Home
Current Affairs January 2024

What is the correct answer?

4

Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of project PERT is preferred for planning because of

A. 1, 2 and 4

B. 3, 4 and 5

C. 1, 3 and 4

D. 1, 2 and 5

Correct Answer :

A. 1, 2 and 4


Related Questions

What is the correct answer?

4

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

A. (a + m + b)/6

B. (a + 2m + b)/6

C. (a + 4m + b)/6

D. (a + 5m + b)/6

What is the correct answer?

4

A construction schedule is prepared after collecting

A. Number of operations

B. Output of labour

C. Output of machinery

D. All the above

What is the correct answer?

4

In CPM analysis,

A. Emphasis is given to activities

B. Uncertainties are not allowed

C. Activities are represented by arrows

D. All the above

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The activity is the time consuming part of a project

B. The beginning and end of a job, are called events

C. The activity which consumes maximum time, is called a node

D. Logically and sequentially connected activities and events form a network

What is the correct answer?

4

Select the correct statement.

A. Activity arrows in a CPM network are drawn to scale

B. The tail of an arrow represents the finish of an activity

C. Arrow bead represents the start of an activity

D. None of the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. CPM analysis is activity oriented

B. PERT analysis is event oriented

C. In CPM, the time is related to cost

D. All the above

What is the correct answer?

4

Final technical authority of a project lies with

A. Assistant Engineer

B. Executive Engineer

C. Superintending Engineer

D. Chief Engineer

What is the correct answer?

4

Sinking fund is

A. The fund for rebuilding a structure when its economic life is over

B. Raised to meet maintenance costs

C. The total sum to be paid to the municipal authorities by the tenants

D. A part of the money kept in reserve for providing additional structures and structural modifications

What is the correct answer?

4

For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

A. Moist loam

B. Good common earth

C. Well blasted rock

D. Wet sticky clay

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

Consider the following statements: Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control. Of these statements

A. 1, 3 and 4 are correct

B. 2, 3 and 4 are correct

C. 1, 2 and 3 are correct

D. 1, 2 and 4 are correct

What is the correct answer?

4

PERT technique of network analysis is mainly useful for

A. Small projects

B. Large and complex projects

C. Research and development projects

D. Deterministic activities

What is the correct answer?

4

The direct cost of a project with respect to normal time is

A. Minimum

B. Maximum

C. Zero

D. Infinite

What is the correct answer?

4

An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

A. Rs. 31050

B. Rs. 34500

C. Rs. 37950

D. Rs. 50000

What is the correct answer?

4

The performance of a specific task in CPM, is known

A. Dummy

B. Event

C. Activity

D. Contract

What is the correct answer?

4

The most suitable type of equipment for compaction of cohesive soils is

A. Smooth-wheeled rollers

B. Vibratory rollers

C. Sheep foot rollers

D. Tampers

What is the correct answer?

4

Works costing less than Rs. 20,000 are treated as

A. Any project

B. Major projects

C. Minor projects

D. All the above

What is the correct answer?

4

While scheduling a project by C.P.M.

A. A project is divided into various activities

B. Required time for each activity is established

C. Net work is drawn by connecting the activities and the events

D. All the above

What is the correct answer?

4

Critical path method

A. Is an improvement upon bar chart method

B. Provides a realistic approach to daily problems

C. Avoids delays which are very common in bar charts

D. All the above

What is the correct answer?

4

The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively

A. 80 and 90

B. 90 and 80

C. 85 and 75

D. 75 and 83

What is the correct answer?

4

Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth, (iv) Output can be increased by increasing the size of shovel. Of these statements

A. (ii), (iii) and (iv) are correct

B. (i), (ii) and (iv) are correct

C. (i), (iii) and (iv) are correct

D. (i) and (iv) are correct

What is the correct answer?

4

Pick up the correct statement from the following:

A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'

B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float

C. The difference between total float and free float, is called interfering float

D. All the above

What is the correct answer?

4

In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

A. Yes, because of heavier overheads and handling cost

B. Yes, because of the very high order of quality control for the factory made components

C. No, because of repetitive manufacture of a number of elements

D. No, because of savings in site labour

What is the correct answer?

4

Critical path lies along the activities having total float

A. Positive

B. Negative

C. Zero

D. Same

What is the correct answer?

4

If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is

A. 30 kg

B. 300 kg

C. 900 kg

D. 1000 kg

What is the correct answer?

4

In PERT analysis, the time estimates of activities and probability of their occurrence follow

A. Normal distribution curve

B. Poisson's distribution curve

C. Beta distribution curve

D. None of the above

What is the correct answer?

4

A golden rule for the procurement of construction stones, suggests

A. 100% at the site

B. 67% at the site and 33% under procurement

C. 50% at the site and 50% under procurement

D. 33% at the site and 67% under procurement

What is the correct answer?

4

The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

What is the correct answer?

4

Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?

A. Concrete

B. Loose sand

C. Asphalt

D. Firm earth

What is the correct answer?

4

For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

A. 8 days

B. 9 days

C. 10 days

D. 15 days