Total duration of project is reduced
Total duration of project is increased
Uniform demand of resources is achieved
Cost of project is controlled
C. Uniform demand of resources is achieved
Bulldozer
Clam shell
Scraper
Dump truck
Small projects
Large and complex projects
Research and development projects
Deterministic activities
Longest duration
Highest cost slope
Least cost slope
Shortest duration
2 kg/tonne
6 kg/tonne
9 kg/tonne
20 kg/tonne
Total float and free float
Total float and independent float
Free float and independent float
None of the above
Comparison of profit and loss
Comparison of assets and liabilities
Change in output due to change in input
Economics of cost and benefits of the project
CPA (Critical Path Analysis)
CPP (Critical Path Plotted)
MCE (Minimum Cost Expenditure)
All the above
Emphasis is given to activities
Uncertainties are not allowed
Activities are represented by arrows
All the above
Kneading
Pressing
Tamping
Vibration
Normal durations for all the activities
Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
50 %
Less than 50 %
More than 50 %
100 %
Line organisation
Line and staff organisation
Functional organisation
Effective organisation
Effective command and control
Rigid discipline in the organisation
Defined responsibilities at all levels
All the above
Optimistic time
Pessimistic time
Most likely time
All the above
Cheapest critical activity
Cheapest noncritical activity
Costliest critical activity
Costliest noncritical activity
A circle
A square
A triangle
All the above
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
All the above
Rs. 31050
Rs. 34500
Rs. 37950
Rs. 50000
to + 3tm+ tp/3
to + 4tm+ tp/4
to + 4tm+ tp/5
to + 4tm+ tp/6
Is always longest
Is always shortest
May be longest
May be shortest
20 kg/tonne
30 kg/tonne
40 kg/tonne
50 kg/tonne
Any project
Major projects
Minor projects
All the above
1910
1920
1930
1940
Started 5 days later
Completed 5 days later
Performed at slower rate in 15 days
All the above
1 and 4 are correct
2 and 3 are correct
1 and 4 are correct
1 and 2 are correct
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost
Increasing the direct cost and indirect cost both
Decreasing the direct cost and indirect cost both
The detailed estimated cost based on detailed design
The several alternatives of the project that have been considered
The soil survey, traffic survey, concept design and approximate cost
The contract documents for inviting tenders
3425 kg
5515 kg
4350 kg
2975 kg
30 kg
300 kg
900 kg
1000 kg