Home
Current Affairs January 2024

What is the correct answer?

4

Which one of the following is not an excavating and moving type of equipment?

A. Bulldozer

B. Clam shell

C. Scraper

D. Dump truck

Correct Answer :

D. Dump truck


Related Questions

What is the correct answer?

4

The main advantage of line organisation is:

A. Effective command and control

B. Rigid discipline in the organisation

C. Defined responsibilities at all levels

D. All the above

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. An activity of a project is denoted by an arrow on the net work

B. The tail of the arrow indicates the start of the activity

C. The head of the arrow indicates the end of the activity

D. The arrows are drawn to scale from left to right

What is the correct answer?

4

Crash project duration is obtained by summing the

A. Normal durations for all the activities

B. Crash durations for all activities

C. Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

What is the correct answer?

4

If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is

A. 4 days

B. 6 days

C. 10 days

D. 16 days

What is the correct answer?

4

In PERT analysis, the time estimates of activities and probability of their occurrence follow

A. Normal distribution curve

B. Poisson's distribution curve

C. Beta distribution curve

D. None of the above

What is the correct answer?

4

In the given figure, the network of a project represents

A. Activity of an excavation of a footing

B. Activity of an excavation which starts at event No. 1 and ends at even No. 2

C. Activity of excavation which takes 8 units of time

D. None of these

What is the correct answer?

4

Construction team means

A. An engineer

B. An architect

C. An owner

D. All the above

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

Residential buildings are treated as

A. Light construction

B. Heavy construction

C. Industrial construction

D. Private construction

What is the correct answer?

4

Mile Stone charts were invented in the year of

A. 1910

B. 1920

C. 1930

D. 1940

What is the correct answer?

4

The independent float affects only

A. Preceding activities

B. Succeeding activities

C. The particular activity involved

D. None of the above

What is the correct answer?

4

Which one of the following represents an activity?

A. Excavation for foundation

B. Curing of concrete

C. Setting of question paper

D. All the above

What is the correct answer?

4

Mobilization advance up to 10% of the cost of work is given to a contractor

A. On commencement of work at site for payment of loan taken by him

B. For the purchase of construction materials

C. For the payment of advances to labour and other staff

D. For all activities required to start the work at site on finalization of the contract document

What is the correct answer?

4

The basic action involved in sheep foot rolling is

A. Kneading

B. Pressing

C. Tamping

D. Vibration

What is the correct answer?

4

If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be

A. Equal to X

B. More than X

C. Less than X

D. Any of the above

What is the correct answer?

4

A construction schedule is prepared after collecting

A. Number of operations

B. Output of labour

C. Output of machinery

D. All the above

What is the correct answer?

4

Which one of the following is not an excavating and moving type of equipment?

A. Bulldozer

B. Clam shell

C. Scraper

D. Dump truck

What is the correct answer?

4

The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as

A. Event

B. Free float

C. Dummy

D. Constraint

What is the correct answer?

4

Which one of the following represents an event?

A. Concrete cured

B. Fixing of door

C. Plastering of walls

D. Selecting sites

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All the Above

What is the correct answer?

4

Pick up the correct statement from the following:

A. The float may be positive, zero or negative

B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed

C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

D. All the above

What is the correct answer?

4

Sensitivity analysis is a study of

A. Comparison of profit and loss

B. Comparison of assets and liabilities

C. Change in output due to change in input

D. Economics of cost and benefits of the project

What is the correct answer?

4

Free float for any activity is defined as the difference between

A. Its earliest finish time and earliest start time for its successor activity

B. Its latest start time and earliest start time

C. Its latest finish time and earliest start time for its successor activity

D. Its earliest finish time and latest start time for its successor activity

What is the correct answer?

4

Grader is used mainly for

A. Trimming and finishing

B. Shaping and trimming

C. Finishing and shaping

D. Finishing, shaping and trimming

What is the correct answer?

4

Site order book is used for recording

A. Instructions by the executive engineers

B. Construction measurements

C. Issue of store equipments

D. Names of the casual labour

What is the correct answer?

4

Select the incorrect statement.

A. Earliest start of an activity is the early event time of the node it leaves.

B. Latest finish of an activity is the late event time of the node it enters.

C. Latest start of an activity is its latest finish minus its duration.

D. None of the above

What is the correct answer?

4

Economic saving of time results by crashing

A. Cheapest critical activity

B. Cheapest noncritical activity

C. Costliest critical activity

D. Costliest noncritical activity

What is the correct answer?

4

Modular co-ordination of construction means proper

A. Planning

B. Designing

C. Execution

D. All the above

What is the correct answer?

4

In time-cost optimization of a project, crashing is done.

A. On all the activities

B. On all the activities lying on the critical path

C. Only on activities lying on the original critical path and having flatter cost slopes

D. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

What is the correct answer?

4

The time which results in the leasi, possible construction cost of an activity, is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time