Home
Current Affairs January 2024

What is the correct answer?

4

The Overall in-charge of an organisation at the site responsible for the execution of the works, is

A. Executive Engineer

B. Engineer

C. Junior Engineer

D. Assistant Engineer

Correct Answer :

B. Engineer


Related Questions

What is the correct answer?

4

The final selection of a construction site, is done by

A. Departmental representative or user

B. Local civil authority representative

C. Representative of engineer authority

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. The difference of latest occurrence time and earliest expected time, is called slack

B. The activities connecting the events having zero slack, lie on the critical path

C. The critical path consumes the maximum time

D. All the above

What is the correct answer?

4

The time with which direct cost does not reduce with the increase in time is known as

A. Crash time

B. Normal time

C. Optimistic time

D. Standard time

What is the correct answer?

4

Consider the following statements: In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated. Of these statements

A. 1, 2 and 3 are correct

B. 1 and 4 are correct

C. 2, 3 and 4 are correct

D. 1, 2 and 4 are correct

What is the correct answer?

4

A critical ratio scheduling

A. Determines the status of each activity

B. Adjusts automatically changes in activity progress

C. Is a dynamic system

D. None of these

What is the correct answer?

4

The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is

A. 3425 kg

B. 5515 kg

C. 4350 kg

D. 2975 kg

What is the correct answer?

4

A construction schedule is prepared after collecting

A. Number of operations

B. Output of labour

C. Output of machinery

D. All the above

What is the correct answer?

4

Output of a bulldozer is
(i) Increased if drawbar HP of the tractor is increased for a given hauling distance
(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance
(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor
(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor
Of these statement

A. (i) and (iii) are correct

B. (i) and (iv) are correct

C. (ii) and (iii) are correct

D. (ii) and (iv) are correct

What is the correct answer?

4

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

A. Longest duration

B. Highest cost slope

C. Least cost slope

D. Shortest duration

What is the correct answer?

4

A CPM family includes

A. CPA (Critical Path Analysis)

B. CPP (Critical Path Plotted)

C. MCE (Minimum Cost Expenditure)

D. All the above

What is the correct answer?

4

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

A. to + 3tm+ tp/3

B. to + 4tm+ tp/4

C. to + 4tm+ tp/5

D. to + 4tm+ tp/6

What is the correct answer?

4

In PERT analysis, the time estimates of activities and probability of their occurrence follow

A. Normal distribution curve

B. Poisson's distribution curve

C. Beta distribution curve

D. None of the above

What is the correct answer?

4

The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively

A. 80 and 90

B. 90 and 80

C. 85 and 75

D. 75 and 83

What is the correct answer?

4

If TL is the latest allowable event occurrence time, total activity slack(s), is equal to

A. LST-EST

B. LFT-EFT

C. TL-EFT

D. All the above

What is the correct answer?

4

Completion of an activity on CPM network diagram, is generally known

A. Event

B. Node

C. Connector

D. All the above

What is the correct answer?

4

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

A. (a + m + b)/6

B. (a + 2m + b)/6

C. (a + 4m + b)/6

D. (a + 5m + b)/6

What is the correct answer?

4

An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

A. Rs. 31050

B. Rs. 34500

C. Rs. 37950

D. Rs. 50000

What is the correct answer?

4

The estimated time required to perform an activity, is known as

A. Event

B. Dummy

C. Duration

D. Float

What is the correct answer?

4

Mile Stone charts were invented in the year of

A. 1910

B. 1920

C. 1930

D. 1940

What is the correct answer?

4

If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is

A. 4 days

B. 6 days

C. 10 days

D. 16 days

What is the correct answer?

4

At a work site, statistical quality control of concrete means

A. Measurement of risks to eliminate failures

B. Applying the theory' of probability to sample testing or inspection

C. Reduction in wastage of inspection costs

D. Reduction in costs for the removal of defects

What is the correct answer?

4

The reduction in project time normally results in

A. Decreasing the direct cost and increasing indirect cost

B. Increasing the direct cost and decreasing the indirect cost

C. Increasing the direct cost and indirect cost both

D. Decreasing the direct cost and indirect cost both

What is the correct answer?

4

Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing. Reason R: If the angle of swing is decreased, the cycle time will be decreased. Select the correct answer.

A. Both A and R is true and R is the correct explanation of A

B. Both A and R is true but R is not the correct explanation of A

C. A is true but R is false

D. A is false but R is true

What is the correct answer?

4

For the network shown in the given figure, the expected time for the activity

A. 1-2 is 4

B. 2-3 is 7

C. 3-4 is 8

D. All the above

What is the correct answer?

4

In the given figure, the network of a project represents

A. Activity of an excavation of a footing

B. Activity of an excavation which starts at event No. 1 and ends at even No. 2

C. Activity of excavation which takes 8 units of time

D. None of these

What is the correct answer?

4

The critical activity has

A. Maximum float

B. Minimum float

C. Zero float

D. None of these

What is the correct answer?

4

Which one of the following is not an excavating and moving type of equipment?

A. Bulldozer

B. Clam shell

C. Scraper

D. Dump truck

What is the correct answer?

4

The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is

A. 19

B. 14

C. 24

D. None of these

What is the correct answer?

4

If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is

A. 30 kg

B. 300 kg

C. 900 kg

D. 1000 kg

What is the correct answer?

4

Crash project duration is obtained by summing the

A. Normal durations for all the activities

B. Crash durations for all activities

C. Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities