Related Questions
What is the correct answer?
4
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
C. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
What is the correct answer?
4
The constraints in case of resource smoothening operation would be
C. Both resources and project duration time
What is the correct answer?
4
Critical path
What is the correct answer?
4
Frequency distribution curves
A. Having a single lump, are called uninodal curves
B. If symmetrical, are called normal curves
C. If not symmetrical, are called skew curves
What is the correct answer?
4
Henry Gantt developed Bar charts for planning and scheduling of projects in
What is the correct answer?
4
PERT is
A. An analytic in concept
B. Limited of event oriented diagrams
C. Used for research and development projects
What is the correct answer?
4
A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will
What is the correct answer?
4
Select the incorrect statement.
A. Earliest start of an activity is the early event time of the node it leaves.
B. Latest finish of an activity is the late event time of the node it enters.
C. Latest start of an activity is its latest finish minus its duration.
What is the correct answer?
4
Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is
What is the correct answer?
4
Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.
A. A is correct but R is not correct
B. R is correct but A is not correct
C. Both A and R is correct
D. Both A and R is incorrect
What is the correct answer?
4
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
What is the correct answer?
4
Which of the following is not a PERT event?
A. Site investigation started
B. Sessional work completed
C. Bus starts from Jaipur
D. Class is being attended
What is the correct answer?
4
If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is
What is the correct answer?
4
A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
What is the correct answer?
4
Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth, (iv) Output can be increased by increasing the size of shovel. Of these statements
A. (ii), (iii) and (iv) are correct
B. (i), (ii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i) and (iv) are correct
What is the correct answer?
4
An event is indicated on the network by a number enclosed in
What is the correct answer?
4
The direct cost of a project with respect to normal time is
What is the correct answer?
4
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
What is the correct answer?
4
Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
What is the correct answer?
4
A construction schedule is prepared after collecting
What is the correct answer?
4
The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be
What is the correct answer?
4
If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
What is the correct answer?
4
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
What is the correct answer?
4
Mile Stone charts were invented in the year of
What is the correct answer?
4
Modular co-ordination of construction means proper
What is the correct answer?
4
Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements
B. (i) and (ii) are correct
C. (i) and (iii) are correct
D. (ii) and (iii) are correct
What is the correct answer?
4
Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
What is the correct answer?
4
Grader is used mainly for
A. Trimming and finishing
D. Finishing, shaping and trimming
What is the correct answer?
4
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
What is the correct answer?
4
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as