The difference of latest occurrence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above
Assistant Engineer
Executive Engineer
Superintending Engineer
Chief Engineer
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
Moist loam
Sand and gravel
Good common earth
Wet sticky clay
Interdependencies of activities
Project progress
Uncertainties
All of the above
80 and 90
90 and 80
85 and 75
75 and 83
A circle
A square
A triangle
All the above
20
25
35
15
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost
Increasing the direct cost and indirect cost both
Decreasing the direct cost and indirect cost both
1
2
3
4
Minimum time
Maximum time
Maximum cost
Minimum cost
Is an improvement upon bar chart method
Provides a realistic approach to daily problems
Avoids delays which are very common in bar charts
All the above
Rigid structure
Extraordinary delay in communications
Top level executions over work
All the above
1, 2, 4, 3, 5
1, 3, 2, 4, 5
1, 2, 3, 4, 5
1, 3, 4, 2, 5
Activity of an excavation of a footing
Activity of an excavation which starts at event No. 1 and ends at even No. 2
Activity of excavation which takes 8 units of time
None of these
Forward pass is used for calculating earliest expected time
Backward pass is used for calculating the latest occurrence time
Maximum value of earliest expected time is used if there is more than one value of any event
All the above
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
All the above
Small projects
Large and complex projects
Research and development projects
Deterministic activities
Site investigation started
Sessional work completed
Bus starts from Jaipur
Class is being attended
Longest duration
Highest cost slope
Least cost slope
Shortest duration
Light construction
Heavy construction
Industrial construction
Private construction
30 kg
300 kg
900 kg
1000 kg
Kneading
Pressing
Tamping
Vibration
The float may be positive, zero or negative
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
If the float of an activity is negative, delay in its performance is bound to delay the completion of project
All the above
3.5 and 5/6
5 and 25/36
3.5 and 25/36
4 and 5/6
An activity of a project is denoted by an arrow on the net work
The tail of the arrow indicates the start of the activity
The head of the arrow indicates the end of the activity
The arrows are drawn to scale from left to right
The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
The difference between the maximum time available for the job and actual time it consumes, is called total float
The difference between the latest start time and earliest start time of an activity, is called total float
None of these
(a + m + b)/6
(a + 2m + b)/6
(a + 4m + b)/6
(a + 5m + b)/6
Resource levelling
Resource smoothening
Updating
Critical path scheduling
Event
Node
Connector
All the above