Home
Current Affairs January 2024

What is the correct answer?

4

In resources levelling

A. Total duration of project is reduced

B. Total duration of project is increased

C. Uniform demand of resources is achieved

D. Cost of project is controlled

Correct Answer :

C. Uniform demand of resources is achieved


Related Questions

What is the correct answer?

4

Which one of the following is not an excavating and moving type of equipment?

A. Bulldozer

B. Clam shell

C. Scraper

D. Dump truck

What is the correct answer?

4

PERT technique of network analysis is mainly useful for

A. Small projects

B. Large and complex projects

C. Research and development projects

D. Deterministic activities

What is the correct answer?

4

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

A. Longest duration

B. Highest cost slope

C. Least cost slope

D. Shortest duration

What is the correct answer?

4

The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to

A. 2 kg/tonne

B. 6 kg/tonne

C. 9 kg/tonne

D. 20 kg/tonne

What is the correct answer?

4

Interfering float is the difference between

A. Total float and free float

B. Total float and independent float

C. Free float and independent float

D. None of the above

What is the correct answer?

4

Sensitivity analysis is a study of

A. Comparison of profit and loss

B. Comparison of assets and liabilities

C. Change in output due to change in input

D. Economics of cost and benefits of the project

What is the correct answer?

4

A CPM family includes

A. CPA (Critical Path Analysis)

B. CPP (Critical Path Plotted)

C. MCE (Minimum Cost Expenditure)

D. All the above

What is the correct answer?

4

In CPM analysis,

A. Emphasis is given to activities

B. Uncertainties are not allowed

C. Activities are represented by arrows

D. All the above

What is the correct answer?

4

The basic action involved in sheep foot rolling is

A. Kneading

B. Pressing

C. Tamping

D. Vibration

What is the correct answer?

4

Crash project duration is obtained by summing the

A. Normal durations for all the activities

B. Crash durations for all activities

C. Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

What is the correct answer?

4

If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be

A. 50 %

B. Less than 50 %

C. More than 50 %

D. 100 %

What is the correct answer?

4

The most popular type of organisation used for Civil Engineering Constructions, is

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

The main advantage of line organisation is:

A. Effective command and control

B. Rigid discipline in the organisation

C. Defined responsibilities at all levels

D. All the above

What is the correct answer?

4

PERT analysis is based on

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All the above

What is the correct answer?

4

Economic saving of time results by crashing

A. Cheapest critical activity

B. Cheapest noncritical activity

C. Costliest critical activity

D. Costliest noncritical activity

What is the correct answer?

4

An event is indicated on the network by a number enclosed in

A. A circle

B. A square

C. A triangle

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time

B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time

C. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity

D. All the above

What is the correct answer?

4

An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

A. Rs. 31050

B. Rs. 34500

C. Rs. 37950

D. Rs. 50000

What is the correct answer?

4

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

A. to + 3tm+ tp/3

B. to + 4tm+ tp/4

C. to + 4tm+ tp/5

D. to + 4tm+ tp/6

What is the correct answer?

4

Critical path

A. Is always longest

B. Is always shortest

C. May be longest

D. May be shortest

What is the correct answer?

4

A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be

A. 20 kg/tonne

B. 30 kg/tonne

C. 40 kg/tonne

D. 50 kg/tonne

What is the correct answer?

4

Works costing less than Rs. 20,000 are treated as

A. Any project

B. Major projects

C. Minor projects

D. All the above

What is the correct answer?

4

Mile Stone charts were invented in the year of

A. 1910

B. 1920

C. 1930

D. 1940

What is the correct answer?

4

If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

A. Started 5 days later

B. Completed 5 days later

C. Performed at slower rate in 15 days

D. All the above

What is the correct answer?

4

Consider the following statements: In the critical path method of construction planning, Free Float can be.
1. Greater than Total Float.
2. Greater than Independent Float
3. Equal to Total Float.
4. Less than Independent Float. Of these statements

A. 1 and 4 are correct

B. 2 and 3 are correct

C. 1 and 4 are correct

D. 1 and 2 are correct

What is the correct answer?

4

Mobilization advance up to 10% of the cost of work is given to a contractor

A. On commencement of work at site for payment of loan taken by him

B. For the purchase of construction materials

C. For the payment of advances to labour and other staff

D. For all activities required to start the work at site on finalization of the contract document

What is the correct answer?

4

The reduction in project time normally results in

A. Decreasing the direct cost and increasing indirect cost

B. Increasing the direct cost and decreasing the indirect cost

C. Increasing the direct cost and indirect cost both

D. Decreasing the direct cost and indirect cost both

What is the correct answer?

4

Preliminary project report for a road project must contain

A. The detailed estimated cost based on detailed design

B. The several alternatives of the project that have been considered

C. The soil survey, traffic survey, concept design and approximate cost

D. The contract documents for inviting tenders

What is the correct answer?

4

The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is

A. 3425 kg

B. 5515 kg

C. 4350 kg

D. 2975 kg

What is the correct answer?

4

If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is

A. 30 kg

B. 300 kg

C. 900 kg

D. 1000 kg