The activity is the time consuming part of a project
The beginning and end of a job, are called events
The activity which consumes maximum time, is called a node
Logically and sequentially connected activities and events form a network
C. The activity which consumes maximum time, is called a node
Assistant Engineer
Executive Engineer
Superintending Engineer
Chief Engineer
8 days
9 days
10 days
15 days
The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
The difference between total float and free float, is called interfering float
All the above
A person
A firm
An agency
All the above
Both A and R is true and R is the correct explanation of A
Both A and R is true but R is not the correct explanation of A
A is true but R is false
A is false but R is true
3.7 years
4.23 years
5 years
7.87 years
Minimum
Maximum
Zero
Infinite
Kneading
Pressing
Tamping
Vibration
Rs. 1740
Rs. 3480
Rs. 5220
Rs. 6960
Equal to X
More than X
Less than X
Any of the above
Is artificially introduced
Is represented by a dotted line
Does not consume time
All the above
3.5 and 5/6
5 and 25/36
3.5 and 25/36
4 and 5/6
Determines the status of each activity
Adjusts automatically changes in activity progress
Is a dynamic system
None of these
Planning
Designing
Execution
All the above
Having a single lump, are called uninodal curves
If symmetrical, are called normal curves
If not symmetrical, are called skew curves
All the above
Duration
Total float
Free float
Interfering float
1910
1920
1930
1940
50 %
84.1 %
99.9 %
100 %
Interdependencies of activities
Project progress
Uncertainties
All of the above
Emphasis is given to activities
Uncertainties are not allowed
Activities are represented by arrows
All the above
20
25
35
15
An analytic in concept
Limited of event oriented diagrams
Used for research and development projects
All the above
Rs. 8,43,750
Rs. 8,75,000
Rs. 10,50,000
Rs. 11,56,250
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications
The activity is the time consuming part of a project
The beginning and end of a job, are called events
The activity which consumes maximum time, is called a node
Logically and sequentially connected activities and events form a network
Reduce by 200 kg
Increase by 200 kg
Increase by 250 kg
Reduce by 250 kg
Departmental representative or user
Local civil authority representative
Representative of engineer authority
All the above
Only (i) is correct
(i) and (ii) are correct
(i) and (iii) are correct
(ii) and (iii) are correct
CPM analysis is activity oriented
PERT analysis is event oriented
In CPM, the time is related to cost
All the above
Strict adherence to specifications
Separation of planning and design part
Each individual maintains functional efficiency
All the above