Its latest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest start time and earliest finish time
Its earliest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
Rs. 1740
Rs. 3480
Rs. 5220
Rs. 6960
The various functions under each activity, are shown by one bar on Bar Charts
Bar chart establishes the interdependency of one event on another
Only approximate percentage of the completed work is reported
None of these
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications
The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
The difference between the maximum time available for the job and actual time it consumes, is called total float
The difference between the latest start time and earliest start time of an activity, is called total float
None of these
Rs. 31050
Rs. 34500
Rs. 37950
Rs. 50000
Concrete
Loose sand
Asphalt
Firm earth
Identify the activities which can be delayed without affecting the total float of preceding activity
Identify the activities, which can be delayed without affecting the total float of succeeding activity
Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Having a single lump, are called uninodal curves
If symmetrical, are called normal curves
If not symmetrical, are called skew curves
All the above
Activity arrows in a CPM network are drawn to scale
The tail of an arrow represents the finish of an activity
Arrow bead represents the start of an activity
None of the above
50 %
Less than 50 %
More than 50 %
100 %
1 and 4 are correct
2 and 3 are correct
1 and 4 are correct
1 and 2 are correct
1, 2, 4, 3, 5
1, 3, 2, 4, 5
1, 2, 3, 4, 5
1, 3, 4, 2, 5
An analytic in concept
Limited of event oriented diagrams
Used for research and development projects
All the above
Kneading
Pressing
Tamping
Vibration
An engineer
An architect
An owner
All the above
Is always longest
Is always shortest
May be longest
May be shortest
Unity of command
Effective control at all levels
Delegation of authority
All the above
2.3% and 84.1%
97.7% and 84.1%
97.7 % and 15.9%
15.9% and 97.7%
Drag line
Hoe
Clam shell
Dipper shovel
Moist loam
Sand and gravel
Good common earth
Wet sticky clay
(a + m + b)/6
(a + 2m + b)/6
(a + 4m + b)/6
(a + 5m + b)/6
(i), (ii) and (iv) are correct
(ii), (iii) and (iv) are correct
(i), (iii) and (iv) are correct
(i), (ii) and (iii) are correct
Rs. 8,800
Rs. 7,600
Rs. 6,400
Rs. 5,000
Minor works
Major works
Large projects
All the Above
Event
Float
Duration
Constraint
Vertical lines
Horizontal lines
Dots
Crosses
Is artificially introduced
Is represented by a dotted line
Does not consume time
All the above
Line organisation
Line and staff organisation
Functional organisation
None of these
Executive Engineer
Engineer
Junior Engineer
Assistant Engineer
19
14
24
None of these