CPA (Critical Path Analysis)
CPP (Critical Path Plotted)
MCE (Minimum Cost Expenditure)
All the above
D. All the above
EF = ES + D
LS = LF - D
LF = LS + D
All the above
Line organisation
Line and staff organisation
Functional organisation
None of these
Dummy
Event
Activity
Contract
LST-EST
LFT-EFT
TL-EFT
All the above
Crash time
Normal time
Optimistic time
Between normal time and crash time
(a + m + b)/6
(a + 2m + b)/6
(a + 4m + b)/6
(a + 5m + b)/6
1, 2, 4, 3, 5
1, 3, 2, 4, 5
1, 2, 3, 4, 5
1, 3, 4, 2, 5
10000 kg
12500 kg
22500 kg
5000 kg
On all the activities
On all the activities lying on the critical path
Only on activities lying on the original critical path and having flatter cost slopes
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Synthesising in concepts
Is built of activities oriented programme
Is based on time estimate
All the above
Optimistic time
Pessimistic time
Most likely time
All the above
Site investigation started
Sessional work completed
Bus starts from Jaipur
Class is being attended
Planning
Designing
Execution
All the above
2.3% and 84.1%
97.7% and 84.1%
97.7 % and 15.9%
15.9% and 97.7%
100% at the site
67% at the site and 33% under procurement
50% at the site and 50% under procurement
33% at the site and 67% under procurement
Is artificially introduced
Is represented by a dotted line
Does not consume time
All the above
Only (i) is correct
(i) and (ii) are correct
(i) and (iii) are correct
(ii) and (iii) are correct
Total float and free float
Total float and independent float
Free float and independent float
None of the above
Preparation of specifications
Preparation of estimates
Initiating the procurement action of resources
All the above
Forward pass is used for calculating earliest expected time
Backward pass is used for calculating the latest occurrence time
Maximum value of earliest expected time is used if there is more than one value of any event
All the above
A project is divided into various activities
Required time for each activity is established
Net work is drawn by connecting the activities and the events
All the above
Light construction
Heavy construction
Industrial construction
None of these
Duration
Total float
Free float
Interfering float
Shows the interdependencies of various jobs
Depicts the delay of jobs, if any
Points outgoing ahead of schedule of jobs, if any
None of these
Rs. 4,75,000
Rs. 5,75,000
Rs. 6,50,000
Rs. 8,50,000
Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest finish time and earliest start time for its successor activity
Its earliest finish time and latest start time for its successor activity
Trimming and finishing
Shaping and trimming
Finishing and shaping
Finishing, shaping and trimming
Rs. 31050
Rs. 34500
Rs. 37950
Rs. 50000
Resource levelling
Resource smoothening
Updating
Critical path scheduling
Normal distribution curve
Poisson's distribution curve
Beta distribution curve
None of the above