Home
Current Affairs January 2024

What is the correct answer?

4

In PERT analysis, the time estimates of activities and probability of their occurrence follow

A. Normal distribution curve

B. Poisson's distribution curve

C. Beta distribution curve

D. None of the above

Correct Answer :

C. Beta distribution curve


Related Questions

What is the correct answer?

4

Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?

A. Concrete

B. Loose sand

C. Asphalt

D. Firm earth

What is the correct answer?

4

Final technical authority of a project lies with

A. Assistant Engineer

B. Executive Engineer

C. Superintending Engineer

D. Chief Engineer

What is the correct answer?

4

The most suitable type of equipment for compaction of cohesive soils is

A. Smooth-wheeled rollers

B. Vibratory rollers

C. Sheep foot rollers

D. Tampers

What is the correct answer?

4

An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

A. Rs. 31050

B. Rs. 34500

C. Rs. 37950

D. Rs. 50000

What is the correct answer?

4

The difference between the time avail-to do a job and the time required to do the job, is known as

A. Event

B. Float

C. Duration

D. Constraint

What is the correct answer?

4

While filling the tender for any work, the contractor considers

A. Site survey

B. Availability of construction materials

C. Availability of labour

D. All the above

What is the correct answer?

4

Sensitivity analysis is a study of

A. Comparison of profit and loss

B. Comparison of assets and liabilities

C. Change in output due to change in input

D. Economics of cost and benefits of the project

What is the correct answer?

4

Which of the following excavators is most suitable for digging under water?

A. Drag line

B. Hoe

C. Clam shell

D. Dipper shovel

What is the correct answer?

4

The process of incorporating changes and rescheduling or replanning is called

A. Resource levelling

B. Resource smoothening

C. Updating

D. Critical path scheduling

What is the correct answer?

4

Pick up the correct statement from the following:

A. The float may be positive, zero or negative

B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed

C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

D. All the above

What is the correct answer?

4

If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is

A. 500 cum

B. 1000 cum

C. 1500 cum

D. 2000 cum

What is the correct answer?

4

The Overall in-charge of an organisation at the site responsible for the execution of the works, is

A. Executive Engineer

B. Engineer

C. Junior Engineer

D. Assistant Engineer

What is the correct answer?

4

The final selection of a construction site, is done by

A. Departmental representative or user

B. Local civil authority representative

C. Representative of engineer authority

D. All the above

What is the correct answer?

4

Pick up the PERT event from the following:

A. Digging of foundation started

B. Digging of foundation completed

C. Laying of concrete started

D. All the above

What is the correct answer?

4

A critical ratio scheduling

A. Determines the status of each activity

B. Adjusts automatically changes in activity progress

C. Is a dynamic system

D. None of these

What is the correct answer?

4

The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to

A. 2 kg/tonne

B. 6 kg/tonne

C. 9 kg/tonne

D. 20 kg/tonne

What is the correct answer?

4

Select the incorrect statement.

A. A critical path always begins at the very first event.

B. A critical path always terminates at the last event.

C. Critical activities control the project duration.

D. Critical activity is the one for which free float is zero.

What is the correct answer?

4

Critical path lies along the activities having total float

A. Positive

B. Negative

C. Zero

D. Same

What is the correct answer?

4

The first method invented for planning projects, was

A. Bar chart method

B. Milestone chart

C. Critical path method (CPM)

D. Programme Evaluation and Review Technique (PERT)

What is the correct answer?

4

Critical path method

A. Is an improvement upon bar chart method

B. Provides a realistic approach to daily problems

C. Avoids delays which are very common in bar charts

D. All the above

What is the correct answer?

4

In PERT analysis, the time estimates of activities and probability of their occurrence follow

A. Normal distribution curve

B. Poisson's distribution curve

C. Beta distribution curve

D. None of the above

What is the correct answer?

4

Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

A. 20

B. 25

C. 35

D. 15

What is the correct answer?

4

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

A. (a + m + b)/6

B. (a + 2m + b)/6

C. (a + 4m + b)/6

D. (a + 5m + b)/6

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All the Above

What is the correct answer?

4

Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements

A. Only (i) is correct

B. (i) and (ii) are correct

C. (i) and (iii) are correct

D. (ii) and (iii) are correct

What is the correct answer?

4

Works costing less than Rs. 20,000 are treated as

A. Any project

B. Major projects

C. Minor projects

D. All the above

What is the correct answer?

4

The salient feature of functional organisation is

A. Strict adherence to specifications

B. Separation of planning and design part

C. Each individual maintains functional efficiency

D. All the above

What is the correct answer?

4

Time and progress chart of a construction, is also known as

A. Bar chart

B. Gantt chart

C. Modified Mile stone chart

D. All the above

What is the correct answer?

4

Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is

A. 1, 3, 2, 4

B. 3, 1, 4, 2

C. 3, 1, 2, 4

D. 1, 3, 4, 2

What is the correct answer?

4

Pick up the correct statement from the following:

A. Programme Evaluation and Review Technique, is event oriented

B. Programme Evaluation and Review Technique is not event oriented

C. Critical Path Method is event oriented

D. Critical Path method is event oriented