What is the correct answer?

4

A pointed arch which forms isosceles or equilateral triangle, is generally known as

A. Three centred arch

B. Two centred arch

C. Lancet arch

D. Bull's eye arch

Correct Answer :

C. Lancet arch


Related Questions

What is the correct answer?

4

The nominal thickness of one brick wall in mm, is

A. 90 mm

B. 150 mm

C. 190 mm

D. 200 mm

What is the correct answer?

4

The important test to be conducted on a stone used in docks and harbours is

A. Hardness test

B. Workability test

C. Weight test

D. Toughness test

What is the correct answer?

4

During percussion drilling

A. Ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole

B. Caving or mixing of strata are caused in soft soils or cohesionless soils

C. The soil to a considerable depth below the bottom of the hole gets disturbed

D. All the above

What is the correct answer?

4

To stagger vertical joints in successive courses of a wall, a piece of brick is generally used at the end of the course, which is known as

A. Bat

B. Header

C. Stretcher

D. Closer

What is the correct answer?

4

In ordinary residential and public buildings, the damp proof course is generally provided at

A. Ground level

B. Plinth level

C. Water table level

D. Midway ground level and water-table level

What is the correct answer?

4

Raft foundations are used for:

A. Providing increased area of foundation over poor bearing capacity of soil

B. Spanning over small soft or loose pockets

C. Counter acting the hydrostatic effect

D. All the above

What is the correct answer?

4

The vertical members fixed between steps and hand rail, are known

A. Balusters

B. Strings

C. Newel posts

D. Soffits

What is the correct answer?

4

The piece of a brick cut along the centre of width in such a way that its length is equal to that of full brick, is called

A. Half brick

B. Queen closer

C. King closer

D. Bevelled closer

What is the correct answer?

4

A pointed arch which forms isosceles or equilateral triangle, is generally known as

A. Three centred arch

B. Two centred arch

C. Lancet arch

D. Bull's eye arch

What is the correct answer?

4

While investigating the site, a thick layer of fairly firm clay over a deep layer of soft clay is encountered. In such a situation, the following type of foundation is useful:

A. Pile formation

B. Raft foundation

C. Grillage foundation

D. None of these

What is the correct answer?

4

Depth or height of the arch is the

A. Perpendicular distance between intrados and extrados

B. Vertical distance between springing line and intrados

C. Perpendicular distance between springing line and extrados

D. None of the above

What is the correct answer?

4

An arch constructed with finely dressed stones, is known

A. Ashlar arch

B. Rubble arch

C. Gauged arch

D. Axed arch

What is the correct answer?

4

The construction joints in buildings are provided after

A. 10 m

B. 15 m

C. 20 m

D. 40 m

What is the correct answer?

4

The pile provided with one or more bulles in its vertical shaft, is generally known as

A. Under-ream pile

B. Friction pile

C. Bearing pile

D. Sheet pile

What is the correct answer?

4

In high mountainous region, the type of roof generally recommended for buildings, is

A. Shed type

B. Gable type

C. Gambrel type

D. Mansard type

What is the correct answer?

4

Single Flemish bond consists of

A. Double Flemish bond facing and English bond backing in each course

B. English bond facing and double Flemish bond backing in each course

C. Stretcher bond facing and double Flemish bond backing in each course

D. Double Flemish bond facing and header bond backing in each course

What is the correct answer?

4

The floor is rubbed with oxalic acid, for making its surface

A. Free from voids

B. Glossy

C. Durable

D. Uniform

What is the correct answer?

4

The width of the hollow space between two walls of a cavity wall should not exceed

A. 5 cm

B. 7.5 cm

C. 10 cm

D. 15 cm

What is the correct answer?

4

Sum of tread and rise must lie between

A. 300 to 350 mm

B. 400 to 450 mm

C. 500 to 550 mm

D. 600 to 650 mm

What is the correct answer?

4

For providing a raft foundation, the following activities are involved
1. Ramming the foundation bed
2. Excavation of the soil upto required depth
3. Laying the reinforcement over the foundation bed
4. Curing the cement concrete placed over reinforcement
5. Pouring the cement concrete over the reinforcement The correct sequence is

A. 1, 2, 3, 4, 5

B. 5, 4, 3, 2, 1

C. 2, 1, 3, 5, 4

D. 3, 2, 5, 1, 4

What is the correct answer?

4

The pile which is provided with a bulb filled with concrete at its lower end, is known as

A. Simplex pile

B. Mac-Arthur pile

C. Raymond pile

D. Franki pile

What is the correct answer?

4

The size of a floor tile commonly used, is

A. 15 cm × 15 cm × 1.8 cm

B. 20 cm × 20 cm × 2 cm

C. 22.5 × 22.5 cm × 2.2 cm

D. All the above

What is the correct answer?

4

The maximum total settlement for raft foundation on clayey soils should be limited to

A. 25 mm

B. 25 to 40 mm

C. 40 to 65 mm

D. 65 to 100 mm

What is the correct answer?

4

The additional piles which are driven to increase the capacity of supporting loads on vertical piles, are known

A. Construction piles

B. Raking piles

C. Eccentric piles

D. Sinking piles

What is the correct answer?

4

The depth of the ground water table may be ascertained by

A. Looking through the well in the vicinity

B. Standing on the well in the vicinity

C. Measuring the depth of water in the well

D. None of the above

What is the correct answer?

4

The bond in which headers and stretchers are laid in alternate courses and every stretcher course is started with a three fourth brick bat, is known as

A. English cross bond

B. Dutch bond

C. Monk bond

D. Rat-trap bond

What is the correct answer?

4

The depth of concrete bed of the foundation depends upon

A. The projection of the concrete block beyond the footing over it

B. The upward soil pressure

C. The mix of the concrete

D. All the above

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. In dog-legged stairs, no space between its flights is provided

B. In open newel stair, a rectangular well is provided

C. In geometric stair, a curved shaped well between forward and backward flights, is provided

D. In geometrical stair, two quarter space landing is provided

What is the correct answer?

4

The depth of an arch is the distance between

A. Ground level and springing line

B. Crown and springing line

C. Crown and ground level

D. Intrados and extrados

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. In king post truss, one vertical post is used

B. In a queen post truss, one vertical post is used

C. In a queen post truss, two vertical posts are used

D. None of these