3.5 and 5/6
5 and 25/36
3.5 and 25/36
4 and 5/6
C. 3.5 and 25/36
Hoe
Shovel
Dragline
None of the above
Start float and finish float are always equal.
Total float can be either start float or finish float.
Start float and finish float need not be equal.
Start float and finish float are the differences between activity times and not event times.
Site survey
Availability of construction materials
Availability of labour
All the above
The various functions under each activity, are shown by one bar on Bar Charts
Bar chart establishes the interdependency of one event on another
Only approximate percentage of the completed work is reported
None of these
A is correct but R is not correct
R is correct but A is not correct
Both A and R is correct
Both A and R is incorrect
An analytic in concept
Limited of event oriented diagrams
Used for research and development projects
All the above
Change of critical path
Decrease of project completion time
Increase of project completion time
All of the above
Vertical lines
Horizontal lines
Dots
Crosses
Measurement of risks to eliminate failures
Applying the theory' of probability to sample testing or inspection
Reduction in wastage of inspection costs
Reduction in costs for the removal of defects
Smooth-wheeled rollers
Vibratory rollers
Sheep foot rollers
Tampers
Small projects
Large and complex projects
Research and development projects
Deterministic activities
Cheapest critical activity
Cheapest noncritical activity
Costliest critical activity
Costliest noncritical activity
Increase in rates of only important materials
Variation in cost in materials element, labour element and petrol-oillubricant element
Variation in total cost of the project on an ad hoc basis
Rate of inflation
3425 kg
5515 kg
4350 kg
2975 kg
CPA (Critical Path Analysis)
CPP (Critical Path Plotted)
MCE (Minimum Cost Expenditure)
All the above
1, 2, 4, 3, 5
1, 3, 2, 4, 5
1, 2, 3, 4, 5
1, 3, 4, 2, 5
Resources
Project duration time
Both resources and project duration time
None of the above
1, 3 and 4 are correct
2, 3 and 4 are correct
1, 2 and 3 are correct
1, 2 and 4 are correct
The difference of latest occurrence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above
Normal distribution curve
Poisson's distribution curve
Beta distribution curve
None of the above
Effective command and control
Rigid discipline in the organisation
Defined responsibilities at all levels
All the above
Drag line
Hoe
Clam shell
Dipper shovel
Having a single lump, are called uninodal curves
If symmetrical, are called normal curves
If not symmetrical, are called skew curves
All the above
Departmental representative or user
Local civil authority representative
Representative of engineer authority
All the above
Comparison of profit and loss
Comparison of assets and liabilities
Change in output due to change in input
Economics of cost and benefits of the project
3.5 and 5/6
5 and 25/36
3.5 and 25/36
4 and 5/6
Crash time
Normal time
Optimistic time
Between normal time and crash time
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications
Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest finish time and earliest start time for its successor activity
Its earliest finish time and latest start time for its successor activity
CPM analysis is activity oriented
PERT analysis is event oriented
In CPM, the time is related to cost
All the above