Home
Current Affairs January 2024

What is the correct answer?

4

The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be

A. Rs. 8,800

B. Rs. 7,600

C. Rs. 6,400

D. Rs. 5,000

Correct Answer :

C. Rs. 6,400


Related Questions

What is the correct answer?

4

A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be

A. Rs. 1740

B. Rs. 3480

C. Rs. 5220

D. Rs. 6960

What is the correct answer?

4

The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively

A. 80 and 90

B. 90 and 80

C. 85 and 75

D. 75 and 83

What is the correct answer?

4

Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?

A. Ice

B. Concrete

C. Loose sand

D. Earth

What is the correct answer?

4

At a work site, statistical quality control of concrete means

A. Measurement of risks to eliminate failures

B. Applying the theory' of probability to sample testing or inspection

C. Reduction in wastage of inspection costs

D. Reduction in costs for the removal of defects

What is the correct answer?

4

The salient feature of functional organisation is

A. Strict adherence to specifications

B. Separation of planning and design part

C. Each individual maintains functional efficiency

D. All the above

What is the correct answer?

4

An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

A. Rs. 31050

B. Rs. 34500

C. Rs. 37950

D. Rs. 50000

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The various functions under each activity, are shown by one bar on Bar Charts

B. Bar chart establishes the interdependency of one event on another

C. Only approximate percentage of the completed work is reported

D. None of these

What is the correct answer?

4

If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is

A. 500 cum

B. 1000 cum

C. 1500 cum

D. 2000 cum

What is the correct answer?

4

Pick up the correct statement from the following:

A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'

B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float

C. The difference between total float and free float, is called interfering float

D. All the above

What is the correct answer?

4

The first method invented for planning projects, was

A. Bar chart method

B. Milestone chart

C. Critical path method (CPM)

D. Programme Evaluation and Review Technique (PERT)

What is the correct answer?

4

Whenever an activity has zero total float, then

A. Free float of the activity must be zero but independent float need not be zero

B. Independent float must be zero but free float need not be zero

C. Free float and independent float both must be zero

D. Free float and independent float both need not be zero

What is the correct answer?

4

A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be

A. 20 kg/tonne

B. 30 kg/tonne

C. 40 kg/tonne

D. 50 kg/tonne

What is the correct answer?

4

Critical path

A. Is always longest

B. Is always shortest

C. May be longest

D. May be shortest

What is the correct answer?

4

Railway projects are treated as

A. Light construction

B. Heavy construction

C. Industrial construction

D. None of these

What is the correct answer?

4

A CPM family includes

A. CPA (Critical Path Analysis)

B. CPP (Critical Path Plotted)

C. MCE (Minimum Cost Expenditure)

D. All the above

What is the correct answer?

4

Total float for any activity is defined as the difference between

A. Its latest finish time and earliest start time for its successor activity

B. Its latest start time and earliest start time

C. Its latest start time and earliest finish time

D. Its earliest finish time and earliest start time for its successor activity

What is the correct answer?

4

PERT is

A. An analytic in concept

B. Limited of event oriented diagrams

C. Used for research and development projects

D. All the above

What is the correct answer?

4

The main principle of an organisation, is

A. Unity of command

B. Effective control at all levels

C. Delegation of authority

D. All the above

What is the correct answer?

4

A golden rule for the procurement of construction stones, suggests

A. 100% at the site

B. 67% at the site and 33% under procurement

C. 50% at the site and 50% under procurement

D. 33% at the site and 67% under procurement

What is the correct answer?

4

Which of the following excavators is most suitable for digging under water?

A. Drag line

B. Hoe

C. Clam shell

D. Dipper shovel

What is the correct answer?

4

A critical ratio scheduling

A. Determines the status of each activity

B. Adjusts automatically changes in activity progress

C. Is a dynamic system

D. None of these

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not consume time

D. All the above

What is the correct answer?

4

Free float is mainly used to

A. Identify the activities which can be delayed without affecting the total float of preceding activity

B. Identify the activities, which can be delayed without affecting the total float of succeeding activity

C. Establish priorities

D. Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

What is the correct answer?

4

PERT analysis is based on

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All the above

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

The time corresponding to minimum total project cost is

A. Crash time

B. Normal time

C. Optimistic time

D. Between normal time and crash time

What is the correct answer?

4

The probability of completion of any activity within its expected time is

A. 50 %

B. 84.1 %

C. 99.9 %

D. 100 %

What is the correct answer?

4

The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is

A. 3425 kg

B. 5515 kg

C. 4350 kg

D. 2975 kg

What is the correct answer?

4

If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

A. Started 5 days later

B. Completed 5 days later

C. Performed at slower rate in 15 days

D. All the above

What is the correct answer?

4

Time and progress chart of a construction, is also known as

A. Bar chart

B. Gantt chart

C. Modified Mile stone chart

D. All the above