1, 3, 2, 4
3, 1, 4, 2
3, 1, 2, 4
1, 3, 4, 2
C. 3, 1, 2, 4
The float may be positive, zero or negative
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
If the float of an activity is negative, delay in its performance is bound to delay the completion of project
All the above
10000 kg
12500 kg
22500 kg
5000 kg
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost
Increasing the direct cost and indirect cost both
Decreasing the direct cost and indirect cost both
3.7 years
4.23 years
5 years
7.87 years
Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest finish time and earliest start time for its successor activity
Its earliest finish time and latest start time for its successor activity
Event
Free float
Dummy
Constraint
1, 2, 4, 3, 5
1, 3, 2, 4, 5
1, 2, 3, 4, 5
1, 3, 4, 2, 5
Executive Engineer
Engineer
Junior Engineer
Assistant Engineer
A is correct but R is not correct
R is correct but A is not correct
Both A and R is correct
Both A and R is incorrect
Both A and R is true and R is the correct explanation of A
Both A and R is true but R is not the correct explanation of A
A is true but R is false
A is false but R is true
Preceding activities
Succeeding activities
The particular activity involved
None of the above
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications
100% at the site
67% at the site and 33% under procurement
50% at the site and 50% under procurement
33% at the site and 67% under procurement
Rs. 1740
Rs. 3480
Rs. 5220
Rs. 6960
Should invest in neither of the two projects
Could invest in either of the two projects
Should invest in project A
Should invest in project B
Started 5 days later
Completed 5 days later
Performed at slower rate in 15 days
All the above
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
Line organisation
Line and staff organisation
Functional organisation
None of these
Start float and finish float are always equal.
Total float can be either start float or finish float.
Start float and finish float need not be equal.
Start float and finish float are the differences between activity times and not event times.
Any project
Major projects
Minor projects
All the above
Interdependencies of activities
Project progress
Uncertainties
All of the above
The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
The difference between the maximum time available for the job and actual time it consumes, is called total float
The difference between the latest start time and earliest start time of an activity, is called total float
None of these
50 %
Less than 50 %
More than 50 %
100 %
Activity of an excavation of a footing
Activity of an excavation which starts at event No. 1 and ends at even No. 2
Activity of excavation which takes 8 units of time
None of these
Instructions by the executive engineers
Construction measurements
Issue of store equipments
Names of the casual labour
Synthesising in concepts
Is built of activities oriented programme
Is based on time estimate
All the above
Having a single lump, are called uninodal curves
If symmetrical, are called normal curves
If not symmetrical, are called skew curves
All the above
(i), (ii) and (iv) are correct
(ii), (iii) and (iv) are correct
(i), (iii) and (iv) are correct
(i), (ii) and (iii) are correct
Identify the activities which can be delayed without affecting the total float of preceding activity
Identify the activities, which can be delayed without affecting the total float of succeeding activity
Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Yes, because of heavier overheads and handling cost
Yes, because of the very high order of quality control for the factory made components
No, because of repetitive manufacture of a number of elements
No, because of savings in site labour