Related Questions
What is the correct answer?
4
Residential buildings are treated as
C. Industrial construction
What is the correct answer?
4
A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will
What is the correct answer?
4
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
B. Completed 5 days later
C. Performed at slower rate in 15 days
What is the correct answer?
4
Frequency distribution curves
A. Having a single lump, are called uninodal curves
B. If symmetrical, are called normal curves
C. If not symmetrical, are called skew curves
What is the correct answer?
4
For the execution of a project, a contractor is
What is the correct answer?
4
Consider the following statements: Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control. Of these statements
A. 1, 3 and 4 are correct
B. 2, 3 and 4 are correct
C. 1, 2 and 3 are correct
D. 1, 2 and 4 are correct
What is the correct answer?
4
Time and progress chart of a construction, is also known as
C. Modified Mile stone chart
What is the correct answer?
4
Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.
A. A is correct but R is not correct
B. R is correct but A is not correct
C. Both A and R is correct
D. Both A and R is incorrect
What is the correct answer?
4
Pick up the incorrect statement from the following:
A. The activity is the time consuming part of a project
B. The beginning and end of a job, are called events
C. The activity which consumes maximum time, is called a node
D. Logically and sequentially connected activities and events form a network
What is the correct answer?
4
Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
What is the correct answer?
4
Final technical authority of a project lies with
C. Superintending Engineer
What is the correct answer?
4
Critical path lies along the activities having total float
What is the correct answer?
4
Critical path
What is the correct answer?
4
Which of the following excavators is most suitable for digging under water?
What is the correct answer?
4
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
What is the correct answer?
4
Pick up the correct statement from the following:
A. Programme Evaluation and Review Technique, is event oriented
B. Programme Evaluation and Review Technique is not event oriented
C. Critical Path Method is event oriented
D. Critical Path method is event oriented
What is the correct answer?
4
A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
What is the correct answer?
4
Frederick W. Taylor introduced a system of working known as
B. Line and staff organisation
C. Functional organisation
D. Effective organisation
What is the correct answer?
4
For completion of a project, the critical path of the network represents
What is the correct answer?
4
Output of a bulldozer is
(i) Increased if drawbar HP of the tractor is increased for a given hauling distance
(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance
(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor
(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor
Of these statement
A. (i) and (iii) are correct
B. (i) and (iv) are correct
C. (ii) and (iii) are correct
D. (ii) and (iv) are correct
What is the correct answer?
4
A Milestone chart
A. Shows the interdependencies of various jobs
B. Depicts the delay of jobs, if any
C. Points outgoing ahead of schedule of jobs, if any
What is the correct answer?
4
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to
What is the correct answer?
4
Consider the following statements: In the critical path method of construction planning, Free Float can be.
1. Greater than Total Float.
2. Greater than Independent Float
3. Equal to Total Float.
4. Less than Independent Float. Of these statements
What is the correct answer?
4
The critical activity has
What is the correct answer?
4
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
What is the correct answer?
4
PERT analysis is based on
What is the correct answer?
4
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
What is the correct answer?
4
The first stage of a construction, is
A. Preparation of estimate
C. Initiation of proposal
What is the correct answer?
4
Select the incorrect statement.
A. Earliest start of an activity is the early event time of the node it leaves.
B. Latest finish of an activity is the late event time of the node it enters.
C. Latest start of an activity is its latest finish minus its duration.
What is the correct answer?
4
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as