Home
Current Affairs January 2024

What is the correct answer?

4

Power stations are generally treated as

A. Light construction

B. Heavy construction

C. Industrial construction

D. Electrical construction

Correct Answer :

C. Industrial construction


Related Questions

What is the correct answer?

4

Total float for any activity is defined as the difference between

A. Its latest finish time and earliest start time for its successor activity

B. Its latest start time and earliest start time

C. Its latest start time and earliest finish time

D. Its earliest finish time and earliest start time for its successor activity

What is the correct answer?

4

Pick up the correct statement from the following:

A. The difference of latest occurrence time and earliest expected time, is called slack

B. The activities connecting the events having zero slack, lie on the critical path

C. The critical path consumes the maximum time

D. All the above

What is the correct answer?

4

For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

A. Moist loam

B. Good common earth

C. Well blasted rock

D. Wet sticky clay

What is the correct answer?

4

Critical path

A. Is always longest

B. Is always shortest

C. May be longest

D. May be shortest

What is the correct answer?

4

The main principle of an organisation, is

A. Unity of command

B. Effective control at all levels

C. Delegation of authority

D. All the above

What is the correct answer?

4

Consider the following statements: In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated. Of these statements

A. 1, 2 and 3 are correct

B. 1 and 4 are correct

C. 2, 3 and 4 are correct

D. 1, 2 and 4 are correct

What is the correct answer?

4

Preliminary project report for a road project must contain

A. The detailed estimated cost based on detailed design

B. The several alternatives of the project that have been considered

C. The soil survey, traffic survey, concept design and approximate cost

D. The contract documents for inviting tenders

What is the correct answer?

4

A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be

A. 3.7 years

B. 4.23 years

C. 5 years

D. 7.87 years

What is the correct answer?

4

For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

A. 1

B. 2

C. 3

D. 4

What is the correct answer?

4

If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

A. EF = ES + D

B. LS = LF - D

C. LF = LS + D

D. All the above

What is the correct answer?

4

Which of the following does not represent an activity?

A. Site located

B. Foundation is being dug

C. The office area is being cleaned

D. The invitations are being sent

What is the correct answer?

4

Interfering float is the difference between

A. Total float and free float

B. Total float and independent float

C. Free float and independent float

D. None of the above

What is the correct answer?

4

The time corresponding to minimum total project cost is

A. Crash time

B. Normal time

C. Optimistic time

D. Between normal time and crash time

What is the correct answer?

4

Free float for any activity is defined as the difference between

A. Its earliest finish time and earliest start time for its successor activity

B. Its latest start time and earliest start time

C. Its latest finish time and earliest start time for its successor activity

D. Its earliest finish time and latest start time for its successor activity

What is the correct answer?

4

The direct cost of a project with respect to normal time is

A. Minimum

B. Maximum

C. Zero

D. Infinite

What is the correct answer?

4

Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements

A. Only (i) is correct

B. (i) and (ii) are correct

C. (i) and (iii) are correct

D. (ii) and (iii) are correct

What is the correct answer?

4

Power stations are generally treated as

A. Light construction

B. Heavy construction

C. Industrial construction

D. Electrical construction

What is the correct answer?

4

The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is

A. 3425 kg

B. 5515 kg

C. 4350 kg

D. 2975 kg

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The activity is the time consuming part of a project

B. The beginning and end of a job, are called events

C. The activity which consumes maximum time, is called a node

D. Logically and sequentially connected activities and events form a network

What is the correct answer?

4

Sinking fund is

A. The fund for rebuilding a structure when its economic life is over

B. Raised to meet maintenance costs

C. The total sum to be paid to the municipal authorities by the tenants

D. A part of the money kept in reserve for providing additional structures and structural modifications

What is the correct answer?

4

If TL is the latest allowable event occurrence time, total activity slack(s), is equal to

A. LST-EST

B. LFT-EFT

C. TL-EFT

D. All the above

What is the correct answer?

4

Output of a bulldozer is
(i) Increased if drawbar HP of the tractor is increased for a given hauling distance
(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance
(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor
(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor
Of these statement

A. (i) and (iii) are correct

B. (i) and (iv) are correct

C. (ii) and (iii) are correct

D. (ii) and (iv) are correct

What is the correct answer?

4

The constraints in case of resource smoothening operation would be

A. Resources

B. Project duration time

C. Both resources and project duration time

D. None of the above

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All the Above

What is the correct answer?

4

The probability of completion of any activity within its expected time is

A. 50 %

B. 84.1 %

C. 99.9 %

D. 100 %

What is the correct answer?

4

If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

A. 3.5 and 5/6

B. 5 and 25/36

C. 3.5 and 25/36

D. 4 and 5/6

What is the correct answer?

4

During the construction period, price variation clause in contracts caters to

A. Increase in rates of only important materials

B. Variation in cost in materials element, labour element and petrol-oillubricant element

C. Variation in total cost of the project on an ad hoc basis

D. Rate of inflation

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity

B. The difference between the maximum time available for the job and actual time it consumes, is called total float

C. The difference between the latest start time and earliest start time of an activity, is called total float

D. None of these

What is the correct answer?

4

Pick up the correct statement from the following:

A. The float may be positive, zero or negative

B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed

C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

D. All the above

What is the correct answer?

4

Pre-tender stage requires

A. Acquisition of land

B. Selection of site

C. Fmalisation of alignment of work

D. All the above