The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
The difference between the maximum time available for the job and actual time it consumes, is called total float
The difference between the latest start time and earliest start time of an activity, is called total float
None of these
D. None of these
8 days
9 days
10 days
15 days
Cheapest critical activity
Cheapest noncritical activity
Costliest critical activity
Costliest noncritical activity
Site located
Foundation is being dug
The office area is being cleaned
The invitations are being sent
Is an improvement upon bar chart method
Provides a realistic approach to daily problems
Avoids delays which are very common in bar charts
All the above
1
2
3
4
Hoe
Shovel
Dragline
None of the above
1910
1920
1930
1940
Effective command and control
Rigid discipline in the organisation
Defined responsibilities at all levels
All the above
Total float
Free float
Interfering float
Independent float
Event flow scheduling technique
Critical ratio scheduling
Slotting technique for scheduling
Short interval scheduling
A circle
A square
A triangle
All the above
Bar chart
Gantt chart
Modified Mile stone chart
All the above
Reduce by 200 kg
Increase by 200 kg
Increase by 250 kg
Reduce by 250 kg
Optimistic time
Pessimistic time
Most likely time
All the above
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
The difference between total float and free float, is called interfering float
All the above
Drag line
Hoe
Clam shell
Dipper shovel
10000 kg
12500 kg
22500 kg
5000 kg
Number of operations
Output of labour
Output of machinery
All the above
Event
Free float
Dummy
Constraint
Event
Node
Connector
All the above
Rs. 8,800
Rs. 7,600
Rs. 6,400
Rs. 5,000
Crash time
Normal time
Optimistic time
Between normal time and crash time
50 %
Less than 50 %
More than 50 %
100 %
Digging of foundation started
Digging of foundation completed
Laying of concrete started
All the above
1, 3 and 4 are correct
2, 3 and 4 are correct
1, 2 and 3 are correct
1, 2 and 4 are correct
To concentrate his attention on critical activities
To divert the resources from non-critical advanced activities to critical activities
To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
All the above
Start float and finish float are always equal.
Total float can be either start float or finish float.
Start float and finish float need not be equal.
Start float and finish float are the differences between activity times and not event times.
1-2 is 4
2-3 is 7
3-4 is 8
All the above
Total float and free float
Total float and independent float
Free float and independent float
None of the above