Optimistic time
Pessimistic time
Most likely time
All the above
D. All the above
Concrete cured
Fixing of door
Plastering of walls
Selecting sites
Site survey
Availability of construction materials
Availability of labour
All the above
(t1 - t2) - t
t - (t1 - t2)
(t1 + t2) - t
t + (t1 - t2)
Crash time
Normal time
Optimistic time
Between normal time and crash time
The detailed estimated cost based on detailed design
The several alternatives of the project that have been considered
The soil survey, traffic survey, concept design and approximate cost
The contract documents for inviting tenders
Bar chart method
Milestone chart
Critical path method (CPM)
Programme Evaluation and Review Technique (PERT)
LST-EST
LFT-EFT
TL-EFT
All the above
The activity is the time consuming part of a project
The beginning and end of a job, are called events
The activity which consumes maximum time, is called a node
Logically and sequentially connected activities and events form a network
Controlling the total quantity at each batch
Weighing accurately, the quantity of each material for a job before mixing
Controlling the quantity of each material into each batch
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
2 kg/tonne
6 kg/tonne
9 kg/tonne
20 kg/tonne
Light construction
Heavy construction
Industrial construction
Electrical construction
Having a single lump, are called uninodal curves
If symmetrical, are called normal curves
If not symmetrical, are called skew curves
All the above
Normal durations for all the activities
Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Free float of the activity must be zero but independent float need not be zero
Independent float must be zero but free float need not be zero
Free float and independent float both must be zero
Free float and independent float both need not be zero
(i) and (iii) are correct
(i) and (iv) are correct
(ii) and (iii) are correct
(ii) and (iv) are correct
Ice
Concrete
Loose sand
Earth
The various functions under each activity, are shown by one bar on Bar Charts
Bar chart establishes the interdependency of one event on another
Only approximate percentage of the completed work is reported
None of these
Duration
Total float
Free float
Interfering float
1, 2 and 3 are correct
1 and 4 are correct
2, 3 and 4 are correct
1, 2 and 4 are correct
Concrete
Loose sand
Asphalt
Firm earth
(a + m + b)/6
(a + 2m + b)/6
(a + 4m + b)/6
(a + 5m + b)/6
The difference of latest occurrence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above
Total duration of project is reduced
Total duration of project is increased
Uniform demand of resources is achieved
Cost of project is controlled
Identify the activities which can be delayed without affecting the total float of preceding activity
Identify the activities, which can be delayed without affecting the total float of succeeding activity
Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Strict adherence to specifications
Separation of planning and design part
Each individual maintains functional efficiency
All the above
Equal to X
More than X
Less than X
Any of the above
Normal time
Slow time
Crash time
Standard time
Light construction
Heavy construction
Industrial construction
Private construction
Moist loam
Good common earth
Well blasted rock
Wet sticky clay
500 cum
1000 cum
1500 cum
2000 cum