Home
Current Affairs January 2024

What is the correct answer?

4

Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth, (iv) Output can be increased by increasing the size of shovel. Of these statements

A. (ii), (iii) and (iv) are correct

B. (i), (ii) and (iv) are correct

C. (i), (iii) and (iv) are correct

D. (i) and (iv) are correct

Correct Answer :

B. (i), (ii) and (iv) are correct


Related Questions

What is the correct answer?

4

At a work site, statistical quality control of concrete means

A. Measurement of risks to eliminate failures

B. Applying the theory' of probability to sample testing or inspection

C. Reduction in wastage of inspection costs

D. Reduction in costs for the removal of defects

What is the correct answer?

4

The main advantage of line organisation is:

A. Effective command and control

B. Rigid discipline in the organisation

C. Defined responsibilities at all levels

D. All the above

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not consume time

D. All the above

What is the correct answer?

4

A critical ratio scheduling

A. Determines the status of each activity

B. Adjusts automatically changes in activity progress

C. Is a dynamic system

D. None of these

What is the correct answer?

4

The difference between the time avail-to do a job and the time required to do the job, is known as

A. Event

B. Float

C. Duration

D. Constraint

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The various functions under each activity, are shown by one bar on Bar Charts

B. Bar chart establishes the interdependency of one event on another

C. Only approximate percentage of the completed work is reported

D. None of these

What is the correct answer?

4

A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is

A. 10000 kg

B. 12500 kg

C. 22500 kg

D. 5000 kg

What is the correct answer?

4

A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will

A. Reduce by 200 kg

B. Increase by 200 kg

C. Increase by 250 kg

D. Reduce by 250 kg

What is the correct answer?

4

Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is

A. 1, 3, 2, 4

B. 3, 1, 4, 2

C. 3, 1, 2, 4

D. 1, 3, 4, 2

What is the correct answer?

4

PERT is

A. An analytic in concept

B. Limited of event oriented diagrams

C. Used for research and development projects

D. All the above

What is the correct answer?

4

The final selection of a construction site, is done by

A. Departmental representative or user

B. Local civil authority representative

C. Representative of engineer authority

D. All the above

What is the correct answer?

4

Consider the following statements: Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control. Of these statements

A. 1, 3 and 4 are correct

B. 2, 3 and 4 are correct

C. 1, 2 and 3 are correct

D. 1, 2 and 4 are correct

What is the correct answer?

4

If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be

A. 50 %

B. Less than 50 %

C. More than 50 %

D. 100 %

What is the correct answer?

4

A contractor has two options;
(I): Invest his money in project A or
(II): Invest his money in project B.
If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

A. Should invest in neither of the two projects

B. Could invest in either of the two projects

C. Should invest in project A

D. Should invest in project B

What is the correct answer?

4

Pick up the correct statement from the following:

A. The difference of latest occurrence time and earliest expected time, is called slack

B. The activities connecting the events having zero slack, lie on the critical path

C. The critical path consumes the maximum time

D. All the above

What is the correct answer?

4

PERT analysis is based on

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All the above

What is the correct answer?

4

The constraints in case of resource smoothening operation would be

A. Resources

B. Project duration time

C. Both resources and project duration time

D. None of the above

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

Grader is used mainly for

A. Trimming and finishing

B. Shaping and trimming

C. Finishing and shaping

D. Finishing, shaping and trimming

What is the correct answer?

4

In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

A. Yes, because of heavier overheads and handling cost

B. Yes, because of the very high order of quality control for the factory made components

C. No, because of repetitive manufacture of a number of elements

D. No, because of savings in site labour

What is the correct answer?

4

If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is

A. (t1 - t2) - t

B. t - (t1 - t2)

C. (t1 + t2) - t

D. t + (t1 - t2)

What is the correct answer?

4

A Milestone chart

A. Shows the interdependencies of various jobs

B. Depicts the delay of jobs, if any

C. Points outgoing ahead of schedule of jobs, if any

D. None of these

What is the correct answer?

4

The performance of a specific task in CPM, is known

A. Dummy

B. Event

C. Activity

D. Contract

What is the correct answer?

4

Consider the following statements: In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated. Of these statements

A. 1, 2 and 3 are correct

B. 1 and 4 are correct

C. 2, 3 and 4 are correct

D. 1, 2 and 4 are correct

What is the correct answer?

4

An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is

A. Rs. 8,43,750

B. Rs. 8,75,000

C. Rs. 10,50,000

D. Rs. 11,56,250

What is the correct answer?

4

A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is

A. Rs. 4,75,000

B. Rs. 5,75,000

C. Rs. 6,50,000

D. Rs. 8,50,000

What is the correct answer?

4

A CPM family includes

A. CPA (Critical Path Analysis)

B. CPP (Critical Path Plotted)

C. MCE (Minimum Cost Expenditure)

D. All the above

What is the correct answer?

4

Final technical authority of a project lies with

A. Assistant Engineer

B. Executive Engineer

C. Superintending Engineer

D. Chief Engineer

What is the correct answer?

4

For the network shown in the given figure, the expected time for the activity

A. 1-2 is 4

B. 2-3 is 7

C. 3-4 is 8

D. All the above

What is the correct answer?

4

Modular co-ordination of construction means proper

A. Planning

B. Designing

C. Execution

D. All the above