall with iron straps
Constructing brick work within a wooden framework
Uneven settlement of abutments
Sliding of voussoirs
Crushing of the material
All the above
In Flemish bond, headers and stretchers are laid alternately in the same course
In Flemish bond every header in each course lies centrally over every stretcher of the underlying course
In English bond, stretchers are laid in every course
In English bond, headers and stretchers are laid in alternate courses
Column footing
Grillage footing
Raft footing
All the above
English bond is used for brick masonry to support heavy loads
Double-Flemish bond is suitable for brick masonry to give uniform face appearance
The stretcher bond is used for the construction of half brick masonry brick
All the above
Mortise and tenon joint
Oblique mortise and tenon joint
Butt joint
Mitred joint
Cracks appear on the plastered surface in the form of hair cracks
In brick work, the efflorescence is removed by applying a solution of zinc sulphate and water
Excessive thermal variations in the backing or plaster causes the plaster to fall
All the above
Purlin
Cleat
Batten
Strut
10 %
15 %
20 %
25 %
Machine foundations
Factory building
Tall structures
All the above
Truck pointing
Recessed pointing
Struck pointing
Grooved pointing
2
3
5
No limit
10 mm
20 mm
30 mm
40 mm