What is the correct answer?
4
The main advantage of line organisation is:
A. Effective command and control
B. Rigid discipline in the organisation
C. Defined responsibilities at all levels
What is the correct answer?
4
The object of technical planning, is
A. Preparation of specifications
B. Preparation of estimates
C. Initiating the procurement action of resources
What is the correct answer?
4
For a given size of bucket, the ideal output of a dragline will be least in
What is the correct answer?
4
Preliminary project report for a road project must contain
A. The detailed estimated cost based on detailed design
B. The several alternatives of the project that have been considered
C. The soil survey, traffic survey, concept design and approximate cost
D. The contract documents for inviting tenders
What is the correct answer?
4
Earliest finish of an activity is always
A. Greater than earliest event time of the following node
B. Less than earliest event time of the following node
C. Less than or equal to earliest event time of the following node
D. Greater than or equal to earliest event time of the following node
What is the correct answer?
4
Consider the following statements: In the critical path method of construction planning, Free Float can be.
1. Greater than Total Float.
2. Greater than Independent Float
3. Equal to Total Float.
4. Less than Independent Float. Of these statements
What is the correct answer?
4
A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
What is the correct answer?
4
Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing. Reason R: If the angle of swing is decreased, the cycle time will be decreased. Select the correct answer.
A. Both A and R is true and R is the correct explanation of A
B. Both A and R is true but R is not the correct explanation of A
C. A is true but R is false
D. A is false but R is true
What is the correct answer?
4
If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is
What is the correct answer?
4
Residential buildings are treated as
C. Industrial construction
What is the correct answer?
4
At a work site, statistical quality control of concrete means
A. Measurement of risks to eliminate failures
B. Applying the theory' of probability to sample testing or inspection
C. Reduction in wastage of inspection costs
D. Reduction in costs for the removal of defects
What is the correct answer?
4
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
What is the correct answer?
4
Critical path
What is the correct answer?
4
The basic action involved in sheep foot rolling is
What is the correct answer?
4
The technique for establishing and maintaining priorities among the various jobs of a project, is known
A. Event flow scheduling technique
B. Critical ratio scheduling
C. Slotting technique for scheduling
D. Short interval scheduling
What is the correct answer?
4
Total float for any activity is defined as the difference between
A. Its latest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest start time and earliest finish time
D. Its earliest finish time and earliest start time for its successor activity
What is the correct answer?
4
Which one of the following represents an activity?
A. Excavation for foundation
C. Setting of question paper
What is the correct answer?
4
Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth, (iv) Output can be increased by increasing the size of shovel. Of these statements
A. (ii), (iii) and (iv) are correct
B. (i), (ii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i) and (iv) are correct
What is the correct answer?
4
PERT analysis is based on
What is the correct answer?
4
Works costing less than Rs. 20,000 are treated as
What is the correct answer?
4
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to
What is the correct answer?
4
Time and progress chart of a construction, is also known as
C. Modified Mile stone chart
What is the correct answer?
4
The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is
What is the correct answer?
4
If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be
What is the correct answer?
4
Consider the following statements: In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated. Of these statements
A. 1, 2 and 3 are correct
C. 2, 3 and 4 are correct
D. 1, 2 and 4 are correct
What is the correct answer?
4
PERT is
A. An analytic in concept
B. Limited of event oriented diagrams
C. Used for research and development projects
What is the correct answer?
4
The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively
What is the correct answer?
4
While filling the tender for any work, the contractor considers
B. Availability of construction materials
C. Availability of labour
What is the correct answer?
4
The independent float affects only
C. The particular activity involved
What is the correct answer?
4
In the given figure, the network of a project represents
A. Activity of an excavation of a footing
B. Activity of an excavation which starts at event No. 1 and ends at even No. 2
C. Activity of excavation which takes 8 units of time