Home
Current Affairs January 2024

What is the correct answer?

4

Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is

A. 1, 2, 4, 3, 5

B. 1, 3, 2, 4, 5

C. 1, 2, 3, 4, 5

D. 1, 3, 4, 2, 5

Correct Answer :

C. 1, 2, 3, 4, 5


Related Questions

What is the correct answer?

4

Completion of an activity on CPM network diagram, is generally known

A. Event

B. Node

C. Connector

D. All the above

What is the correct answer?

4

The main advantage of line organisation is:

A. Effective command and control

B. Rigid discipline in the organisation

C. Defined responsibilities at all levels

D. All the above

What is the correct answer?

4

Mobilization advance up to 10% of the cost of work is given to a contractor

A. On commencement of work at site for payment of loan taken by him

B. For the purchase of construction materials

C. For the payment of advances to labour and other staff

D. For all activities required to start the work at site on finalization of the contract document

What is the correct answer?

4

Free float for any activity is defined as the difference between

A. Its earliest finish time and earliest start time for its successor activity

B. Its latest start time and earliest start time

C. Its latest finish time and earliest start time for its successor activity

D. Its earliest finish time and latest start time for its successor activity

What is the correct answer?

4

Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

A. 20

B. 25

C. 35

D. 15

What is the correct answer?

4

Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is

A. 1, 3, 2, 4

B. 3, 1, 4, 2

C. 3, 1, 2, 4

D. 1, 3, 4, 2

What is the correct answer?

4

If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is

A. 4 days

B. 6 days

C. 10 days

D. 16 days

What is the correct answer?

4

Interfering float is the difference between

A. Total float and free float

B. Total float and independent float

C. Free float and independent float

D. None of the above

What is the correct answer?

4

Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is

A. 1, 2, 4, 3, 5

B. 1, 3, 2, 4, 5

C. 1, 2, 3, 4, 5

D. 1, 3, 4, 2, 5

What is the correct answer?

4

If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

A. EF = ES + D

B. LS = LF - D

C. LF = LS + D

D. All the above

What is the correct answer?

4

While scheduling a project by C.P.M.

A. A project is divided into various activities

B. Required time for each activity is established

C. Net work is drawn by connecting the activities and the events

D. All the above

What is the correct answer?

4

The salient feature of functional organisation is

A. Strict adherence to specifications

B. Separation of planning and design part

C. Each individual maintains functional efficiency

D. All the above

What is the correct answer?

4

The Overall in-charge of an organisation at the site responsible for the execution of the works, is

A. Executive Engineer

B. Engineer

C. Junior Engineer

D. Assistant Engineer

What is the correct answer?

4

The most suitable type of equipment for compaction of cohesive soils is

A. Smooth-wheeled rollers

B. Vibratory rollers

C. Sheep foot rollers

D. Tampers

What is the correct answer?

4

Sinking fund is

A. The fund for rebuilding a structure when its economic life is over

B. Raised to meet maintenance costs

C. The total sum to be paid to the municipal authorities by the tenants

D. A part of the money kept in reserve for providing additional structures and structural modifications

What is the correct answer?

4

Which of the following earth moving machines has the shortest cycle time?

A. Drag line

B. Hoe

C. Clam shell

D. Dipper shovel

What is the correct answer?

4

For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

A. 8 days

B. 9 days

C. 10 days

D. 15 days

What is the correct answer?

4

Pick up the correct statement from the following:

A. The float may be positive, zero or negative

B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed

C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

D. All the above

What is the correct answer?

4

The reduction in project time normally results in

A. Decreasing the direct cost and increasing indirect cost

B. Increasing the direct cost and decreasing the indirect cost

C. Increasing the direct cost and indirect cost both

D. Decreasing the direct cost and indirect cost both

What is the correct answer?

4

Mile Stone charts were invented in the year of

A. 1910

B. 1920

C. 1930

D. 1940

What is the correct answer?

4

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

A. (a + m + b)/6

B. (a + 2m + b)/6

C. (a + 4m + b)/6

D. (a + 5m + b)/6

What is the correct answer?

4

Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth, (iv) Output can be increased by increasing the size of shovel. Of these statements

A. (ii), (iii) and (iv) are correct

B. (i), (ii) and (iv) are correct

C. (i), (iii) and (iv) are correct

D. (i) and (iv) are correct

What is the correct answer?

4

Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?

A. Ice

B. Concrete

C. Loose sand

D. Earth

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The various functions under each activity, are shown by one bar on Bar Charts

B. Bar chart establishes the interdependency of one event on another

C. Only approximate percentage of the completed work is reported

D. None of these

What is the correct answer?

4

Pick up the correct statement from the following:

A. Forward pass is used for calculating earliest expected time

B. Backward pass is used for calculating the latest occurrence time

C. Maximum value of earliest expected time is used if there is more than one value of any event

D. All the above

What is the correct answer?

4

Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of project PERT is preferred for planning because of

A. 1, 2 and 4

B. 3, 4 and 5

C. 1, 3 and 4

D. 1, 2 and 5

What is the correct answer?

4

The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is

A. 19

B. 14

C. 24

D. None of these

What is the correct answer?

4

If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

A. 3.5 and 5/6

B. 5 and 25/36

C. 3.5 and 25/36

D. 4 and 5/6

What is the correct answer?

4

In the given figure, the network of a project represents

A. Activity of an excavation of a footing

B. Activity of an excavation which starts at event No. 1 and ends at even No. 2

C. Activity of excavation which takes 8 units of time

D. None of these

What is the correct answer?

4

Pick up the correct statement from the following:

A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'

B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float

C. The difference between total float and free float, is called interfering float

D. All the above