Light construction
Heavy construction
Industrial construction
Private construction
A. Light construction
Cheapest critical activity
Cheapest noncritical activity
Costliest critical activity
Costliest noncritical activity
The difference of latest occurrence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above
Should invest in neither of the two projects
Could invest in either of the two projects
Should invest in project A
Should invest in project B
Hoe
Shovel
Dragline
None of the above
20
25
35
15
Normal distribution curve
Poisson's distribution curve
Beta distribution curve
None of the above
Bar chart
Gantt chart
Modified Mile stone chart
All the above
Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest finish time and earliest start time for its successor activity
Its earliest finish time and latest start time for its successor activity
Crash time
Normal time
Optimistic time
Between normal time and crash time
1, 3, 2, 4
3, 1, 4, 2
3, 1, 2, 4
1, 3, 4, 2
Site investigation started
Sessional work completed
Bus starts from Jaipur
Class is being attended
Digging of foundation started
Digging of foundation completed
Laying of concrete started
All the above
Strict adherence to specifications
Separation of planning and design part
Each individual maintains functional efficiency
All the above
2.3% and 84.1%
97.7% and 84.1%
97.7 % and 15.9%
15.9% and 97.7%
Identify the activities which can be delayed without affecting the total float of preceding activity
Identify the activities, which can be delayed without affecting the total float of succeeding activity
Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Measurement of risks to eliminate failures
Applying the theory' of probability to sample testing or inspection
Reduction in wastage of inspection costs
Reduction in costs for the removal of defects
The activity is the time consuming part of a project
The beginning and end of a job, are called events
The activity which consumes maximum time, is called a node
Logically and sequentially connected activities and events form a network
Earliest expected time is denoted by TE
Latest occurrence time is denoted by TL
Contractual obligation time is denoted by Ts
All the above
Departmental representative or user
Local civil authority representative
Representative of engineer authority
All the above
Earliest start of an activity is the early event time of the node it leaves.
Latest finish of an activity is the late event time of the node it enters.
Latest start of an activity is its latest finish minus its duration.
None of the above
Line organisation
Line and staff organisation
Functional organisation
Effective organisation
An analytic in concept
Limited of event oriented diagrams
Used for research and development projects
All the above
Equal to X
More than X
Less than X
Any of the above
Acquisition of land
Selection of site
Fmalisation of alignment of work
All the above
A circle
A square
A triangle
All the above
3.5 and 5/6
5 and 25/36
3.5 and 25/36
4 and 5/6
Most likely time
Optimistic time
Pessimistic time
Expected time
Free float of the activity must be zero but independent float need not be zero
Independent float must be zero but free float need not be zero
Free float and independent float both must be zero
Free float and independent float both need not be zero
Any project
Major projects
Minor projects
All the above
Site located
Foundation is being dug
The office area is being cleaned
The invitations are being sent