Increase in rates of only important materials
Variation in cost in materials element, labour element and petrol-oillubricant element
Variation in total cost of the project on an ad hoc basis
Rate of inflation
B. Variation in cost in materials element, labour element and petrol-oillubricant element
Synthesising in concepts
Is built of activities oriented programme
Is based on time estimate
All the above
Programme Evaluation and Review Technique, is event oriented
Programme Evaluation and Review Technique is not event oriented
Critical Path Method is event oriented
Critical Path method is event oriented
to + 3tm+ tp/3
to + 4tm+ tp/4
to + 4tm+ tp/5
to + 4tm+ tp/6
The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
The difference between total float and free float, is called interfering float
All the above
Comparison of profit and loss
Comparison of assets and liabilities
Change in output due to change in input
Economics of cost and benefits of the project
An activity
An event
Both event and activity
None of the above
Drag line
Hoe
Clam shell
Dipper shovel
Crash time
Normal time
Optimistic time
Between normal time and crash time
3.5 and 5/6
5 and 25/36
3.5 and 25/36
4 and 5/6
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
Normal durations for all the activities
Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
1880
1900
1920
1940
Kneading
Pressing
Tamping
Vibration
Moist loam
Good common earth
Well blasted rock
Wet sticky clay
An engineer
An architect
An owner
All the above
Total float
Free float
Interfering float
Independent float
Event
Free float
Dummy
Constraint
20 kg/tonne
30 kg/tonne
40 kg/tonne
50 kg/tonne
Assistant Engineer
Executive Engineer
Superintending Engineer
Chief Engineer
1 and 4 are correct
2 and 3 are correct
1 and 4 are correct
1 and 2 are correct
Total duration of project is reduced
Total duration of project is increased
Uniform demand of resources is achieved
Cost of project is controlled
A is correct but R is not correct
R is correct but A is not correct
Both A and R is correct
Both A and R is incorrect
Minimum
Maximum
Zero
Infinite
Activity arrows in a CPM network are drawn to scale
The tail of an arrow represents the finish of an activity
Arrow bead represents the start of an activity
None of the above
Unity of command
Effective control at all levels
Delegation of authority
All the above
Controlling the total quantity at each batch
Weighing accurately, the quantity of each material for a job before mixing
Controlling the quantity of each material into each batch
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Determines the status of each activity
Adjusts automatically changes in activity progress
Is a dynamic system
None of these
Reduce by 200 kg
Increase by 200 kg
Increase by 250 kg
Reduce by 250 kg
Duration
Total float
Free float
Interfering float
Normal time
Slow time
Crash time
Standard time