What is the correct answer?
4
Which one of the following represents an activity?
A. Excavation for foundation
C. Setting of question paper
What is the correct answer?
4
Economic saving of time results by crashing
A. Cheapest critical activity
B. Cheapest noncritical activity
C. Costliest critical activity
D. Costliest noncritical activity
What is the correct answer?
4
A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is
What is the correct answer?
4
The time which results in the leasi, possible construction cost of an activity, is known as
What is the correct answer?
4
Critical Path Net Work helps an engineer
A. To concentrate his attention on critical activities
B. To divert the resources from non-critical advanced activities to critical activities
C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
What is the correct answer?
4
For which of the following materials, the output of power shovels for a fixed shovel size will be maximum
What is the correct answer?
4
Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
What is the correct answer?
4
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
What is the correct answer?
4
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
What is the correct answer?
4
The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be
What is the correct answer?
4
Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is
What is the correct answer?
4
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
What is the correct answer?
4
Updating may result in
A. Change of critical path
B. Decrease of project completion time
C. Increase of project completion time
What is the correct answer?
4
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
What is the correct answer?
4
A CPM family includes
A. CPA (Critical Path Analysis)
B. CPP (Critical Path Plotted)
C. MCE (Minimum Cost Expenditure)
What is the correct answer?
4
Whenever an activity has zero total float, then
A. Free float of the activity must be zero but independent float need not be zero
B. Independent float must be zero but free float need not be zero
C. Free float and independent float both must be zero
D. Free float and independent float both need not be zero
What is the correct answer?
4
Which one of the following represents an event?
What is the correct answer?
4
Pick up the correct statement from the following:
A. The float may be positive, zero or negative
B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project
What is the correct answer?
4
If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
What is the correct answer?
4
The performance of a specific task in CPM, is known
What is the correct answer?
4
Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
What is the correct answer?
4
Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing. Reason R: If the angle of swing is decreased, the cycle time will be decreased. Select the correct answer.
A. Both A and R is true and R is the correct explanation of A
B. Both A and R is true but R is not the correct explanation of A
C. A is true but R is false
D. A is false but R is true
What is the correct answer?
4
A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is
What is the correct answer?
4
Which one of the following is not an excavating and moving type of equipment?
What is the correct answer?
4
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
What is the correct answer?
4
Which of the following excavators is most suitable for digging under water?
What is the correct answer?
4
If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be
What is the correct answer?
4
The time with which direct cost does not reduce with the increase in time is known as
What is the correct answer?
4
Total float for any activity is defined as the difference between
A. Its latest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest start time and earliest finish time
D. Its earliest finish time and earliest start time for its successor activity
What is the correct answer?
4
Pre-tender stage requires
C. Fmalisation of alignment of work