Related Questions
What is the correct answer?
4
Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is
What is the correct answer?
4
The most suitable type of equipment for compaction of cohesive soils is
A. Smooth-wheeled rollers
What is the correct answer?
4
While scheduling a project by C.P.M.
A. A project is divided into various activities
B. Required time for each activity is established
C. Net work is drawn by connecting the activities and the events
What is the correct answer?
4
The main advantage of line organisation is:
A. Effective command and control
B. Rigid discipline in the organisation
C. Defined responsibilities at all levels
What is the correct answer?
4
For a given size of bucket, the ideal output of a dragline will be least in
What is the correct answer?
4
Pick up the correct statement from the following:
A. Earliest expected time is denoted by TE
B. Latest occurrence time is denoted by TL
C. Contractual obligation time is denoted by Ts
What is the correct answer?
4
For excavating utility trenches with precise control of depth, the excavation equipment used is
What is the correct answer?
4
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?
A. Yes, because of heavier overheads and handling cost
B. Yes, because of the very high order of quality control for the factory made components
C. No, because of repetitive manufacture of a number of elements
D. No, because of savings in site labour
What is the correct answer?
4
The time with which direct cost does not reduce with the increase in time is known as
What is the correct answer?
4
In time-cost optimization of a project, crashing is done.
B. On all the activities lying on the critical path
C. Only on activities lying on the original critical path and having flatter cost slopes
D. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
What is the correct answer?
4
The estimated time required to perform an activity, is known as
What is the correct answer?
4
The basic action involved in sheep foot rolling is
What is the correct answer?
4
Critical path
What is the correct answer?
4
A dummy activity
A. Is artificially introduced
B. Is represented by a dotted line
What is the correct answer?
4
Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of project PERT is preferred for planning because of
What is the correct answer?
4
The first method invented for planning projects, was
C. Critical path method (CPM)
D. Programme Evaluation and Review Technique (PERT)
What is the correct answer?
4
An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?
What is the correct answer?
4
Various activities of a project, are shown on bar charts by
What is the correct answer?
4
Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements
B. (i) and (ii) are correct
C. (i) and (iii) are correct
D. (ii) and (iii) are correct
What is the correct answer?
4
Which one of the following represents an activity?
A. Excavation for foundation
C. Setting of question paper
What is the correct answer?
4
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
What is the correct answer?
4
For the network shown in the given figure, the expected time for the activity
What is the correct answer?
4
A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is
What is the correct answer?
4
The reduction in project time normally results in
A. Decreasing the direct cost and increasing indirect cost
B. Increasing the direct cost and decreasing the indirect cost
C. Increasing the direct cost and indirect cost both
D. Decreasing the direct cost and indirect cost both
What is the correct answer?
4
The performance of a specific task in CPM, is known
What is the correct answer?
4
A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is
What is the correct answer?
4
A golden rule for the procurement of construction stones, suggests
B. 67% at the site and 33% under procurement
C. 50% at the site and 50% under procurement
D. 33% at the site and 67% under procurement
What is the correct answer?
4
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
What is the correct answer?
4
The main principle of an organisation, is
B. Effective control at all levels
C. Delegation of authority
What is the correct answer?
4
Frederick W. Taylor introduced a system of working known as
B. Line and staff organisation
C. Functional organisation
D. Effective organisation