(t1 - t2) - t
t - (t1 - t2)
(t1 + t2) - t
t + (t1 - t2)
A. (t1 - t2) - t
Earliest start of an activity is the early event time of the node it leaves.
Latest finish of an activity is the late event time of the node it enters.
Latest start of an activity is its latest finish minus its duration.
None of the above
Planning
Designing
Execution
All the above
Determines the status of each activity
Adjusts automatically changes in activity progress
Is a dynamic system
None of these
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
Is always longest
Is always shortest
May be longest
May be shortest
Should invest in neither of the two projects
Could invest in either of the two projects
Should invest in project A
Should invest in project B
Minor works
Major works
Large projects
All the Above
1
2
3
4
1, 2 and 3 are correct
1 and 4 are correct
2, 3 and 4 are correct
1, 2 and 4 are correct
Optimistic time
Pessimistic time
Most likely time
All the above
Trimming and finishing
Shaping and trimming
Finishing and shaping
Finishing, shaping and trimming
On all the activities
On all the activities lying on the critical path
Only on activities lying on the original critical path and having flatter cost slopes
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
80 and 90
90 and 80
85 and 75
75 and 83
A is correct but R is not correct
R is correct but A is not correct
Both A and R is correct
Both A and R is incorrect
19
14
24
None of these
Is an improvement upon bar chart method
Provides a realistic approach to daily problems
Avoids delays which are very common in bar charts
All the above
1 and 4 are correct
2 and 3 are correct
1 and 4 are correct
1 and 2 are correct
Start float and finish float are always equal.
Total float can be either start float or finish float.
Start float and finish float need not be equal.
Start float and finish float are the differences between activity times and not event times.
Optimistic time estimate refers to activities
Pessimistic time estimate refers to activities
Most likely time estimate refers to activities
All the above
Change of critical path
Decrease of project completion time
Increase of project completion time
All of the above
Minimum time
Maximum time
Maximum cost
Minimum cost
LST-EST
LFT-EFT
TL-EFT
All the above
A circle
A square
A triangle
All the above
Rs. 31050
Rs. 34500
Rs. 37950
Rs. 50000
Digging of foundation started
Digging of foundation completed
Laying of concrete started
All the above
The detailed estimated cost based on detailed design
The several alternatives of the project that have been considered
The soil survey, traffic survey, concept design and approximate cost
The contract documents for inviting tenders
An activity
An event
Both event and activity
None of the above
Vertical lines
Horizontal lines
Dots
Crosses
1, 2 and 4
3, 4 and 5
1, 3 and 4
1, 2 and 5
Synthesising in concepts
Is built of activities oriented programme
Is based on time estimate
All the above