Home
Current Affairs January 2024

What is the correct answer?

4

Which of the following is not a PERT event?

A. Site investigation started

B. Sessional work completed

C. Bus starts from Jaipur

D. Class is being attended

Correct Answer :

D. Class is being attended


Related Questions

What is the correct answer?

4

Henry Gantt developed Bar charts for planning and scheduling of projects in

A. 1880

B. 1900

C. 1920

D. 1940

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All the Above

What is the correct answer?

4

Time and progress chart of a construction, is also known as

A. Bar chart

B. Gantt chart

C. Modified Mile stone chart

D. All the above

What is the correct answer?

4

Select the incorrect statement.

A. A critical path always begins at the very first event.

B. A critical path always terminates at the last event.

C. Critical activities control the project duration.

D. Critical activity is the one for which free float is zero.

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not consume time

D. All the above

What is the correct answer?

4

If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is

A. 4 days

B. 6 days

C. 10 days

D. 16 days

What is the correct answer?

4

If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is

A. 30 kg

B. 300 kg

C. 900 kg

D. 1000 kg

What is the correct answer?

4

In the given figure, the network of a project represents

A. Activity of an excavation of a footing

B. Activity of an excavation which starts at event No. 1 and ends at even No. 2

C. Activity of excavation which takes 8 units of time

D. None of these

What is the correct answer?

4

For a given size of bucket, the ideal output of a dragline will be least in

A. Moist loam

B. Sand and gravel

C. Good common earth

D. Wet sticky clay

What is the correct answer?

4

PERT is

A. An analytic in concept

B. Limited of event oriented diagrams

C. Used for research and development projects

D. All the above

What is the correct answer?

4

Which of the following earth moving machines has the shortest cycle time?

A. Drag line

B. Hoe

C. Clam shell

D. Dipper shovel

What is the correct answer?

4

Updating may result in

A. Change of critical path

B. Decrease of project completion time

C. Increase of project completion time

D. All of the above

What is the correct answer?

4

Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?

A. Ice

B. Concrete

C. Loose sand

D. Earth

What is the correct answer?

4

Pick up the correct statement from the following:

A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'

B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float

C. The difference between total float and free float, is called interfering float

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. Optimistic time estimate refers to activities

B. Pessimistic time estimate refers to activities

C. Most likely time estimate refers to activities

D. All the above

What is the correct answer?

4

The time which results in the leasi, possible construction cost of an activity, is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

What is the correct answer?

4

Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

A. 20

B. 25

C. 35

D. 15

What is the correct answer?

4

Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?

A. Concrete

B. Loose sand

C. Asphalt

D. Firm earth

What is the correct answer?

4

Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is

A. 1, 3, 2, 4

B. 3, 1, 4, 2

C. 3, 1, 2, 4

D. 1, 3, 4, 2

What is the correct answer?

4

Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is

A. 1, 2, 4, 3, 5

B. 1, 3, 2, 4, 5

C. 1, 2, 3, 4, 5

D. 1, 3, 4, 2, 5

What is the correct answer?

4

The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

A. Total float

B. Free float

C. Interfering float

D. Independent float

What is the correct answer?

4

If TL is the latest allowable event occurrence time, total activity slack(s), is equal to

A. LST-EST

B. LFT-EFT

C. TL-EFT

D. All the above

What is the correct answer?

4

In time-cost optimization of a project, crashing is done.

A. On all the activities

B. On all the activities lying on the critical path

C. Only on activities lying on the original critical path and having flatter cost slopes

D. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The various functions under each activity, are shown by one bar on Bar Charts

B. Bar chart establishes the interdependency of one event on another

C. Only approximate percentage of the completed work is reported

D. None of these

What is the correct answer?

4

The main disadvantage of line organisation, is

A. Rigid structure

B. Extraordinary delay in communications

C. Top level executions over work

D. All the above

What is the correct answer?

4

The salient feature of functional organisation is

A. Strict adherence to specifications

B. Separation of planning and design part

C. Each individual maintains functional efficiency

D. All the above

What is the correct answer?

4

Which of the following is a weakness of bar chart?

A. Interdependencies of activities

B. Project progress

C. Uncertainties

D. All of the above

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

A. Longest duration

B. Highest cost slope

C. Least cost slope

D. Shortest duration

What is the correct answer?

4

For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

A. Moist loam

B. Good common earth

C. Well blasted rock

D. Wet sticky clay