On all the activities
On all the activities lying on the critical path
Only on activities lying on the original critical path and having flatter cost slopes
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
D. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Hoe
Shovel
Dragline
None of the above
Controlling the total quantity at each batch
Weighing accurately, the quantity of each material for a job before mixing
Controlling the quantity of each material into each batch
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Acquisition of land
Selection of site
Fmalisation of alignment of work
All the above
Trimming and finishing
Shaping and trimming
Finishing and shaping
Finishing, shaping and trimming
Its latest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest start time and earliest finish time
Its earliest finish time and earliest start time for its successor activity
CPA (Critical Path Analysis)
CPP (Critical Path Plotted)
MCE (Minimum Cost Expenditure)
All the above
Event
Node
Connector
All the above
Number of operations
Output of labour
Output of machinery
All the above
Digging of foundation started
Digging of foundation completed
Laying of concrete started
All the above
LST-EST
LFT-EFT
TL-EFT
All the above
Line organisation
Line and staff organisation
Functional organisation
None of these
An activity
An event
Both event and activity
None of the above
Identify the activities which can be delayed without affecting the total float of preceding activity
Identify the activities, which can be delayed without affecting the total float of succeeding activity
Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Normal distribution curve
Poisson's distribution curve
Beta distribution curve
None of the above
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications
Increase in rates of only important materials
Variation in cost in materials element, labour element and petrol-oillubricant element
Variation in total cost of the project on an ad hoc basis
Rate of inflation
(a + m + b)/6
(a + 2m + b)/6
(a + 4m + b)/6
(a + 5m + b)/6
The various functions under each activity, are shown by one bar on Bar Charts
Bar chart establishes the interdependency of one event on another
Only approximate percentage of the completed work is reported
None of these
Resource levelling
Resource smoothening
Updating
Critical path scheduling
Small projects
Large and complex projects
Research and development projects
Deterministic activities
Positive
Negative
Zero
Same
Maximum float
Minimum float
Zero float
None of these
Emphasis is given to activities
Uncertainties are not allowed
Activities are represented by arrows
All the above
Event
Float
Duration
Constraint
The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
The difference between the maximum time available for the job and actual time it consumes, is called total float
The difference between the latest start time and earliest start time of an activity, is called total float
None of these
Resources
Project duration time
Both resources and project duration time
None of the above
Earliest expected time is denoted by TE
Latest occurrence time is denoted by TL
Contractual obligation time is denoted by Ts
All the above
3.7 years
4.23 years
5 years
7.87 years
Is an improvement upon bar chart method
Provides a realistic approach to daily problems
Avoids delays which are very common in bar charts
All the above
Most likely time
Optimistic time
Pessimistic time
Expected time