Home
Current Affairs January 2024

What is the correct answer?

4

A CPM family includes

A. CPA (Critical Path Analysis)

B. CPP (Critical Path Plotted)

C. MCE (Minimum Cost Expenditure)

D. All the above

Correct Answer :

D. All the above


Related Questions

What is the correct answer?

4

If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

A. EF = ES + D

B. LS = LF - D

C. LF = LS + D

D. All the above

What is the correct answer?

4

Military organisation is known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. None of these

What is the correct answer?

4

The performance of a specific task in CPM, is known

A. Dummy

B. Event

C. Activity

D. Contract

What is the correct answer?

4

If TL is the latest allowable event occurrence time, total activity slack(s), is equal to

A. LST-EST

B. LFT-EFT

C. TL-EFT

D. All the above

What is the correct answer?

4

The time corresponding to minimum total project cost is

A. Crash time

B. Normal time

C. Optimistic time

D. Between normal time and crash time

What is the correct answer?

4

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

A. (a + m + b)/6

B. (a + 2m + b)/6

C. (a + 4m + b)/6

D. (a + 5m + b)/6

What is the correct answer?

4

Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is

A. 1, 2, 4, 3, 5

B. 1, 3, 2, 4, 5

C. 1, 2, 3, 4, 5

D. 1, 3, 4, 2, 5

What is the correct answer?

4

A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is

A. 10000 kg

B. 12500 kg

C. 22500 kg

D. 5000 kg

What is the correct answer?

4

In time-cost optimization of a project, crashing is done.

A. On all the activities

B. On all the activities lying on the critical path

C. Only on activities lying on the original critical path and having flatter cost slopes

D. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

What is the correct answer?

4

CPM is

A. Synthesising in concepts

B. Is built of activities oriented programme

C. Is based on time estimate

D. All the above

What is the correct answer?

4

PERT analysis is based on

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All the above

What is the correct answer?

4

Which of the following is not a PERT event?

A. Site investigation started

B. Sessional work completed

C. Bus starts from Jaipur

D. Class is being attended

What is the correct answer?

4

Modular co-ordination of construction means proper

A. Planning

B. Designing

C. Execution

D. All the above

What is the correct answer?

4

If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be

A. 2.3% and 84.1%

B. 97.7% and 84.1%

C. 97.7 % and 15.9%

D. 15.9% and 97.7%

What is the correct answer?

4

A golden rule for the procurement of construction stones, suggests

A. 100% at the site

B. 67% at the site and 33% under procurement

C. 50% at the site and 50% under procurement

D. 33% at the site and 67% under procurement

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not consume time

D. All the above

What is the correct answer?

4

Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements

A. Only (i) is correct

B. (i) and (ii) are correct

C. (i) and (iii) are correct

D. (ii) and (iii) are correct

What is the correct answer?

4

Interfering float is the difference between

A. Total float and free float

B. Total float and independent float

C. Free float and independent float

D. None of the above

What is the correct answer?

4

The object of technical planning, is

A. Preparation of specifications

B. Preparation of estimates

C. Initiating the procurement action of resources

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. Forward pass is used for calculating earliest expected time

B. Backward pass is used for calculating the latest occurrence time

C. Maximum value of earliest expected time is used if there is more than one value of any event

D. All the above

What is the correct answer?

4

While scheduling a project by C.P.M.

A. A project is divided into various activities

B. Required time for each activity is established

C. Net work is drawn by connecting the activities and the events

D. All the above

What is the correct answer?

4

Railway projects are treated as

A. Light construction

B. Heavy construction

C. Industrial construction

D. None of these

What is the correct answer?

4

The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

What is the correct answer?

4

A Milestone chart

A. Shows the interdependencies of various jobs

B. Depicts the delay of jobs, if any

C. Points outgoing ahead of schedule of jobs, if any

D. None of these

What is the correct answer?

4

A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is

A. Rs. 4,75,000

B. Rs. 5,75,000

C. Rs. 6,50,000

D. Rs. 8,50,000

What is the correct answer?

4

Free float for any activity is defined as the difference between

A. Its earliest finish time and earliest start time for its successor activity

B. Its latest start time and earliest start time

C. Its latest finish time and earliest start time for its successor activity

D. Its earliest finish time and latest start time for its successor activity

What is the correct answer?

4

Grader is used mainly for

A. Trimming and finishing

B. Shaping and trimming

C. Finishing and shaping

D. Finishing, shaping and trimming

What is the correct answer?

4

An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

A. Rs. 31050

B. Rs. 34500

C. Rs. 37950

D. Rs. 50000

What is the correct answer?

4

The process of incorporating changes and rescheduling or replanning is called

A. Resource levelling

B. Resource smoothening

C. Updating

D. Critical path scheduling

What is the correct answer?

4

In PERT analysis, the time estimates of activities and probability of their occurrence follow

A. Normal distribution curve

B. Poisson's distribution curve

C. Beta distribution curve

D. None of the above