Preceding activities
Succeeding activities
The particular activity involved
None of the above
C. The particular activity involved
Concrete
Loose sand
Asphalt
Firm earth
Rs. 8,43,750
Rs. 8,75,000
Rs. 10,50,000
Rs. 11,56,250
Preparation of specifications
Preparation of estimates
Initiating the procurement action of resources
All the above
Concrete cured
Fixing of door
Plastering of walls
Selecting sites
The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
The difference between total float and free float, is called interfering float
All the above
Minimum time
Maximum time
Maximum cost
Minimum cost
Emphasis is given to activities
Uncertainties are not allowed
Activities are represented by arrows
All the above
Event
Free float
Dummy
Constraint
Effective command and control
Rigid discipline in the organisation
Defined responsibilities at all levels
All the above
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost
Increasing the direct cost and indirect cost both
Decreasing the direct cost and indirect cost both
Assistant Engineer
Executive Engineer
Superintending Engineer
Chief Engineer
Yes, because of heavier overheads and handling cost
Yes, because of the very high order of quality control for the factory made components
No, because of repetitive manufacture of a number of elements
No, because of savings in site labour
Ice
Concrete
Loose sand
Earth
Optimistic time
Pessimistic time
Most likely time
All the above
The detailed estimated cost based on detailed design
The several alternatives of the project that have been considered
The soil survey, traffic survey, concept design and approximate cost
The contract documents for inviting tenders
1, 3 and 4 are correct
2, 3 and 4 are correct
1, 2 and 3 are correct
1, 2 and 4 are correct
Cheapest critical activity
Cheapest noncritical activity
Costliest critical activity
Costliest noncritical activity
Hoe
Shovel
Dragline
None of the above
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications
Bar chart
Gantt chart
Modified Mile stone chart
All the above
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
The various functions under each activity, are shown by one bar on Bar Charts
Bar chart establishes the interdependency of one event on another
Only approximate percentage of the completed work is reported
None of these
Line organisation
Line and staff organisation
Functional organisation
Effective organisation
Digging of foundation started
Digging of foundation completed
Laying of concrete started
All the above
50 %
Less than 50 %
More than 50 %
100 %
1, 3, 2, 4
3, 1, 4, 2
3, 1, 2, 4
1, 3, 4, 2
Earliest expected time is denoted by TE
Latest occurrence time is denoted by TL
Contractual obligation time is denoted by Ts
All the above
Any project
Major projects
Minor projects
All the above
To concentrate his attention on critical activities
To divert the resources from non-critical advanced activities to critical activities
To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
All the above
1-2 is 4
2-3 is 7
3-4 is 8
All the above