Home
Current Affairs January 2024

What is the correct answer?

4

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

A. to + 3tm+ tp/3

B. to + 4tm+ tp/4

C. to + 4tm+ tp/5

D. to + 4tm+ tp/6

Correct Answer :

D. to + 4tm+ tp/6


Related Questions

What is the correct answer?

4

Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?

A. Ice

B. Concrete

C. Loose sand

D. Earth

What is the correct answer?

4

A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is

A. Rs. 4,75,000

B. Rs. 5,75,000

C. Rs. 6,50,000

D. Rs. 8,50,000

What is the correct answer?

4

For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

A. Moist loam

B. Good common earth

C. Well blasted rock

D. Wet sticky clay

What is the correct answer?

4

The critical activity has

A. Maximum float

B. Minimum float

C. Zero float

D. None of these

What is the correct answer?

4

A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is

A. 10000 kg

B. 12500 kg

C. 22500 kg

D. 5000 kg

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity

B. The difference between the maximum time available for the job and actual time it consumes, is called total float

C. The difference between the latest start time and earliest start time of an activity, is called total float

D. None of these

What is the correct answer?

4

The difference between the time avail-to do a job and the time required to do the job, is known as

A. Event

B. Float

C. Duration

D. Constraint

What is the correct answer?

4

A contractor has two options;
(I): Invest his money in project A or
(II): Invest his money in project B.
If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

A. Should invest in neither of the two projects

B. Could invest in either of the two projects

C. Should invest in project A

D. Should invest in project B

What is the correct answer?

4

Crash project duration is obtained by summing the

A. Normal durations for all the activities

B. Crash durations for all activities

C. Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

What is the correct answer?

4

Batching refers to

A. Controlling the total quantity at each batch

B. Weighing accurately, the quantity of each material for a job before mixing

C. Controlling the quantity of each material into each batch

D. Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch

What is the correct answer?

4

Free float for any activity is defined as the difference between

A. Its earliest finish time and earliest start time for its successor activity

B. Its latest start time and earliest start time

C. Its latest finish time and earliest start time for its successor activity

D. Its earliest finish time and latest start time for its successor activity

What is the correct answer?

4

For the network shown in the given figure, the expected time for the activity

A. 1-2 is 4

B. 2-3 is 7

C. 3-4 is 8

D. All the above

What is the correct answer?

4

Residential buildings are treated as

A. Light construction

B. Heavy construction

C. Industrial construction

D. Private construction

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The activity is the time consuming part of a project

B. The beginning and end of a job, are called events

C. The activity which consumes maximum time, is called a node

D. Logically and sequentially connected activities and events form a network

What is the correct answer?

4

If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is

A. 30 kg

B. 300 kg

C. 900 kg

D. 1000 kg

What is the correct answer?

4

Pick up the correct statement from the following:

A. Optimistic time estimate refers to activities

B. Pessimistic time estimate refers to activities

C. Most likely time estimate refers to activities

D. All the above

What is the correct answer?

4

A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be

A. 20 kg/tonne

B. 30 kg/tonne

C. 40 kg/tonne

D. 50 kg/tonne

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All the Above

What is the correct answer?

4

Henry Gantt developed Bar charts for planning and scheduling of projects in

A. 1880

B. 1900

C. 1920

D. 1940

What is the correct answer?

4

The most popular type of organisation used for Civil Engineering Constructions, is

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be

A. Rs. 8,800

B. Rs. 7,600

C. Rs. 6,400

D. Rs. 5,000

What is the correct answer?

4

Consider the following statements: In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated. Of these statements

A. 1, 2 and 3 are correct

B. 1 and 4 are correct

C. 2, 3 and 4 are correct

D. 1, 2 and 4 are correct

What is the correct answer?

4

The Overall in-charge of an organisation at the site responsible for the execution of the works, is

A. Executive Engineer

B. Engineer

C. Junior Engineer

D. Assistant Engineer

What is the correct answer?

4

The area under the Beta distribution curve is divided into two equal parts by

A. Most likely time

B. Optimistic time

C. Pessimistic time

D. Expected time

What is the correct answer?

4

Mile Stone charts were invented in the year of

A. 1910

B. 1920

C. 1930

D. 1940

What is the correct answer?

4

If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

A. EF = ES + D

B. LS = LF - D

C. LF = LS + D

D. All the above

What is the correct answer?

4

Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

A. 20

B. 25

C. 35

D. 15

What is the correct answer?

4

An event is indicated on the network by a number enclosed in

A. A circle

B. A square

C. A triangle

D. All the above

What is the correct answer?

4

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

A. Longest duration

B. Highest cost slope

C. Least cost slope

D. Shortest duration

What is the correct answer?

4

Various activities of a project, are shown on bar charts by

A. Vertical lines

B. Horizontal lines

C. Dots

D. Crosses