What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity

B. The difference between the maximum time available for the job and actual time it consumes, is called total float

C. The difference between the latest start time and earliest start time of an activity, is called total float

D. None of these

Correct Answer :

D. None of these


Related Questions

What is the correct answer?

4

For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

A. 8 days

B. 9 days

C. 10 days

D. 15 days

What is the correct answer?

4

Economic saving of time results by crashing

A. Cheapest critical activity

B. Cheapest noncritical activity

C. Costliest critical activity

D. Costliest noncritical activity

What is the correct answer?

4

Which of the following does not represent an activity?

A. Site located

B. Foundation is being dug

C. The office area is being cleaned

D. The invitations are being sent

What is the correct answer?

4

Critical path method

A. Is an improvement upon bar chart method

B. Provides a realistic approach to daily problems

C. Avoids delays which are very common in bar charts

D. All the above

What is the correct answer?

4

For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

A. 1

B. 2

C. 3

D. 4

What is the correct answer?

4

For excavating utility trenches with precise control of depth, the excavation equipment used is

A. Hoe

B. Shovel

C. Dragline

D. None of the above

What is the correct answer?

4

Mile Stone charts were invented in the year of

A. 1910

B. 1920

C. 1930

D. 1940

What is the correct answer?

4

The main advantage of line organisation is:

A. Effective command and control

B. Rigid discipline in the organisation

C. Defined responsibilities at all levels

D. All the above

What is the correct answer?

4

The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

A. Total float

B. Free float

C. Interfering float

D. Independent float

What is the correct answer?

4

The technique for establishing and maintaining priorities among the various jobs of a project, is known

A. Event flow scheduling technique

B. Critical ratio scheduling

C. Slotting technique for scheduling

D. Short interval scheduling

What is the correct answer?

4

An event is indicated on the network by a number enclosed in

A. A circle

B. A square

C. A triangle

D. All the above

What is the correct answer?

4

Time and progress chart of a construction, is also known as

A. Bar chart

B. Gantt chart

C. Modified Mile stone chart

D. All the above

What is the correct answer?

4

A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will

A. Reduce by 200 kg

B. Increase by 200 kg

C. Increase by 250 kg

D. Reduce by 250 kg

What is the correct answer?

4

PERT analysis is based on

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All the above

What is the correct answer?

4

Mobilization advance up to 10% of the cost of work is given to a contractor

A. On commencement of work at site for payment of loan taken by him

B. For the purchase of construction materials

C. For the payment of advances to labour and other staff

D. For all activities required to start the work at site on finalization of the contract document

What is the correct answer?

4

Pick up the correct statement from the following:

A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'

B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float

C. The difference between total float and free float, is called interfering float

D. All the above

What is the correct answer?

4

Which of the following earth moving machines has the shortest cycle time?

A. Drag line

B. Hoe

C. Clam shell

D. Dipper shovel

What is the correct answer?

4

A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is

A. 10000 kg

B. 12500 kg

C. 22500 kg

D. 5000 kg

What is the correct answer?

4

A construction schedule is prepared after collecting

A. Number of operations

B. Output of labour

C. Output of machinery

D. All the above

What is the correct answer?

4

The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as

A. Event

B. Free float

C. Dummy

D. Constraint

What is the correct answer?

4

Completion of an activity on CPM network diagram, is generally known

A. Event

B. Node

C. Connector

D. All the above

What is the correct answer?

4

The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be

A. Rs. 8,800

B. Rs. 7,600

C. Rs. 6,400

D. Rs. 5,000

What is the correct answer?

4

The time corresponding to minimum total project cost is

A. Crash time

B. Normal time

C. Optimistic time

D. Between normal time and crash time

What is the correct answer?

4

If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be

A. 50 %

B. Less than 50 %

C. More than 50 %

D. 100 %

What is the correct answer?

4

Pick up the PERT event from the following:

A. Digging of foundation started

B. Digging of foundation completed

C. Laying of concrete started

D. All the above

What is the correct answer?

4

Consider the following statements: Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control. Of these statements

A. 1, 3 and 4 are correct

B. 2, 3 and 4 are correct

C. 1, 2 and 3 are correct

D. 1, 2 and 4 are correct

What is the correct answer?

4

Critical Path Net Work helps an engineer

A. To concentrate his attention on critical activities

B. To divert the resources from non-critical advanced activities to critical activities

C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

D. All the above

What is the correct answer?

4

Select the incorrect statement.

A. Start float and finish float are always equal.

B. Total float can be either start float or finish float.

C. Start float and finish float need not be equal.

D. Start float and finish float are the differences between activity times and not event times.

What is the correct answer?

4

For the network shown in the given figure, the expected time for the activity

A. 1-2 is 4

B. 2-3 is 7

C. 3-4 is 8

D. All the above

What is the correct answer?

4

Interfering float is the difference between

A. Total float and free float

B. Total float and independent float

C. Free float and independent float

D. None of the above