Concrete
Loose sand
Asphalt
Firm earth
B. Loose sand
Is artificially introduced
Is represented by a dotted line
Does not consume time
All the above
CPA (Critical Path Analysis)
CPP (Critical Path Plotted)
MCE (Minimum Cost Expenditure)
All the above
Forward pass is used for calculating earliest expected time
Backward pass is used for calculating the latest occurrence time
Maximum value of earliest expected time is used if there is more than one value of any event
All the above
Strict adherence to specifications
Separation of planning and design part
Each individual maintains functional efficiency
All the above
2.3% and 84.1%
97.7% and 84.1%
97.7 % and 15.9%
15.9% and 97.7%
The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
The difference between total float and free float, is called interfering float
All the above
Assistant Engineer
Executive Engineer
Superintending Engineer
Chief Engineer
20 kg/tonne
30 kg/tonne
40 kg/tonne
50 kg/tonne
2 kg/tonne
6 kg/tonne
9 kg/tonne
20 kg/tonne
Synthesising in concepts
Is built of activities oriented programme
Is based on time estimate
All the above
Total float and free float
Total float and independent float
Free float and independent float
None of the above
Smooth-wheeled rollers
Vibratory rollers
Sheep foot rollers
Tampers
(i), (ii) and (iv) are correct
(ii), (iii) and (iv) are correct
(i), (iii) and (iv) are correct
(i), (ii) and (iii) are correct
Event flow scheduling technique
Critical ratio scheduling
Slotting technique for scheduling
Short interval scheduling
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
All the above
4 days
6 days
10 days
16 days
Shows the interdependencies of various jobs
Depicts the delay of jobs, if any
Points outgoing ahead of schedule of jobs, if any
None of these
1-2 is 4
2-3 is 7
3-4 is 8
All the above
to + 3tm+ tp/3
to + 4tm+ tp/4
to + 4tm+ tp/5
to + 4tm+ tp/6
Interdependencies of activities
Project progress
Uncertainties
All of the above
Optimistic time
Pessimistic time
Most likely time
All the above
An engineer
An architect
An owner
All the above
Drag line
Hoe
Clam shell
Dipper shovel
Activity arrows in a CPM network are drawn to scale
The tail of an arrow represents the finish of an activity
Arrow bead represents the start of an activity
None of the above
Greater than earliest event time of the following node
Less than earliest event time of the following node
Less than or equal to earliest event time of the following node
Greater than or equal to earliest event time of the following node
8 days
9 days
10 days
15 days
Any project
Major projects
Minor projects
All the above
80 and 90
90 and 80
85 and 75
75 and 83
The difference of latest occurrence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above
Equal to X
More than X
Less than X
Any of the above