Home
Current Affairs January 2024

What is the correct answer?

4

During the construction period, price variation clause in contracts caters to

A. Increase in rates of only important materials

B. Variation in cost in materials element, labour element and petrol-oillubricant element

C. Variation in total cost of the project on an ad hoc basis

D. Rate of inflation

Correct Answer :

B. Variation in cost in materials element, labour element and petrol-oillubricant element


Related Questions

What is the correct answer?

4

CPM is

A. Synthesising in concepts

B. Is built of activities oriented programme

C. Is based on time estimate

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. Programme Evaluation and Review Technique, is event oriented

B. Programme Evaluation and Review Technique is not event oriented

C. Critical Path Method is event oriented

D. Critical Path method is event oriented

What is the correct answer?

4

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

A. to + 3tm+ tp/3

B. to + 4tm+ tp/4

C. to + 4tm+ tp/5

D. to + 4tm+ tp/6

What is the correct answer?

4

Pick up the correct statement from the following:

A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'

B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float

C. The difference between total float and free float, is called interfering float

D. All the above

What is the correct answer?

4

Sensitivity analysis is a study of

A. Comparison of profit and loss

B. Comparison of assets and liabilities

C. Change in output due to change in input

D. Economics of cost and benefits of the project

What is the correct answer?

4

Slack time refers to

A. An activity

B. An event

C. Both event and activity

D. None of the above

What is the correct answer?

4

Which of the following excavators is most suitable for digging under water?

A. Drag line

B. Hoe

C. Clam shell

D. Dipper shovel

What is the correct answer?

4

The time corresponding to minimum total project cost is

A. Crash time

B. Normal time

C. Optimistic time

D. Between normal time and crash time

What is the correct answer?

4

If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

A. 3.5 and 5/6

B. 5 and 25/36

C. 3.5 and 25/36

D. 4 and 5/6

What is the correct answer?

4

Mobilization advance up to 10% of the cost of work is given to a contractor

A. On commencement of work at site for payment of loan taken by him

B. For the purchase of construction materials

C. For the payment of advances to labour and other staff

D. For all activities required to start the work at site on finalization of the contract document

What is the correct answer?

4

Crash project duration is obtained by summing the

A. Normal durations for all the activities

B. Crash durations for all activities

C. Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

What is the correct answer?

4

Henry Gantt developed Bar charts for planning and scheduling of projects in

A. 1880

B. 1900

C. 1920

D. 1940

What is the correct answer?

4

The basic action involved in sheep foot rolling is

A. Kneading

B. Pressing

C. Tamping

D. Vibration

What is the correct answer?

4

For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

A. Moist loam

B. Good common earth

C. Well blasted rock

D. Wet sticky clay

What is the correct answer?

4

Construction team means

A. An engineer

B. An architect

C. An owner

D. All the above

What is the correct answer?

4

The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

A. Total float

B. Free float

C. Interfering float

D. Independent float

What is the correct answer?

4

The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as

A. Event

B. Free float

C. Dummy

D. Constraint

What is the correct answer?

4

A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be

A. 20 kg/tonne

B. 30 kg/tonne

C. 40 kg/tonne

D. 50 kg/tonne

What is the correct answer?

4

Final technical authority of a project lies with

A. Assistant Engineer

B. Executive Engineer

C. Superintending Engineer

D. Chief Engineer

What is the correct answer?

4

Consider the following statements: In the critical path method of construction planning, Free Float can be.
1. Greater than Total Float.
2. Greater than Independent Float
3. Equal to Total Float.
4. Less than Independent Float. Of these statements

A. 1 and 4 are correct

B. 2 and 3 are correct

C. 1 and 4 are correct

D. 1 and 2 are correct

What is the correct answer?

4

In resources levelling

A. Total duration of project is reduced

B. Total duration of project is increased

C. Uniform demand of resources is achieved

D. Cost of project is controlled

What is the correct answer?

4

Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.

A. A is correct but R is not correct

B. R is correct but A is not correct

C. Both A and R is correct

D. Both A and R is incorrect

What is the correct answer?

4

The direct cost of a project with respect to normal time is

A. Minimum

B. Maximum

C. Zero

D. Infinite

What is the correct answer?

4

Select the correct statement.

A. Activity arrows in a CPM network are drawn to scale

B. The tail of an arrow represents the finish of an activity

C. Arrow bead represents the start of an activity

D. None of the above

What is the correct answer?

4

The main principle of an organisation, is

A. Unity of command

B. Effective control at all levels

C. Delegation of authority

D. All the above

What is the correct answer?

4

Batching refers to

A. Controlling the total quantity at each batch

B. Weighing accurately, the quantity of each material for a job before mixing

C. Controlling the quantity of each material into each batch

D. Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch

What is the correct answer?

4

A critical ratio scheduling

A. Determines the status of each activity

B. Adjusts automatically changes in activity progress

C. Is a dynamic system

D. None of these

What is the correct answer?

4

A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will

A. Reduce by 200 kg

B. Increase by 200 kg

C. Increase by 250 kg

D. Reduce by 250 kg

What is the correct answer?

4

The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

What is the correct answer?

4

The time which results in the leasi, possible construction cost of an activity, is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time