Home
Current Affairs January 2024

What is the correct answer?

4

Batching refers to

A. Controlling the total quantity at each batch

B. Weighing accurately, the quantity of each material for a job before mixing

C. Controlling the quantity of each material into each batch

D. Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch

Correct Answer :

C. Controlling the quantity of each material into each batch


Related Questions

What is the correct answer?

4

The basic action involved in sheep foot rolling is

A. Kneading

B. Pressing

C. Tamping

D. Vibration

What is the correct answer?

4

Output of a bulldozer is
(i) Increased if drawbar HP of the tractor is increased for a given hauling distance
(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance
(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor
(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor
Of these statement

A. (i) and (iii) are correct

B. (i) and (iv) are correct

C. (ii) and (iii) are correct

D. (ii) and (iv) are correct

What is the correct answer?

4

Preliminary project report for a road project must contain

A. The detailed estimated cost based on detailed design

B. The several alternatives of the project that have been considered

C. The soil survey, traffic survey, concept design and approximate cost

D. The contract documents for inviting tenders

What is the correct answer?

4

In PERT analysis, the time estimates of activities and probability of their occurrence follow

A. Normal distribution curve

B. Poisson's distribution curve

C. Beta distribution curve

D. None of the above

What is the correct answer?

4

Modular co-ordination of construction means proper

A. Planning

B. Designing

C. Execution

D. All the above

What is the correct answer?

4

Pick up the PERT event from the following:

A. Digging of foundation started

B. Digging of foundation completed

C. Laying of concrete started

D. All the above

What is the correct answer?

4

A critical ratio scheduling

A. Determines the status of each activity

B. Adjusts automatically changes in activity progress

C. Is a dynamic system

D. None of these

What is the correct answer?

4

The object of technical planning, is

A. Preparation of specifications

B. Preparation of estimates

C. Initiating the procurement action of resources

D. All the above

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. An activity of a project is denoted by an arrow on the net work

B. The tail of the arrow indicates the start of the activity

C. The head of the arrow indicates the end of the activity

D. The arrows are drawn to scale from left to right

What is the correct answer?

4

Which of the following does not represent an activity?

A. Site located

B. Foundation is being dug

C. The office area is being cleaned

D. The invitations are being sent

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The activity is the time consuming part of a project

B. The beginning and end of a job, are called events

C. The activity which consumes maximum time, is called a node

D. Logically and sequentially connected activities and events form a network

What is the correct answer?

4

Which of the following earth moving machines has the shortest cycle time?

A. Drag line

B. Hoe

C. Clam shell

D. Dipper shovel

What is the correct answer?

4

Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.

A. A is correct but R is not correct

B. R is correct but A is not correct

C. Both A and R is correct

D. Both A and R is incorrect

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All the Above

What is the correct answer?

4

Pick up the correct statement from the following:

A. Earliest expected time is denoted by TE

B. Latest occurrence time is denoted by TL

C. Contractual obligation time is denoted by Ts

D. All the above

What is the correct answer?

4

The final selection of a construction site, is done by

A. Departmental representative or user

B. Local civil authority representative

C. Representative of engineer authority

D. All the above

What is the correct answer?

4

The most popular type of organisation used for Civil Engineering Constructions, is

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is

A. 10000 kg

B. 12500 kg

C. 22500 kg

D. 5000 kg

What is the correct answer?

4

Time and progress chart of a construction, is also known as

A. Bar chart

B. Gantt chart

C. Modified Mile stone chart

D. All the above

What is the correct answer?

4

Which of the following is a weakness of bar chart?

A. Interdependencies of activities

B. Project progress

C. Uncertainties

D. All of the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. The difference of latest occurrence time and earliest expected time, is called slack

B. The activities connecting the events having zero slack, lie on the critical path

C. The critical path consumes the maximum time

D. All the above

What is the correct answer?

4

Which one of the following is not an excavating and moving type of equipment?

A. Bulldozer

B. Clam shell

C. Scraper

D. Dump truck

What is the correct answer?

4

Free float is mainly used to

A. Identify the activities which can be delayed without affecting the total float of preceding activity

B. Identify the activities, which can be delayed without affecting the total float of succeeding activity

C. Establish priorities

D. Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

What is the correct answer?

4

The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be

A. Rs. 8,800

B. Rs. 7,600

C. Rs. 6,400

D. Rs. 5,000

What is the correct answer?

4

Select the correct statement.

A. Activity arrows in a CPM network are drawn to scale

B. The tail of an arrow represents the finish of an activity

C. Arrow bead represents the start of an activity

D. None of the above

What is the correct answer?

4

Which one of the following represents an event?

A. Concrete cured

B. Fixing of door

C. Plastering of walls

D. Selecting sites

What is the correct answer?

4

The estimated time required to perform an activity, is known as

A. Event

B. Dummy

C. Duration

D. Float

What is the correct answer?

4

A contractor has two options;
(I): Invest his money in project A or
(II): Invest his money in project B.
If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

A. Should invest in neither of the two projects

B. Could invest in either of the two projects

C. Should invest in project A

D. Should invest in project B

What is the correct answer?

4

PERT is

A. An analytic in concept

B. Limited of event oriented diagrams

C. Used for research and development projects

D. All the above

What is the correct answer?

4

Consider the following statements: In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated. Of these statements

A. 1, 2 and 3 are correct

B. 1 and 4 are correct

C. 2, 3 and 4 are correct

D. 1, 2 and 4 are correct