Only (i) is correct
(i) and (ii) are correct
(i) and (iii) are correct
(ii) and (iii) are correct
C. (i) and (iii) are correct
Unity of command
Effective control at all levels
Delegation of authority
All the above
Cheapest critical activity
Cheapest noncritical activity
Costliest critical activity
Costliest noncritical activity
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
Line organisation
Line and staff organisation
Functional organisation
Effective organisation
Started 5 days later
Completed 5 days later
Performed at slower rate in 15 days
All the above
Measurement of risks to eliminate failures
Applying the theory' of probability to sample testing or inspection
Reduction in wastage of inspection costs
Reduction in costs for the removal of defects
The various functions under each activity, are shown by one bar on Bar Charts
Bar chart establishes the interdependency of one event on another
Only approximate percentage of the completed work is reported
None of these
Its latest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest start time and earliest finish time
Its earliest finish time and earliest start time for its successor activity
An activity of a project is denoted by an arrow on the net work
The tail of the arrow indicates the start of the activity
The head of the arrow indicates the end of the activity
The arrows are drawn to scale from left to right
Longest duration
Highest cost slope
Least cost slope
Shortest duration
Is always longest
Is always shortest
May be longest
May be shortest
Increase in rates of only important materials
Variation in cost in materials element, labour element and petrol-oillubricant element
Variation in total cost of the project on an ad hoc basis
Rate of inflation
Minimum time
Maximum time
Maximum cost
Minimum cost
CPA (Critical Path Analysis)
CPP (Critical Path Plotted)
MCE (Minimum Cost Expenditure)
All the above
Kneading
Pressing
Tamping
Vibration
1, 2 and 4
3, 4 and 5
1, 3 and 4
1, 2 and 5
Instructions by the executive engineers
Construction measurements
Issue of store equipments
Names of the casual labour
The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
The difference between total float and free float, is called interfering float
All the above
Event
Float
Duration
Constraint
Having a single lump, are called uninodal curves
If symmetrical, are called normal curves
If not symmetrical, are called skew curves
All the above
Activity arrows in a CPM network are drawn to scale
The tail of an arrow represents the finish of an activity
Arrow bead represents the start of an activity
None of the above
Excavation for foundation
Curing of concrete
Setting of question paper
All the above
The float may be positive, zero or negative
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
If the float of an activity is negative, delay in its performance is bound to delay the completion of project
All the above
2.3% and 84.1%
97.7% and 84.1%
97.7 % and 15.9%
15.9% and 97.7%
2 kg/tonne
6 kg/tonne
9 kg/tonne
20 kg/tonne
Optimistic time estimate refers to activities
Pessimistic time estimate refers to activities
Most likely time estimate refers to activities
All the above
Dummy
Event
Activity
Contract
Change of critical path
Decrease of project completion time
Increase of project completion time
All of the above
1, 2, 4, 3, 5
1, 3, 2, 4, 5
1, 2, 3, 4, 5
1, 3, 4, 2, 5
Ice
Concrete
Loose sand
Earth