Home
Current Affairs January 2024

What is the correct answer?

4

Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements

A. Only (i) is correct

B. (i) and (ii) are correct

C. (i) and (iii) are correct

D. (ii) and (iii) are correct

Correct Answer :

C. (i) and (iii) are correct


Related Questions

What is the correct answer?

4

The main principle of an organisation, is

A. Unity of command

B. Effective control at all levels

C. Delegation of authority

D. All the above

What is the correct answer?

4

Economic saving of time results by crashing

A. Cheapest critical activity

B. Cheapest noncritical activity

C. Costliest critical activity

D. Costliest noncritical activity

What is the correct answer?

4

Mobilization advance up to 10% of the cost of work is given to a contractor

A. On commencement of work at site for payment of loan taken by him

B. For the purchase of construction materials

C. For the payment of advances to labour and other staff

D. For all activities required to start the work at site on finalization of the contract document

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

A. Started 5 days later

B. Completed 5 days later

C. Performed at slower rate in 15 days

D. All the above

What is the correct answer?

4

At a work site, statistical quality control of concrete means

A. Measurement of risks to eliminate failures

B. Applying the theory' of probability to sample testing or inspection

C. Reduction in wastage of inspection costs

D. Reduction in costs for the removal of defects

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The various functions under each activity, are shown by one bar on Bar Charts

B. Bar chart establishes the interdependency of one event on another

C. Only approximate percentage of the completed work is reported

D. None of these

What is the correct answer?

4

Total float for any activity is defined as the difference between

A. Its latest finish time and earliest start time for its successor activity

B. Its latest start time and earliest start time

C. Its latest start time and earliest finish time

D. Its earliest finish time and earliest start time for its successor activity

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. An activity of a project is denoted by an arrow on the net work

B. The tail of the arrow indicates the start of the activity

C. The head of the arrow indicates the end of the activity

D. The arrows are drawn to scale from left to right

What is the correct answer?

4

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

A. Longest duration

B. Highest cost slope

C. Least cost slope

D. Shortest duration

What is the correct answer?

4

Critical path

A. Is always longest

B. Is always shortest

C. May be longest

D. May be shortest

What is the correct answer?

4

During the construction period, price variation clause in contracts caters to

A. Increase in rates of only important materials

B. Variation in cost in materials element, labour element and petrol-oillubricant element

C. Variation in total cost of the project on an ad hoc basis

D. Rate of inflation

What is the correct answer?

4

For completion of a project, the critical path of the network represents

A. Minimum time

B. Maximum time

C. Maximum cost

D. Minimum cost

What is the correct answer?

4

A CPM family includes

A. CPA (Critical Path Analysis)

B. CPP (Critical Path Plotted)

C. MCE (Minimum Cost Expenditure)

D. All the above

What is the correct answer?

4

The basic action involved in sheep foot rolling is

A. Kneading

B. Pressing

C. Tamping

D. Vibration

What is the correct answer?

4

Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of project PERT is preferred for planning because of

A. 1, 2 and 4

B. 3, 4 and 5

C. 1, 3 and 4

D. 1, 2 and 5

What is the correct answer?

4

Site order book is used for recording

A. Instructions by the executive engineers

B. Construction measurements

C. Issue of store equipments

D. Names of the casual labour

What is the correct answer?

4

Pick up the correct statement from the following:

A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'

B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float

C. The difference between total float and free float, is called interfering float

D. All the above

What is the correct answer?

4

The difference between the time avail-to do a job and the time required to do the job, is known as

A. Event

B. Float

C. Duration

D. Constraint

What is the correct answer?

4

Frequency distribution curves

A. Having a single lump, are called uninodal curves

B. If symmetrical, are called normal curves

C. If not symmetrical, are called skew curves

D. All the above

What is the correct answer?

4

Select the correct statement.

A. Activity arrows in a CPM network are drawn to scale

B. The tail of an arrow represents the finish of an activity

C. Arrow bead represents the start of an activity

D. None of the above

What is the correct answer?

4

Which one of the following represents an activity?

A. Excavation for foundation

B. Curing of concrete

C. Setting of question paper

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. The float may be positive, zero or negative

B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed

C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

D. All the above

What is the correct answer?

4

If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be

A. 2.3% and 84.1%

B. 97.7% and 84.1%

C. 97.7 % and 15.9%

D. 15.9% and 97.7%

What is the correct answer?

4

The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to

A. 2 kg/tonne

B. 6 kg/tonne

C. 9 kg/tonne

D. 20 kg/tonne

What is the correct answer?

4

Pick up the correct statement from the following:

A. Optimistic time estimate refers to activities

B. Pessimistic time estimate refers to activities

C. Most likely time estimate refers to activities

D. All the above

What is the correct answer?

4

The performance of a specific task in CPM, is known

A. Dummy

B. Event

C. Activity

D. Contract

What is the correct answer?

4

Updating may result in

A. Change of critical path

B. Decrease of project completion time

C. Increase of project completion time

D. All of the above

What is the correct answer?

4

Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is

A. 1, 2, 4, 3, 5

B. 1, 3, 2, 4, 5

C. 1, 2, 3, 4, 5

D. 1, 3, 4, 2, 5

What is the correct answer?

4

Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?

A. Ice

B. Concrete

C. Loose sand

D. Earth