While filling the tender for any work, the contractor considers

A. Site survey

B. Availability of construction materials

C. Availability of labour

D. All the above

Correct Answer :

D. All the above


Related Questions

What is the correct answer?

4

For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

A. 1

B. 2

C. 3

D. 4

What is the correct answer?

4

The most suitable type of equipment for compaction of cohesive soils is

A. Smooth-wheeled rollers

B. Vibratory rollers

C. Sheep foot rollers

D. Tampers

What is the correct answer?

4

The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

What is the correct answer?

4

The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively

A. 80 and 90

B. 90 and 80

C. 85 and 75

D. 75 and 83

What is the correct answer?

4

The technique for establishing and maintaining priorities among the various jobs of a project, is known

A. Event flow scheduling technique

B. Critical ratio scheduling

C. Slotting technique for scheduling

D. Short interval scheduling

What is the correct answer?

4

Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth, (iv) Output can be increased by increasing the size of shovel. Of these statements

A. (ii), (iii) and (iv) are correct

B. (i), (ii) and (iv) are correct

C. (i), (iii) and (iv) are correct

D. (i) and (iv) are correct

What is the correct answer?

4

Select the incorrect statement.

A. Start float and finish float are always equal.

B. Total float can be either start float or finish float.

C. Start float and finish float need not be equal.

D. Start float and finish float are the differences between activity times and not event times.

What is the correct answer?

4

The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be

A. Rs. 8,800

B. Rs. 7,600

C. Rs. 6,400

D. Rs. 5,000

What is the correct answer?

4

The main principle of an organisation, is

A. Unity of command

B. Effective control at all levels

C. Delegation of authority

D. All the above

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The various functions under each activity, are shown by one bar on Bar Charts

B. Bar chart establishes the interdependency of one event on another

C. Only approximate percentage of the completed work is reported

D. None of these

What is the correct answer?

4

A contractor has two options;
(I): Invest his money in project A or
(II): Invest his money in project B.
If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

A. Should invest in neither of the two projects

B. Could invest in either of the two projects

C. Should invest in project A

D. Should invest in project B

What is the correct answer?

4

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

A. to + 3tm+ tp/3

B. to + 4tm+ tp/4

C. to + 4tm+ tp/5

D. to + 4tm+ tp/6

What is the correct answer?

4

Critical path

A. Is always longest

B. Is always shortest

C. May be longest

D. May be shortest

What is the correct answer?

4

Which of the following earth moving machines has the shortest cycle time?

A. Drag line

B. Hoe

C. Clam shell

D. Dipper shovel

What is the correct answer?

4

If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is

A. 500 cum

B. 1000 cum

C. 1500 cum

D. 2000 cum

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. An activity of a project is denoted by an arrow on the net work

B. The tail of the arrow indicates the start of the activity

C. The head of the arrow indicates the end of the activity

D. The arrows are drawn to scale from left to right

What is the correct answer?

4

An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is

A. Rs. 8,43,750

B. Rs. 8,75,000

C. Rs. 10,50,000

D. Rs. 11,56,250

What is the correct answer?

4

The time with which direct cost does not reduce with the increase in time is known as

A. Crash time

B. Normal time

C. Optimistic time

D. Standard time

What is the correct answer?

4

Pick up the correct statement from the following:

A. Earliest expected time is denoted by TE

B. Latest occurrence time is denoted by TL

C. Contractual obligation time is denoted by Ts

D. All the above

What is the correct answer?

4

In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

A. Yes, because of heavier overheads and handling cost

B. Yes, because of the very high order of quality control for the factory made components

C. No, because of repetitive manufacture of a number of elements

D. No, because of savings in site labour

What is the correct answer?

4

Final technical authority of a project lies with

A. Assistant Engineer

B. Executive Engineer

C. Superintending Engineer

D. Chief Engineer

What is the correct answer?

4

Earliest finish of an activity is always

A. Greater than earliest event time of the following node

B. Less than earliest event time of the following node

C. Less than or equal to earliest event time of the following node

D. Greater than or equal to earliest event time of the following node

What is the correct answer?

4

Free float for any activity is defined as the difference between

A. Its earliest finish time and earliest start time for its successor activity

B. Its latest start time and earliest start time

C. Its latest finish time and earliest start time for its successor activity

D. Its earliest finish time and latest start time for its successor activity

What is the correct answer?

4

The time corresponding to minimum total project cost is

A. Crash time

B. Normal time

C. Optimistic time

D. Between normal time and crash time

What is the correct answer?

4

An event is indicated on the network by a number enclosed in

A. A circle

B. A square

C. A triangle

D. All the above

What is the correct answer?

4

Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing. Reason R: If the angle of swing is decreased, the cycle time will be decreased. Select the correct answer.

A. Both A and R is true and R is the correct explanation of A

B. Both A and R is true but R is not the correct explanation of A

C. A is true but R is false

D. A is false but R is true

What is the correct answer?

4

Sinking fund is

A. The fund for rebuilding a structure when its economic life is over

B. Raised to meet maintenance costs

C. The total sum to be paid to the municipal authorities by the tenants

D. A part of the money kept in reserve for providing additional structures and structural modifications

What is the correct answer?

4

In PERT analysis, the time estimates of activities and probability of their occurrence follow

A. Normal distribution curve

B. Poisson's distribution curve

C. Beta distribution curve

D. None of the above

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

Works costing less than Rs. 20,000 are treated as

A. Any project

B. Major projects

C. Minor projects

D. All the above