Related Questions
What is the correct answer?
4
The main principle of an organisation, is
B. Effective control at all levels
C. Delegation of authority
What is the correct answer?
4
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
What is the correct answer?
4
Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing. Reason R: If the angle of swing is decreased, the cycle time will be decreased. Select the correct answer.
A. Both A and R is true and R is the correct explanation of A
B. Both A and R is true but R is not the correct explanation of A
C. A is true but R is false
D. A is false but R is true
What is the correct answer?
4
The critical activity has
What is the correct answer?
4
Economic saving of time results by crashing
A. Cheapest critical activity
B. Cheapest noncritical activity
C. Costliest critical activity
D. Costliest noncritical activity
What is the correct answer?
4
Time and progress chart of a construction, is also known as
C. Modified Mile stone chart
What is the correct answer?
4
A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is
What is the correct answer?
4
The object of technical planning, is
A. Preparation of specifications
B. Preparation of estimates
C. Initiating the procurement action of resources
What is the correct answer?
4
The Overall in-charge of an organisation at the site responsible for the execution of the works, is
What is the correct answer?
4
Critical path method
A. Is an improvement upon bar chart method
B. Provides a realistic approach to daily problems
C. Avoids delays which are very common in bar charts
What is the correct answer?
4
Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.
A. A is correct but R is not correct
B. R is correct but A is not correct
C. Both A and R is correct
D. Both A and R is incorrect
What is the correct answer?
4
Completion of an activity on CPM network diagram, is generally known
What is the correct answer?
4
While filling the tender for any work, the contractor considers
B. Availability of construction materials
C. Availability of labour
What is the correct answer?
4
Frederick W. Taylor introduced a system of working known as
B. Line and staff organisation
C. Functional organisation
D. Effective organisation
What is the correct answer?
4
Henry Gantt developed Bar charts for planning and scheduling of projects in
What is the correct answer?
4
The final selection of a construction site, is done by
A. Departmental representative or user
B. Local civil authority representative
C. Representative of engineer authority
What is the correct answer?
4
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?
A. Yes, because of heavier overheads and handling cost
B. Yes, because of the very high order of quality control for the factory made components
C. No, because of repetitive manufacture of a number of elements
D. No, because of savings in site labour
What is the correct answer?
4
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
What is the correct answer?
4
The difference between the time avail-to do a job and the time required to do the job, is known as
What is the correct answer?
4
A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
What is the correct answer?
4
Construction team means
What is the correct answer?
4
The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is
What is the correct answer?
4
If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is
What is the correct answer?
4
Frequency distribution curves
A. Having a single lump, are called uninodal curves
B. If symmetrical, are called normal curves
C. If not symmetrical, are called skew curves
What is the correct answer?
4
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
What is the correct answer?
4
Works costing less than Rs. 20,000 are treated as
What is the correct answer?
4
Mile Stone charts were invented in the year of
What is the correct answer?
4
Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of project PERT is preferred for planning because of
What is the correct answer?
4
If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be
What is the correct answer?
4
Interfering float is the difference between
A. Total float and free float
B. Total float and independent float
C. Free float and independent float